8203 N ST CLAIR AVE 91605

Certificate Information: 8203 N ST CLAIR AVE 91605

Application / Permit
20010-20000-03684
Plan Check / Job No.
B20VN13287
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY DETACHED 31' 6" X 40' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING. "The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."
Permit Issued
Issued on 3/17/2022
Issuing Office
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2020 APPLICANT
Assigned to Plan Check Engineer 11/10/2020 GURUNATH NESARAJAH
Corrections Issued 11/11/2020 GURUNATH NESARAJAH
Applicant returned to address corrections 11/23/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 2/25/2022 GURUNATH NESARAJAH
Plan Check Approved 3/11/2022 GURUNATH NESARAJAH
Issued 3/17/2022 APPLICANT
Building Plans Picked Up 3/24/2022 APPLICANT
CofO in Progress 4/24/2024 MATTHEW NELSON
Permit Finaled 5/1/2024 RUBEN SALAS
CofO Issued 5/1/2024 RUBEN SALAS
Permit Finaled 5/1/2024 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 2/6/2021 RIDWAN HARDY
Address approval Cleared 10/5/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 10/7/2021 GABRIEL ROBLES
Sewer availability Cleared 10/7/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 11/15/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 3/1/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/10/2022 Approved CHRISTOPHER DELLEFIELD
Underground Mechanical 5/10/2022 Partial Approval CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 5/19/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 5/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Grounding or Bonding 5/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 5/23/2022 Approved CHRISTOPHER DELLEFIELD
Grounding or Bonding 5/23/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 7/19/2022 Partial Approval CHRISTOPHER DELLEFIELD
PLUMBING-Rough 7/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 8/12/2022 Conditional Approval ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Approved DEANDRE HOFFMAN
Rough-Elec/Plmb/HVAC 9/12/2022 Partial Approval DEANDRE HOFFMAN
BUILDING-Rough-Frame 10/13/2022 Not Ready for Inspection DEANDRE HOFFMAN
Interior/Exterior Lathing 10/13/2022 Partial Approval DEANDRE HOFFMAN
Rough-Elec/Plmb/HVAC 10/13/2022 Corrections Issued DEANDRE HOFFMAN
Verify Sprinkler Sign Off 10/13/2022 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 10/20/2022 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 10/20/2022 No Access for Inspection MATTHEW NELSON
Rough-Elec/Plmb/HVAC 10/20/2022 No Access for Inspection MATTHEW NELSON
Rough-Elec/Plmb/HVAC 10/27/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 11/3/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Drywall Nailing 11/29/2022 Approved MATTHEW NELSON
Insulation 11/29/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 12/27/2022 Approved MATTHEW NELSON
Shower Pan 12/27/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 5/18/2023 Approved MATTHEW NELSON
Final 5/18/2023 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 5/18/2023 Approved MATTHEW NELSON
Green Building Final 5/18/2023 Corrections Issued MATTHEW NELSON
Green Building Rough 5/18/2023 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 5/18/2023 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 5/18/2023 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 5/18/2023 Approved MATTHEW NELSON
Final 3/18/2024 Corrections Issued MATTHEW NELSON
Green Building Final 3/18/2024 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/18/2024 SGSOV Approved MATTHEW NELSON
Service/Power Release 3/18/2024 Not Ready for Inspection MATTHEW NELSON
Final 4/22/2024 OK to Issue CofO MATTHEW NELSON
Green Building Final 4/22/2024 Approved MATTHEW NELSON
Service/Power Release 4/22/2024 Approved MATTHEW NELSON