17813 W PRAIRIE ST 91325
Certificate Information: 17813 W PRAIRIE ST 91325
- Application / Permit
- 20010-20000-03983
- Plan Check / Job No.
- B20VN13984
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30' X 29' ACCESSORY DWELLING UNIT WITH ATTACHED 14'-6" X 5' ENTRY PORCH PER GOV STATE CODE 65852.2(e)(1)(B). WORK DONE PER WFPP.
- Permit Issued
- Issued on 6/18/2021
- Issuing Office
- Current Status
- CofO Issued on 2/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 11/6/2020 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 2/19/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 5/4/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 6/11/2021 | ROSENDO MEDINA |
| Plan Check Approved | 6/14/2021 | ROSENDO MEDINA |
| Issued | 6/18/2021 | APPLICANT |
| Building Plans Picked Up | 6/22/2021 | APPLICANT |
| CofO in Progress | 1/27/2022 | RAUL OLAGI |
| Permit Finaled | 2/5/2022 | MICHAEL SMITH |
| CofO Issued | 2/5/2022 | MICHAEL SMITH |
| Permit Finaled | 2/5/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/30/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/30/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 1/27/2021 | JEREMY CARTER |
| Low Impact Development | Cleared | 3/16/2021 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 3/18/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 4/22/2021 | OSCAR CASTRO |
| Construction within easement | Cleared | 4/22/2021 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/29/2021 | Partial Inspection | MARK JOHNSON |
| PLUMBING-Rough | 7/7/2021 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 7/9/2021 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 7/19/2021 | Corrections Issued | MARK JOHNSON |
| Green Building Rough | 7/19/2021 | Not Ready for Inspection | MARK JOHNSON |
| Sewer | 7/19/2021 | Approved | MARK JOHNSON |
| Verify Sprinkler Sign Off | 7/19/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 8/4/2021 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/4/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 8/4/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/4/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/20/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 8/20/2021 | Approved | MARK JOHNSON |
| Insulation | 8/25/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 8/25/2021 | Approved | MARK JOHNSON |
| Drywall Nailing | 8/30/2021 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 9/8/2021 | Partial Approval | ADAM ESCOTO |
| Shower Pan | 9/8/2021 | Approved | ADAM ESCOTO |
| Pre-Inspection | 10/5/2021 | Partial Inspection | MARK JOHNSON |
| Final | 11/9/2021 | Corrections Issued | MARK JOHNSON |
| Green Building Final | 11/9/2021 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 11/9/2021 | SGSOV Not Ready | MARK JOHNSON |
| Service/Power Release | 11/9/2021 | Not Required | MARK JOHNSON |
| Smoke Detectors | 11/9/2021 | Not Ready for Inspection | MARK JOHNSON |
| Final | 1/14/2022 | No Access for Inspection | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 1/14/2022 | SGSOV Not Ready | MARK JOHNSON |
| Smoke Detectors | 1/14/2022 | No Access for Inspection | MARK JOHNSON |
| Final | 1/18/2022 | Corrections Issued | MARK JOHNSON |
| Final | 1/20/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 1/20/2022 | Approved | RAUL OLAGI |
| Gas Test | 1/24/2022 | Approved | RAUL OLAGI |
| Final | 1/26/2022 | OK to Issue CofO | RAUL OLAGI |