9955 N LINDLEY AVE 91325

Certificate Information: 9955 N LINDLEY AVE 91325

Application / Permit
20010-20000-03693
Plan Check / Job No.
B20VN13323
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 75' X 46'6" IRREGULAR SHAPED ONE STORY SINGLE FAMILY DWELLING , NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/26/2021
Issuing Office
Current Status
CofO Issued on 9/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2020 APPLICANT
Assigned to Plan Check Engineer 11/5/2020 RARES BODEA
Corrections Issued 11/7/2020 RARES BODEA
Quality Review Completed 11/13/2020 STEVEN KIM
Building Plans Picked Up 11/13/2020 APPLICANT
Applicant returned to address corrections 6/23/2021 RARES BODEA
Applicant returned to address corrections 7/12/2021 RARES BODEA
Plan Check Approved 7/26/2021 RARES BODEA
Issued 7/26/2021 APPLICANT
CofO in Progress 9/28/2022 JEFFREY PARD
Permit Finaled 9/28/2022 JOHN JANSON
CofO Issued 9/28/2022 JOHN JANSON
Permit Finaled 9/28/2022 JOHN JANSON

Permit Application Clearance Information

ZA Case Cleared 11/23/2020 DANG NGUYEN
Address approval Cleared 11/30/2020 LEE GUILBEAUX
Permit Cleared 11/30/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/1/2020 LEE GUILBEAUX
"Q" conditions Cleared 2/16/2021 MIGUEL GAMBOA
"T" removal Cleared 2/16/2021 MIGUEL GAMBOA
Tract Map conditions Cleared 2/16/2021 MIGUEL GAMBOA
Hydrant and Access approval Cleared 2/26/2021 JEREMY CARTER
Low Impact Development Cleared 5/14/2021 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 5/17/2021 ADRIAN CASTRO
Trees in Parkway Cleared 6/2/2021 JOHN KIM
Miscellaneous Cleared 6/22/2021 LEE GUILBEAUX
Sewer availability Cleared 6/22/2021 LEE GUILBEAUX
APC Cleared 7/23/2021 MIGUEL GAMBOA

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/29/2021 Partial Approval JEFFREY PARD
Excavation/Setback/Form/Re-Bar 8/11/2021 Approved JEFFREY PARD
Underground Mechanical 10/1/2021 Approved JEFFREY PARD
Underground Mechanical 10/21/2021 Approved DAVID SCANTLIN
PLUMBING-Rough 11/1/2021 Approved JEFFREY PARD
ELECTRICAL-Rough 11/3/2021 Approved JEFFREY PARD
BUILDING-Rough-Frame 11/5/2021 Partial Approval JEFFREY PARD
Green Building Rough 11/5/2021 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 11/5/2021 Approved JEFFREY PARD
Verify Sprinkler Sign Off 11/5/2021 Approved JEFFREY PARD
Insulation 11/9/2021 Approved JEFFREY PARD
Interior/Exterior Lathing 11/9/2021 Approved JEFFREY PARD
Drywall Nailing 11/15/2021 Approved DAVID SCANTLIN
Interior/Exterior Lathing 12/10/2021 Approved JAVIER RAMOS JR
Shower Pan 12/10/2021 Approved JAVIER RAMOS JR
HVAC-Final 6/1/2022 Approved JEFFREY PARD
PLUMBING-Final 6/1/2022 Approved JEFFREY PARD
ELECTRICAL-Final 6/2/2022 Approved JEFFREY PARD
Service/Power Release 6/8/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 8/24/2022 Approved JEFFREY PARD
Final 8/24/2022 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 8/24/2022 Approved JEFFREY PARD
Green Building Final 8/24/2022 Approved JEFFREY PARD
Green Building Rough 8/24/2022 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 8/24/2022 SGSOV Approved JEFFREY PARD
Smoke Detectors 8/24/2022 Approved JEFFREY PARD
Final 9/27/2022 OK to Issue CofO JEFFREY PARD