12216 W HART ST 91605
Certificate Information: 12216 W HART ST 91605
- Application / Permit
- 20010-20000-03852
- Plan Check / Job No.
- B20VN13676
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ONE STORY 48' X 25' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/12/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 11/23/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 12/1/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 12/1/2020 | APPLICANT |
| Plan Check Approved | 3/8/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 4/12/2021 | APPLICANT |
| CofO in Progress | 12/1/2022 | ROBERT GOLD |
| CofO Issued | 12/1/2022 | RONALD MYRICK |
| Permit Finaled | 12/1/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/10/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 12/14/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 2/25/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 2/25/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Morales,, Carlos A; Lic. No.: C69972 | 38100 SAN MATEO AVE PALMDALE, CA 93551 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/19/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Gas Test | 7/19/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 7/19/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 8/2/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 8/6/2021 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/9/2021 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 9/9/2021 | Approved | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 9/9/2021 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 9/9/2021 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 9/9/2021 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 9/13/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 9/13/2021 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 9/17/2021 | Conditional Approval | DAVID MATSON |
| Drywall Nailing | 9/23/2021 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 9/23/2021 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 10/1/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 3/23/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 3/23/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 3/23/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 3/23/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 3/23/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/22/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 4/22/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 7/12/2022 | Corrections Issued | RAFAEL CORTES |
| Green Building Final | 7/12/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Service/Power Release | 7/12/2022 | Corrections Issued | RAFAEL CORTES |
| Final | 8/9/2022 | Corrections Issued | RAFAEL CORTES |
| Green Building Final | 8/9/2022 | Approved | RAFAEL CORTES |
| Service/Power Release | 8/9/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 8/16/2022 | Corrections Issued | RAFAEL CORTES |
| Service/Power Release | 8/16/2022 | Approved | RAFAEL CORTES |
| Final | 11/14/2022 | Corrections Issued | CALEB MEISTER |
| Final | 12/1/2022 | OK to Issue CofO | ROBERT GOLD |