7018 N JELLICO AVE 91406

Certificate Information: 7018 N JELLICO AVE 91406

Application / Permit
20010-20000-03832
Plan Check / Job No.
B20VN13637
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d)(g) & WFPP
Permit Issued
Issued on 6/8/2021
Issuing Office
Current Status
CofO Issued on 3/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 NILOOFAR MEHRAIN
Corrections Issued 11/4/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 11/6/2020 APPLICANT
Plan Check Approved 5/20/2021 NILOOFAR MEHRAIN
Issued 6/8/2021 APPLICANT
CofO in Progress 3/2/2022 SEAN HAUPT
Permit Finaled 3/6/2022 MICHAEL SMITH
CofO Issued 3/6/2022 MICHAEL SMITH
Permit Finaled 3/6/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/19/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 11/19/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/19/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/19/2021 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 3/18/2021 RIDWAN HARDY
Construction within easement Cleared 3/18/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 5/13/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/9/2021 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 9/21/2021 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 10/15/2021 Corrections Issued SEAN HAUPT
Excavation/Setback/Form/Re-Bar 10/21/2021 Approved SEAN HAUPT
BUILDING-Rough-Frame 10/29/2021 Not Ready for Inspection SEAN HAUPT
Green Building Rough 10/29/2021 Not Ready for Inspection SEAN HAUPT
Insulation 10/29/2021 Not Ready for Inspection SEAN HAUPT
Underground Mechanical 10/29/2021 Approved SEAN HAUPT
Verify Sprinkler Sign Off 10/29/2021 Not Ready for Inspection SEAN HAUPT
Wood Frame 10/29/2021 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 11/4/2021 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 11/30/2021 Approved SEAN HAUPT
BUILDING-Rough-Frame 12/7/2021 Approved SEAN HAUPT
ELECTRICAL-Rough 12/7/2021 Approved SEAN HAUPT
Green Building Rough 12/7/2021 Approved SEAN HAUPT
HVAC-Rough 12/7/2021 Approved SEAN HAUPT
Interior/Exterior Lathing 12/7/2021 Approved SEAN HAUPT
PLUMBING-Rough 12/7/2021 Approved SEAN HAUPT
Rough-Elec/Plmb/HVAC 12/7/2021 Approved SEAN HAUPT
Verify Sprinkler Sign Off 12/7/2021 Approved SEAN HAUPT
BUILDING-Rough-Frame 12/14/2021 Approved SEAN HAUPT
Insulation 12/14/2021 Approved SEAN HAUPT
Interior/Exterior Lathing 12/14/2021 Approved SEAN HAUPT
Shower Pan 12/14/2021 Approved SEAN HAUPT
Drywall Nailing 12/20/2021 Approved SEAN HAUPT
ELECTRICAL-Final 2/22/2022 Corrections Issued SEAN HAUPT
Final 2/22/2022 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 2/22/2022 Approved SEAN HAUPT
Green Building Final 2/22/2022 Approved SEAN HAUPT
HVAC-Final 2/22/2022 Approved SEAN HAUPT
PLUMBING-Final 2/22/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 2/22/2022 SGSOV Approved SEAN HAUPT
Service/Power Release 2/22/2022 Approved SEAN HAUPT
Smoke Detectors 2/22/2022 Approved SEAN HAUPT
ELECTRICAL-Final 3/2/2022 Approved SEAN HAUPT
Final 3/2/2022 OK to Issue CofO SEAN HAUPT