8203 N ST CLAIR AVE 91605
Certificate Information: 8203 N ST CLAIR AVE 91605
- Application / Permit
- 20010-20000-03684
- Plan Check / Job No.
- B20VN13287
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY DETACHED 31' 6" X 40' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING. "The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- CofO Issued on 5/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 11/11/2020 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 11/23/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 2/25/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/11/2022 | GURUNATH NESARAJAH |
| Issued | 3/17/2022 | APPLICANT |
| Building Plans Picked Up | 3/24/2022 | APPLICANT |
| CofO in Progress | 4/24/2024 | MATTHEW NELSON |
| Permit Finaled | 5/1/2024 | RUBEN SALAS |
| CofO Issued | 5/1/2024 | RUBEN SALAS |
| Permit Finaled | 5/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/6/2021 | RIDWAN HARDY |
| Address approval | Cleared | 10/5/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 10/7/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 11/15/2021 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 3/1/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/10/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 5/10/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 5/19/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 5/19/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Grounding or Bonding | 5/19/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 5/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Grounding or Bonding | 5/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 7/19/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 8/12/2022 | Conditional Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2022 | Approved | DEANDRE HOFFMAN |
| Rough-Elec/Plmb/HVAC | 9/12/2022 | Partial Approval | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 10/13/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 10/13/2022 | Partial Approval | DEANDRE HOFFMAN |
| Rough-Elec/Plmb/HVAC | 10/13/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Verify Sprinkler Sign Off | 10/13/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 10/20/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 10/20/2022 | No Access for Inspection | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 10/20/2022 | No Access for Inspection | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 10/27/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 11/3/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 11/29/2022 | Approved | MATTHEW NELSON |
| Insulation | 11/29/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/27/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 12/27/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/18/2023 | Approved | MATTHEW NELSON |
| Final | 5/18/2023 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 5/18/2023 | Approved | MATTHEW NELSON |
| Green Building Final | 5/18/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 5/18/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/18/2023 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 5/18/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 5/18/2023 | Approved | MATTHEW NELSON |
| Final | 3/18/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 3/18/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/18/2024 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 3/18/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 4/22/2024 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 4/22/2024 | Approved | MATTHEW NELSON |
| Service/Power Release | 4/22/2024 | Approved | MATTHEW NELSON |