5642 N TILDEN AVE 91401
Certificate Information: 5642 N TILDEN AVE 91401
- Application / Permit
- 20010-20000-03861
- Plan Check / Job No.
- B20VN13711
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30'-10" X 24'-8" , 2-STORY ACCESSORY DWELLING UNIT WITH ROOF TOP DECK PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/27/2021
- Issuing Office
- Current Status
- CofO Issued on 5/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | PARISA ZAHABI |
| Corrections Issued | 10/24/2020 | PARISA ZAHABI |
| Quality Review Completed | 10/29/2020 | OMID HEDAYAT |
| Applicant returned to address corrections | 3/17/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 5/3/2021 | PARISA ZAHABI |
| Plan Check Approved | 5/27/2021 | PARISA ZAHABI |
| Issued | 5/27/2021 | APPLICANT |
| Building Plans Picked Up | 6/1/2021 | APPLICANT |
| CofO in Progress | 4/19/2022 | RICHARD DOCKUS |
| CofO Issued | 5/14/2022 | MICHAEL SMITH |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/13/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 3/4/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/26/2021 | GABRIEL ROBLES |
| Green Code | Cleared | 5/27/2021 | PARISA ZAHABI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 2310 W MAGNOLIA BLVD STE A BURBANK, CA 91506 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 6/17/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 8/2/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/2/2021 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 8/6/2021 | Partial Approval | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2021 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2021 | Corrections Issued | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2021 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2021 | Corrections Issued | RICHARD DOCKUS |
| Deputy Wood Construction | 8/26/2021 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2021 | Partial Approval | RICHARD DOCKUS |
| PLUMBING-Rough | 9/8/2021 | Approved | RICHARD DOCKUS |
| Shower Pan | 9/8/2021 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2021 | Partial Inspection | MISAEL ESPARZA |
| HVAC-Rough | 9/10/2021 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/13/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 9/20/2021 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2021 | Approved | RICHARD DOCKUS |
| Green Building Rough | 9/20/2021 | Approved | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 9/20/2021 | Approved | RICHARD DOCKUS |
| Wood Frame | 9/20/2021 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/29/2021 | Partial Approval | JENNIFER RABUCHIN |
| Special/Order Compliance | 9/29/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/4/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/13/2021 | Approved | ALAN MORELOS |
| Drywall Nailing | 10/14/2021 | Approved | ALAN MORELOS |
| Insulation | 11/29/2021 | Approved | ALAN MORELOS |
| Underground Mechanical | 11/29/2021 | Approved | ALAN MORELOS |
| Service/Power Release | 12/3/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/11/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 2/11/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 2/11/2022 | Approved | RICHARD DOCKUS |
| Green Building Final | 2/11/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 2/11/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Final | 2/11/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 2/11/2022 | SGSOV Approved | RICHARD DOCKUS |
| Service/Power Release | 2/11/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Smoke Detectors | 2/11/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 2/18/2022 | Approved | RICHARD DOCKUS |
| Pre-Inspection | 2/18/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 3/15/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Final | 3/15/2022 | Corrections Issued | MICHAEL TEMPLE |
| Final | 3/15/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Service/Power Release | 3/15/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Final | 4/5/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Service/Power Release | 4/5/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 4/14/2022 | Corrections Issued | RICHARD DOCKUS |
| Service/Power Release | 4/14/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Drywall Nailing | 4/18/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 4/18/2022 | Approved | RICHARD DOCKUS |
| Final | 4/18/2022 | OK to Issue CofO | RICHARD DOCKUS |
| Gas Test | 4/18/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 4/18/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 4/18/2022 | Approved | RICHARD DOCKUS |
| Service/Power Release | 4/18/2022 | Not Required | RICHARD DOCKUS |
| Verify Rec and Parks Fee Memo | 4/18/2022 | Approved | RICHARD DOCKUS |