10637 W JIMENEZ ST 91342
Certificate Information: 10637 W JIMENEZ ST 91342
- Application / Permit
- 20010-20000-03815
- Plan Check / Job No.
- B20VN13608
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ACCESSORY DWELLING UNIT (35' X 24') PER LAMC 12.22A33(c)(d)(g) & WFPP
- Permit Issued
- Issued on 6/5/2021
- Issuing Office
- Current Status
- CofO Issued on 6/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/4/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 5/21/2021 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 5/26/2021 | APPLICANT |
| Issued | 6/5/2021 | APPLICANT |
| CofO in Progress | 6/16/2022 | MATTHEW NELSON |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
| CofO Issued | 6/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 3/10/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/10/2021 | JOHN TRIANTAFYLLOS |
| Specific Plan | Cleared | 4/28/2021 | PEGGY MALONE-BROWN |
| ZI | Cleared | 4/28/2021 | PEGGY MALONE-BROWN |
| Hydrant and Access approval | Cleared | 5/13/2021 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/14/2021 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 5/21/2021 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 5/21/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/7/2021 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/15/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 7/15/2021 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 7/20/2021 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/20/2021 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2021 | Partial Approval | WILLIAM KUEHN |
| Underground Mechanical | 7/30/2021 | Partial Approval | WILLIAM KUEHN |
| Wood Frame | 8/5/2021 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 8/13/2021 | Corrections Issued | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2021 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 8/13/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/13/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/13/2021 | Approved | MATTHEW NELSON |
| Insulation | 8/20/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 9/1/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 9/20/2021 | Partial Approval | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/20/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/16/2021 | Conditional Approval | DAVID MATSON |
| Final | 11/16/2021 | Corrections Issued | DAVID MATSON |
| Green Building Final | 11/16/2021 | Not Ready for Inspection | DAVID MATSON |
| Green Building Rough | 11/16/2021 | Not Ready for Inspection | DAVID MATSON |
| MERV13>=Final | 11/16/2021 | Not Ready for Inspection | DAVID MATSON |
| MERV13>=Rough | 11/16/2021 | Corrections Issued | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 11/16/2021 | SGSOV Not Ready | DAVID MATSON |
| Service/Power Release | 11/16/2021 | Corrections Issued | DAVID MATSON |
| Smoke Detectors | 11/16/2021 | Approved | DAVID MATSON |
| Verify Sprinkler Sign Off | 11/16/2021 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 11/30/2021 | Partial Approval | MATTHEW NELSON |
| Final | 11/30/2021 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 11/30/2021 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 11/30/2021 | Approved | MATTHEW NELSON |
| MERV13>=Final | 11/30/2021 | Corrections Issued | MATTHEW NELSON |
| MERV13>=Rough | 11/30/2021 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/30/2021 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 11/30/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 12/6/2021 | Partial Approval | MATTHEW NELSON |
| Final | 12/6/2021 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 12/6/2021 | Approved | MATTHEW NELSON |
| MERV13>=Final | 12/6/2021 | Approved | MATTHEW NELSON |
| MERV13>=Rough | 12/6/2021 | Partial Approval | MATTHEW NELSON |
| Service/Power Release | 12/6/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/25/2022 | Partial Approval | MATTHEW NELSON |
| Final | 1/25/2022 | Corrections Issued | MATTHEW NELSON |
| MERV13>=Rough | 1/25/2022 | Approved | MATTHEW NELSON |
| Service/Power Release | 1/25/2022 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/6/2022 | Approved | MATTHEW NELSON |
| Final | 6/6/2022 | Corrections Issued | MATTHEW NELSON |
| Service/Power Release | 6/6/2022 | Approved | MATTHEW NELSON |
| Final | 6/16/2022 | OK to Issue CofO | MATTHEW NELSON |