6012 S 10TH AVE 1-18 90043

Certificate Information: 6012 S 10TH AVE 1-18 90043

Application / Permit
20010-20000-03766
Plan Check / Job No.
B20VN13503
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3-STORY 116'6"X30'0" 18-UNIT APT BLDG. TOC PROJECT; 100% AFFORDABLE HOUSING. NFPA 13 FIRE SPRINKLERS REQ'D THROGHOUT. ALL ELECTRIC BUILDING
Permit Issued
Issued on 9/30/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2020 APPLICANT
Disabled Access Plans Picked Up 10/30/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 MARVEL DELACRUZ
Green Plans Picked Up 11/12/2020 APPLICANT
Corrections Issued 11/15/2020 MARVEL DELACRUZ
Quality Review Completed 11/20/2020 STEVEN KIM
Building Plans Picked Up 11/20/2020 APPLICANT
Applicant returned to address corrections 2/7/2023 MARVEL DELACRUZ
Applicant returned to address corrections 2/29/2024 MARVEL DELACRUZ
Applicant returned to address corrections 3/7/2024 MARVEL DELACRUZ
Applicant returned to address corrections 4/19/2024 MARVEL DELACRUZ
Plan Check Approved 4/19/2024 MARVEL DELACRUZ
Issued 9/30/2024 APPLICANT
CofO in Progress 1/5/2026 RAFAEL ESPINOZA
Permit Finaled 1/5/2026 ERNESTO CORRAL
CofO Issued 1/5/2026 ERNESTO CORRAL
Permit Finaled 1/5/2026 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 1/15/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/15/2021 WALLIE JONG
Highway dedication Cleared 1/15/2021 WALLIE JONG
Miscellaneous Cleared 2/24/2021 ANACANY HURTADO
Frnt yard landscape/Water mgmt Cleared 3/4/2021 ANACANY HURTADO
Opn space landscape/Water mgmt Cleared 3/4/2021 ANACANY HURTADO
Hydrant and Access approval Cleared 7/28/2021 KURT CORRAL
Fire Marshal Fire Life Safety Cleared 8/31/2021 OSCAR SALGADO JR
Low Impact Development Cleared 10/15/2021 AMMAR ELTAWIL
Building over 36-ft Cleared 12/14/2021 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 1/27/2022 CINDY QI
Sewer availability Cleared 1/31/2022 CINDY QI
DAS Clearance Cleared 2/8/2022 NORLITO MEDRANO
Green Code Cleared 2/10/2022 MICHAEL AYERS
Miscellaneous Cleared 1/23/2023 ROBIN ETNIEL
Density Bonus 12.22.A.31 Cleared 10/10/2023 JAMES MCCARTHY
Green Code Cleared 1/10/2024 MICHAEL AYERS

Contact Information

Contractor M7 Construction Corp; Lic. No.: 1077393-B 15021 VENTURA BLVD SUITE 440      SHERMAN OAKS, CA 91403
Engineer Chatsky,, German; Lic. No.: C84153 6541 ODESSA AVE UNIT 11      LAKE BALBOA, CA 91406

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/17/2024 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 12/24/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 1/6/2025 Partial Approval JAMES POWERS
Deputy Wood Construction 1/22/2025 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 No Access for Inspection RAFAEL ESPINOZA
Green Building Rough 1/22/2025 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 1/22/2025 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 1/22/2025 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/23/2025 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/10/2025 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Partial Approval RAFAEL ESPINOZA
Green Building Rough 2/10/2025 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/10/2025 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 2/10/2025 Partial Inspection RAFAEL ESPINOZA
Deputy Wood Construction 2/27/2025 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Partial Approval RAFAEL ESPINOZA
Green Building Rough 2/27/2025 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/27/2025 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 2/27/2025 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/19/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 3/19/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 3/25/2025 Partial Approval RAFAEL ESPINOZA
Wood Frame 3/25/2025 Partial Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 4/4/2025 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 4/4/2025 Partial Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/11/2025 Partial Inspection RAFAEL ESPINOZA
Wood Frame 4/11/2025 Partial Approval RAFAEL ESPINOZA
Insulation 4/15/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/18/2025 Partial Approval RAFAEL ESPINOZA
Insulation 4/25/2025 Partial Approval RAFAEL ESPINOZA
Insulation 5/28/2025 Partial Approval RAFAEL ESPINOZA
Insulation 6/3/2025 Partial Inspection RAFAEL ESPINOZA
Insulation 6/6/2025 Approved RAFAEL ESPINOZA
Drywall Nailing 6/23/2025 Not Ready for Inspection RAFAEL CORTES
Green Building Rough 6/23/2025 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 6/25/2025 Partial Approval RAFAEL ESPINOZA
Green Building Rough 6/25/2025 Not Ready for Inspection RAFAEL ESPINOZA
Pre-Inspection 8/15/2025 Approved RAFAEL CORTES
Pre-Inspection 8/20/2025 Approved RAFAEL CORTES
Drywall Nailing 11/5/2025 Approved RAFAEL CORTES
Final 11/5/2025 Partial Approval RAFAEL CORTES
Footing/Foundation/Slab 11/5/2025 Approved RAFAEL CORTES
Green Building Final 11/5/2025 Approved RAFAEL CORTES
Green Building Rough 11/5/2025 Approved RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 11/5/2025 SGSOV No Gas RAFAEL CORTES
Smoke Detectors 11/5/2025 Approved RAFAEL CORTES
Verify Sprinkler Sign Off 11/5/2025 Approved RAFAEL CORTES
Wood Frame 11/5/2025 Approved RAFAEL CORTES
Final 11/10/2025 Partial Inspection RAFAEL ESPINOZA
Final 12/31/2025 OK to Issue CofO RAFAEL ESPINOZA