8627 N LASAINE AVE 91325

Certificate Information: 8627 N LASAINE AVE 91325

Application / Permit
20010-20000-03828
Plan Check / Job No.
B20VN13632
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW DETACHED 24' X 26' RECREATION ROOM. ALL WORK DONE PER WFPP. NFPA 13D FIRE SPRINKERS TO BE PROVIDED.
Permit Issued
Issued on 1/28/2022
Issuing Office
Current Status
CofO Issued on 1/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 GURUNATH NESARAJAH
Corrections Issued 11/28/2020 GURUNATH NESARAJAH
Plan Check Approved 1/27/2022 GURUNATH NESARAJAH
Issued 1/28/2022 APPLICANT
Building Plans Picked Up 2/7/2022 APPLICANT
CofO in Progress 1/11/2023 ROBERT GOLD
CofO Issued 1/14/2023 MICHAEL SMITH
Permit Finaled 1/14/2023 MICHAEL SMITH

Permit Application Clearance Information

ZA Case Cleared 1/29/2021 LAUREN PADICK
ZA Case Cleared 1/29/2021 LAUREN PADICK
ZI Cleared 1/29/2021 LAUREN PADICK
ZA Case Cleared 3/24/2021 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 4/21/2021 ADRIAN CASTRO
Construction near power lines Cleared 7/22/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 10/24/2021 ROBERT DUFF
Low Impact Development Cleared 1/10/2022 TA ANH
Roof/Waste drainage to street Cleared 1/13/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Pampa Investment Inc; Lic. No.: 832632-B 984 BROADWAY #302      CHULA VISTA, CA 91911

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/21/2022 Partial Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 4/26/2022 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 4/26/2022 Not Ready for Inspection MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 5/2/2022 Not Ready for Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 5/2/2022 Partial Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 5/4/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 6/30/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Approved JAVIER RAMOS JR
HVAC-Rough 6/30/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/30/2022 Corrections Issued JAVIER RAMOS JR
Wood Frame 6/30/2022 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 7/14/2022 Partial Approval DEANDRE HOFFMAN
Green Building Rough 8/2/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 8/2/2022 Approved JAVIER RAMOS JR
Wood Frame 8/2/2022 Approved JAVIER RAMOS JR
Insulation 8/5/2022 Approved JAVIER RAMOS JR
Drywall Nailing 8/12/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 9/21/2022 Approved DEANDRE HOFFMAN
Sewer 9/21/2022 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 11/10/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 11/10/2022 Approved JAVIER RAMOS JR
Final 11/10/2022 OK to Issue CofO JAVIER RAMOS JR
Footing/Foundation/Slab 11/10/2022 Approved JAVIER RAMOS JR
Green Building Final 11/10/2022 Approved JAVIER RAMOS JR
HVAC-Final 11/10/2022 Approved JAVIER RAMOS JR
PLUMBING-Final 11/10/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 11/10/2022 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 11/10/2022 Not Required JAVIER RAMOS JR
Smoke Detectors 11/10/2022 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 11/10/2022 Approved JAVIER RAMOS JR