17201 W WEDDINGTON ST 91316

Certificate Information: 17201 W WEDDINGTON ST 91316

Application / Permit
20010-20000-03691
Plan Check / Job No.
B20VN13316
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 20' 1" X 11' 9" DETACHED RECREATION ROOM. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 3/12/2021
Issuing Office
Current Status
CofO Issued on 11/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 GURUNATH NESARAJAH
Corrections Issued 10/17/2020 GURUNATH NESARAJAH
Quality Review Completed 10/22/2020 OMID HEDAYAT
Applicant returned to address corrections 2/19/2021 GURUNATH NESARAJAH
Plan Check Approved 3/12/2021 GURUNATH NESARAJAH
Issued 3/12/2021 APPLICANT
Building Plans Picked Up 3/15/2021 APPLICANT
CofO in Progress 11/17/2021 STEVEN BACK
Permit Finaled 11/18/2021 JOHN JANSON
CofO Issued 11/18/2021 JOHN JANSON
Permit Finaled 11/18/2021 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/20/2020 ADRIAN CASTRO
Construction near power lines Cleared 12/21/2020 RIDWAN HARDY
Low Impact Development Cleared 1/6/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/6/2021 ADRIAN CASTRO
ZI Cleared 1/7/2021 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/22/2021 Approved STEVEN BACK
Footing/Foundation/Slab 3/22/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 3/22/2021 Partial Approval STEVEN BACK
Footing/Foundation/Slab 3/26/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/4/2021 Partial Approval STEVEN BACK
ELECTRICAL-Rough 5/24/2021 Not Ready for Inspection STEVEN BACK
HVAC-Rough 5/24/2021 Approved STEVEN BACK
PLUMBING-Rough 5/24/2021 Approved STEVEN BACK
ELECTRICAL-Rough 5/28/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Approved RONALD COWAN
HVAC-Rough 5/28/2021 Approved RONALD COWAN
Interior/Exterior Lathing 6/1/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 6/7/2021 Approved STEVEN BACK
Green Building Rough 6/7/2021 Approved STEVEN BACK
Verify Sprinkler Sign Off 6/7/2021 Approved STEVEN BACK
Drywall Nailing 6/11/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 6/17/2021 Approved RYAN SALAZAR
ELECTRICAL-Final 10/27/2021 Approved STEVEN BACK
Final 10/27/2021 Corrections Issued STEVEN BACK
Gas Test 10/27/2021 Approved STEVEN BACK
Green Building Final 10/27/2021 Approved STEVEN BACK
HVAC-Final 10/27/2021 Approved STEVEN BACK
PLUMBING-Final 10/27/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 10/27/2021 SGSOV Approved STEVEN BACK
Service/Power Release 10/27/2021 Not Required STEVEN BACK
Smoke Detectors 10/27/2021 Approved STEVEN BACK
ELECTRICAL-Final 11/8/2021 Approved STEVEN BACK
Final 11/8/2021 Not Ready for Inspection STEVEN BACK
HVAC-Final 11/8/2021 Approved STEVEN BACK
Service/Power Release 11/8/2021 Not Required STEVEN BACK
Final 11/17/2021 OK to Issue CofO STEVEN BACK