6845 N COSTELLO AVE 91405

Certificate Information: 6845 N COSTELLO AVE 91405

Application / Permit
20010-20000-03730
Plan Check / Job No.
B20VN13396
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW DETACHED 21' X 21' GARAGE
Permit Issued
Issued on 4/6/2021
Issuing Office
Current Status
CofO Issued on 5/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 SELLA BENYAMIN
Corrections Issued 11/17/2020 SELLA BENYAMIN
Quality Review Completed 11/20/2020 STEVEN KIM
Building Plans Picked Up 11/20/2020 APPLICANT
Plan Check Approved 4/6/2021 SELLA BENYAMIN
Issued 4/6/2021 APPLICANT
CofO in Progress 4/25/2025 RYAN SALAZAR
Permit Finaled 5/2/2025 RUBEN SALAS
CofO Issued 5/2/2025 RUBEN SALAS
Permit Finaled 5/2/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/3/2020 ABDULLAH SADOZAI
Low Impact Development Cleared 3/23/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/24/2021 ADRIAN CASTRO
Construction near power lines Cleared 4/6/2021 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/12/2021 Partial Inspection MICHAEL TEMPLE
PLUMBING-Rough 7/16/2021 Partial Approval RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 7/28/2021 Not Ready for Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 7/30/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 10/21/2021 Corrections Issued RICHARD DOCKUS
Pre-Inspection 10/21/2021 Partial Inspection MICHAEL TEMPLE
Drywall Nailing 10/26/2021 Not Ready for Inspection RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 10/26/2021 Partial Approval RICHARD DOCKUS
HVAC-Rough 12/9/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 12/9/2021 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 12/13/2021 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 1/4/2022 Approved ALAN MORELOS
ELECTRICAL-Rough 1/10/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 1/21/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 2/4/2022 Not Ready for Inspection RICHARD DOCKUS
Final 2/4/2022 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 2/4/2022 Approved RICHARD DOCKUS
Green Building Final 2/4/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Rough 2/4/2022 Not Ready for Inspection RICHARD DOCKUS
Interior/Exterior Lathing 2/4/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 2/4/2022 SGSOV Not Ready RICHARD DOCKUS
Service/Power Release 2/4/2022 Not Ready for Inspection RICHARD DOCKUS
Smoke Detectors 2/4/2022 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 4/10/2025 Approved RYAN SALAZAR
Final 4/10/2025 Corrections Issued RYAN SALAZAR
Green Building Final 4/10/2025 Approved RYAN SALAZAR
Green Building Rough 4/10/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/10/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 4/10/2025 Not Required RYAN SALAZAR
Smoke Detectors 4/10/2025 Approved RYAN SALAZAR
Final 4/21/2025 OK to Issue CofO RYAN SALAZAR