11822 W VOSE ST 91605
Certificate Information: 11822 W VOSE ST 91605
- Application / Permit
- 20010-20000-03850
- Plan Check / Job No.
- B20VN13669
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- (N) 2-STORY TYPE I-A WAREHOUSE/PARKING/OFFICE BUILDING (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 6/29/2022
- Issuing Office
- Current Status
- CofO Issued on 4/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/19/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 11/19/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 11/23/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 11/23/2020 | APPLICANT |
| Green Plans Picked Up | 11/23/2020 | APPLICANT |
| Applicant returned to address corrections | 1/4/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/22/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 5/6/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 6/14/2022 | NILOOFAR MEHRAIN |
| Issued | 6/29/2022 | APPLICANT |
| CofO in Progress | 3/28/2025 | JOHN KITCKO |
| CofO Issued | 4/22/2025 | RICKEY JACKSON |
| Permit Finaled | 4/22/2025 | RICKEY JACKSON |
Permit Application Clearance Information
| Highway dedication | Cleared | 12/10/2020 | GABRIEL ROBLES |
| Address approval | Cleared | 1/7/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 4/21/2021 | MATTHEW CRAIG |
| Green Code | Cleared | 6/11/2021 | MICHAEL AYERS |
| Permit | Cleared | 11/15/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/15/2021 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 11/23/2021 | ADALBERTO VERA |
| Low Impact Development | Cleared | 3/25/2022 | AMMAR ELTAWIL |
| DAS Clearance | Cleared | 5/19/2022 | NILOOFAR MEHRAIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/29/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/6/2023 | Corrections Issued | JOHN KITCKO |
| Grading Pre-Inspection | 6/12/2023 | Corrections Issued | ROBERT DAVIS |
| Footing/Foundation/Slab | 8/25/2023 | Partial Approval | JOHN KITCKO |
| Deputy Drilled-In Anchors | 9/14/2023 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 10/10/2023 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 10/10/2023 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 10/11/2023 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 10/12/2023 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 10/13/2023 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 10/17/2023 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 10/18/2023 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 10/20/2023 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 10/23/2023 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 11/1/2023 | Approved | JOHN KITCKO |
| Deputy Reinf. Concrete | 11/6/2023 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 11/7/2023 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 11/8/2023 | Conditional Approval | JEFFREY DURAN |
| Masonry Wall/Backfill | 11/22/2023 | Partial Approval | CAMERON CHABAN |
| Masonry Wall/Backfill | 11/28/2023 | Partial Approval | JOHN KITCKO |
| Deputy Drilled-In Anchors | 11/30/2023 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 12/1/2023 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 12/5/2023 | Partial Inspection | ANDREW DORSO |
| Pre-Inspection | 12/6/2023 | Partial Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 12/12/2023 | Conditional Approval | JOHN KITCKO |
| Masonry Wall/Backfill | 12/13/2023 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 12/26/2023 | Approved | JOHN KITCKO |
| Masonry Wall/Backfill | 12/28/2023 | Not Ready for Inspection | JOHN KITCKO |
| Masonry Wall/Backfill | 12/29/2023 | Partial Approval | JOHN KITCKO |
| Masonry Wall/Backfill | 1/11/2024 | Partial Approval | JOHN KITCKO |
| Special/Order Compliance | 1/11/2024 | Partial Inspection | BRIAN KELLY |
| Masonry Wall/Backfill | 1/19/2024 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 1/23/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 1/29/2024 | Conditional Approval | JOHN KITCKO |
| Masonry Wall/Backfill | 2/7/2024 | Not Ready for Inspection | JOHN KITCKO |
| Masonry Wall/Backfill | 2/8/2024 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 2/13/2024 | Approved | JOHN KITCKO |
| Masonry Wall/Backfill | 2/13/2024 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 2/29/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/1/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/4/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 3/11/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 3/12/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/13/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/14/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 3/15/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/18/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/19/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/20/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 3/21/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/22/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/28/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/29/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/1/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 4/2/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 4/3/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/4/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 4/5/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/8/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 4/9/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 4/10/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/11/2024 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 5/1/2024 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 5/6/2024 | Not Ready for Inspection | JOHN KITCKO |
| Structural Steel Frame | 5/6/2024 | Partial Inspection | JOHN KITCKO |
| Verify Sprinkler Sign Off | 5/6/2024 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Steel/Welding | 5/8/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 5/16/2024 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 5/16/2024 | Partial Approval | JOHN KITCKO |
| Deputy Drilled-In Anchors | 5/31/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 6/5/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/6/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/7/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/10/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 6/11/2024 | Conditional Approval | JOHN KITCKO |
| Wood Frame | 6/25/2024 | Corrections Issued | JOHN KITCKO |
| Wood Frame | 7/2/2024 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 7/8/2024 | Conditional Approval | ROBERT DAVIS |
| Wood Frame | 7/17/2024 | Conditional Approval | JOHN KITCKO |
| Reinforced Masonry Frame | 7/23/2024 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 7/31/2024 | Not Ready for Inspection | GREGORY POMISH |
| Reinforced Concrete Frame | 7/31/2024 | Corrections Issued | GREGORY POMISH |
| Verify Sprinkler Sign Off | 7/31/2024 | Not Ready for Inspection | GREGORY POMISH |
| Deputy Steel/Welding | 8/7/2024 | Conditional Approval | CAMERON CHABAN |
| Green Building Rough | 8/16/2024 | Not Ready for Inspection | JOHN KITCKO |
| Reinforced Concrete Frame | 8/16/2024 | Partial Approval | JOHN KITCKO |
| Verify Sprinkler Sign Off | 8/16/2024 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 10/8/2024 | Approved | JOHN KITCKO |
| Final | 3/18/2025 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 3/18/2025 | Approved | JOHN KITCKO |
| Green Building Final | 3/18/2025 | Approved | JOHN KITCKO |
| Green Building Rough | 3/18/2025 | Approved | JOHN KITCKO |
| Reinforced Concrete Frame | 3/18/2025 | Approved | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 3/18/2025 | SGSOV No Gas | JOHN KITCKO |
| Smoke Detectors | 3/18/2025 | Approved | JOHN KITCKO |
| Structural Steel Frame | 3/18/2025 | Approved | JOHN KITCKO |
| Verify Sprinkler Sign Off | 3/18/2025 | Approved | JOHN KITCKO |
| Final | 3/20/2025 | Partial Inspection | JOHN KITCKO |
| Final | 3/28/2025 | OK to Issue CofO | JOHN KITCKO |