5642 N TILDEN AVE 91401

Certificate Information: 5642 N TILDEN AVE 91401

Application / Permit
20010-20000-03861
Plan Check / Job No.
B20VN13711
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30'-10" X 24'-8" , 2-STORY ACCESSORY DWELLING UNIT WITH ROOF TOP DECK PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/27/2021
Issuing Office
Current Status
CofO Issued on 5/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 PARISA ZAHABI
Corrections Issued 10/24/2020 PARISA ZAHABI
Quality Review Completed 10/29/2020 OMID HEDAYAT
Applicant returned to address corrections 3/17/2021 PARISA ZAHABI
Applicant returned to address corrections 5/3/2021 PARISA ZAHABI
Plan Check Approved 5/27/2021 PARISA ZAHABI
Issued 5/27/2021 APPLICANT
Building Plans Picked Up 6/1/2021 APPLICANT
CofO in Progress 4/19/2022 RICHARD DOCKUS
CofO Issued 5/14/2022 MICHAEL SMITH
Permit Finaled 5/14/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/13/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/13/2020 ADRIAN CASTRO
Sewer availability Cleared 11/13/2020 ADRIAN CASTRO
Low Impact Development Cleared 3/4/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/26/2021 GABRIEL ROBLES
Green Code Cleared 5/27/2021 PARISA ZAHABI

Contact Information

Contractor Owner-Builder       ,
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 2310 W MAGNOLIA BLVD STE A      BURBANK, CA 91506

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/8/2021 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 6/17/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 8/2/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/2/2021 Partial Approval JENNIFER RABUCHIN
Insulation 8/6/2021 Partial Approval RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 8/9/2021 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/16/2021 Corrections Issued RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 8/17/2021 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 8/24/2021 Corrections Issued RICHARD DOCKUS
Deputy Wood Construction 8/26/2021 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 9/8/2021 Approved RICHARD DOCKUS
Shower Pan 9/8/2021 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 9/10/2021 Partial Inspection MISAEL ESPARZA
HVAC-Rough 9/10/2021 Approved RICHARD DOCKUS
ELECTRICAL-Rough 9/13/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 9/20/2021 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 9/20/2021 Approved RICHARD DOCKUS
Green Building Rough 9/20/2021 Approved RICHARD DOCKUS
Verify Sprinkler Sign Off 9/20/2021 Approved RICHARD DOCKUS
Wood Frame 9/20/2021 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 9/29/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 9/29/2021 Partial Approval JENNIFER RABUCHIN
Special/Order Compliance 9/29/2021 Approved JENNIFER RABUCHIN
Insulation 10/4/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/13/2021 Approved ALAN MORELOS
Drywall Nailing 10/14/2021 Approved ALAN MORELOS
Insulation 11/29/2021 Approved ALAN MORELOS
Underground Mechanical 11/29/2021 Approved ALAN MORELOS
Service/Power Release 12/3/2021 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 2/11/2022 Not Ready for Inspection RICHARD DOCKUS
Final 2/11/2022 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 2/11/2022 Approved RICHARD DOCKUS
Green Building Final 2/11/2022 Approved RICHARD DOCKUS
HVAC-Final 2/11/2022 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Final 2/11/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Approved RICHARD DOCKUS
Service/Power Release 2/11/2022 Not Ready for Inspection RICHARD DOCKUS
Smoke Detectors 2/11/2022 Approved RICHARD DOCKUS
HVAC-Final 2/18/2022 Approved RICHARD DOCKUS
Pre-Inspection 2/18/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 3/15/2022 Not Ready for Inspection MICHAEL TEMPLE
Final 3/15/2022 Corrections Issued MICHAEL TEMPLE
Final 3/15/2022 Not Ready for Inspection MICHAEL TEMPLE
Service/Power Release 3/15/2022 Not Ready for Inspection MICHAEL TEMPLE
Final 4/5/2022 Not Ready for Inspection RICHARD DOCKUS
Service/Power Release 4/5/2022 Not Ready for Inspection RICHARD DOCKUS
Final 4/14/2022 Corrections Issued RICHARD DOCKUS
Service/Power Release 4/14/2022 Not Ready for Inspection RICHARD DOCKUS
Drywall Nailing 4/18/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 4/18/2022 Approved RICHARD DOCKUS
Final 4/18/2022 OK to Issue CofO RICHARD DOCKUS
Gas Test 4/18/2022 Approved RICHARD DOCKUS
HVAC-Final 4/18/2022 Approved RICHARD DOCKUS
PLUMBING-Final 4/18/2022 Approved RICHARD DOCKUS
Service/Power Release 4/18/2022 Not Required RICHARD DOCKUS
Verify Rec and Parks Fee Memo 4/18/2022 Approved RICHARD DOCKUS