1741 W 81ST ST 90047
Certificate Information: 1741 W 81ST ST 90047
- Application / Permit
- 20010-20000-03982
- Plan Check / Job No.
- B20VN13981
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- (N) DETACHED GARAGE W/ RECREATION ROOM ABOVE (15'-7" X 24'-1")
- Permit Issued
- Issued on 9/23/2021
- Issuing Office
- Current Status
- CofO Issued on 10/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 12/1/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 12/1/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 12/7/2020 | APPLICANT |
| Plan Check Approved | 6/18/2021 | NILOOFAR MEHRAIN |
| Issued | 9/23/2021 | APPLICANT |
| CofO in Progress | 9/29/2022 | ENRIQUE MIRELES |
| Permit Finaled | 10/12/2022 | DEROLD HAUFF |
| CofO Issued | 10/12/2022 | DEROLD HAUFF |
| Permit Finaled | 10/12/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2021 | CELINA MORENO |
| Sewer availability | Cleared | 2/25/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 3/25/2021 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 4/17/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/17/2021 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 6/2/2021 | ROSA SILVA |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | Asap New Renovations Inc; Lic. No.: 1018950-B | 17950 TIARA STREET ENCINO, CA 91316 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/1/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/18/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2021 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 11/9/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 11/9/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 11/9/2021 | Corrections Issued | FREDDIE RIVERA |
| Wood Frame | 11/9/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 11/17/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 11/17/2021 | Approved | FREDDIE RIVERA |
| Insulation | 11/17/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/17/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 11/29/2021 | Approved | ADAM ESCOTO |
| BUILDING-Rough-Frame | 1/13/2022 | Approved | FREDDIE RIVERA |
| Final | 1/13/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 1/13/2022 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/13/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 1/13/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Smoke Detectors | 1/13/2022 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 1/13/2022 | Approved | FREDDIE RIVERA |
| Final | 2/28/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/28/2022 | SGSOV No Gas | FREDDIE RIVERA |
| Service/Power Release | 2/28/2022 | Not Required | FREDDIE RIVERA |
| Final | 9/7/2022 | OK to Issue CofO | ENRIQUE MIRELES |