4440 N LEDGE AVE 91602

Certificate Information: 4440 N LEDGE AVE 91602

Application / Permit
20010-20000-03931
Plan Check / Job No.
B20VN13829
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE STORY SINGLE FAMILY DWELLING EXCEPT FOR 5' LF AT NORTH SIDE AND BUILD AN IRREGULAR SHAPED 66'3" X 44' TWO STORY SINGLE FAMILY DWELLING WITH AN ATTACHED TWO CAR GARAGE AND WITH NEW 10'-9" X 21'-6" ATTACHED TRELLIS, NFPA-13D FIRE SPRINKLERS THROUGHOUT REQUIRED, ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/27/2021
Issuing Office
Current Status
CofO Issued on 6/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2020 APPLICANT
Assigned to Plan Check Engineer 11/19/2020 CHON CHIO KUO
Corrections Issued 11/23/2020 CHON CHIO KUO
Quality Review Completed 12/2/2020 STEVEN KIM
Building Plans Picked Up 12/9/2020 APPLICANT
Applicant returned to address corrections 8/4/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 8/25/2021 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 9/21/2021 SEWADA ZADOORAN MILAGARDI
Issued 9/27/2021 APPLICANT
CofO in Progress 9/28/2023 JACK KARGODORIAN
Permit Finaled 6/25/2024 RUBEN SALAS
CofO Issued 6/25/2024 RUBEN SALAS
Permit Finaled 6/25/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/11/2021 JOHN TRIANTAFYLLOS
Permit Cleared 1/11/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/11/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 2/12/2021 MATTHEW CRAIG
Low Impact Development Cleared 5/11/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 5/13/2021 ADRIAN CASTRO
ZI Cleared 8/2/2021 MIGUEL GAMBOA
Green Code Cleared 9/21/2021 CHON CHIO KUO

Contact Information

Contractor Owner-Builder       ,
Engineer Tan,, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/14/2021 Approved MICHAEL PELHAM
Deputy Reinf. Concrete 10/18/2021 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 10/18/2021 Corrections Issued THOMAS FINNILA
Deputy Reinf. Concrete 10/20/2021 Approved THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 10/20/2021 Corrections Issued THOMAS FINNILA
Deputy Reinf. Concrete 10/27/2021 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 10/27/2021 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 10/28/2021 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 11/12/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 11/29/2021 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Conditional Approval THOMAS FINNILA
Deputy Steel/Welding 12/17/2021 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/5/2022 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 2/2/2022 Approved THOMAS FINNILA
Deputy Wood Construction 5/2/2022 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/2/2022 Partial Approval THOMAS FINNILA
HVAC-Rough 5/2/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/2/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 5/19/2022 Approved THOMAS FINNILA
PLUMBING-Rough 5/19/2022 Approved THOMAS FINNILA
BUILDING-Rough-Frame 6/23/2022 Partial Approval ROBERT GOLD
HVAC-Rough 6/23/2022 Partial Approval ROBERT GOLD
Interior/Exterior Lathing 6/23/2022 Not Ready for Inspection ROBERT GOLD
Insulation 7/5/2022 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 7/13/2022 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 7/13/2022 Approved THOMAS FINNILA
HVAC-Rough 7/13/2022 Approved THOMAS FINNILA
Insulation 7/13/2022 Not Ready for Inspection THOMAS FINNILA
Shower Pan 7/25/2022 Conditional Approval THOMAS FINNILA
Interior/Exterior Lathing 8/4/2022 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 8/15/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 8/15/2022 Partial Approval GREGG CUMMINGS
Shower Pan 8/15/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 8/19/2022 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 8/25/2022 Approved CALEB MEISTER
Gas Test 11/30/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Service/Power Release 3/9/2023 Corrections Issued JACK KARGODORIAN
Gas Test 3/13/2023 Not Ready for Inspection JACK KARGODORIAN
Gas Test 3/29/2023 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Final 4/3/2023 Approved JACK KARGODORIAN
HVAC-Final 5/8/2023 Approved JACK KARGODORIAN
HVAC-Final 5/19/2023 Approved JACK KARGODORIAN
Gas Test 9/8/2023 Approved JUAN VALENZUELA
Pre-Inspection 9/8/2023 Partial Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 9/28/2023 Approved JACK KARGODORIAN
Final 9/28/2023 OK to Issue CofO JACK KARGODORIAN
Green Building Final 9/28/2023 Approved JACK KARGODORIAN
MERV13>=Final 9/28/2023 Approved JACK KARGODORIAN
MERV13>=Rough 9/28/2023 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/28/2023 SGSOV Approved JACK KARGODORIAN
Service/Power Release 9/28/2023 Approved JACK KARGODORIAN
Smoke Detectors 9/28/2023 Approved JACK KARGODORIAN