6082 N CALVIN AVE 91356

Certificate Information: 6082 N CALVIN AVE 91356

Application / Permit
20010-20000-03887
Plan Check / Job No.
B20VN13762
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30'-0" x 40'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 4/27/2021
Issuing Office
Current Status
CofO Issued on 8/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 SARKIS HARABEDIAN
Corrections Issued 10/24/2020 SARKIS HARABEDIAN
Quality Review Completed 10/27/2020 STEVEN KIM
Building Plans Picked Up 10/28/2020 APPLICANT
Applicant returned to address corrections 1/5/2021 SARKIS HARABEDIAN
Plan Check Approved 4/26/2021 SARKIS HARABEDIAN
Issued 4/27/2021 APPLICANT
CofO in Progress 7/27/2022 SEAN HAUPT
Permit Finaled 8/27/2022 MICHAEL SMITH
CofO Issued 8/27/2022 MICHAEL SMITH
Permit Finaled 8/27/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/12/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/12/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/12/2021 JOHN TRIANTAFYLLOS
Metro Rail approval Cleared 1/14/2021 SARKIS HARABEDIAN
Hydrant and Access approval Cleared 2/22/2021 KURT CORRAL
Low Impact Development Cleared 4/12/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 4/14/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/6/2021 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 7/12/2021 Partial Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 7/28/2021 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 8/4/2021 Approved STEVEN BACK
Pre-Inspection 10/4/2021 Partial Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Not Ready for Inspection SEAN HAUPT
Deputy Drilled-In Anchors 10/18/2021 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 10/26/2021 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Approved SEAN HAUPT
Interior/Exterior Lathing 11/2/2021 Approved SEAN HAUPT
Insulation 11/10/2021 Approved SEAN HAUPT
Insulation 11/12/2021 Not Ready for Inspection SEAN HAUPT
Drywall Nailing 11/16/2021 Approved DAVID SCANTLIN
Green Building Rough 11/16/2021 Approved DAVID SCANTLIN
Shower Pan 12/3/2021 Approved SEAN HAUPT
Underground Mechanical 1/19/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 3/4/2022 Approved SEAN HAUPT
ELECTRICAL-Final 3/4/2022 Approved SEAN HAUPT
Final 3/4/2022 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 3/4/2022 Approved SEAN HAUPT
Green Building Final 3/4/2022 Approved SEAN HAUPT
HVAC-Final 3/4/2022 Approved SEAN HAUPT
PLUMBING-Final 3/4/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 3/4/2022 SGSOV Approved SEAN HAUPT
Service/Power Release 3/4/2022 Approved SEAN HAUPT
Smoke Detectors 3/4/2022 Approved SEAN HAUPT
Verify Sprinkler Sign Off 3/4/2022 Approved SEAN HAUPT
Final 7/26/2022 OK to Issue CofO SEAN HAUPT