8609 N AQUEDUCT AVE 91343

Certificate Information: 8609 N AQUEDUCT AVE 91343

Application / Permit
20010-20000-03651
Plan Check / Job No.
B20VN13222
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(22) Storage Building
Work Description
NEW DETACHED 23' X 35' 1-STORY STORAGE BUILDING. ALL WORK DONE PER WFPP. NFPA 13D FIRE SPRINKLERS TO BE PROVIDED.
Permit Issued
Issued on 8/13/2021
Issuing Office
Current Status
CofO Issued on 5/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 GURUNATH NESARAJAH
Corrections Issued 11/29/2020 GURUNATH NESARAJAH
Applicant returned to address corrections 8/3/2021 GURUNATH NESARAJAH
Plan Check Approved 8/12/2021 GURUNATH NESARAJAH
Issued 8/13/2021 APPLICANT
Building Plans Picked Up 8/26/2021 APPLICANT
CofO in Progress 5/3/2022 RAUL OLAGI
Permit Finaled 5/4/2022 RONALD MYRICK
CofO Issued 5/4/2022 RONALD MYRICK
Permit Finaled 5/4/2022 RONALD MYRICK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/9/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 4/9/2021 MATTHEW CRAIG
Low Impact Development Cleared 7/13/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 7/19/2021 CARLOS AGUILERA
Miscellaneous Cleared 8/5/2021 MATTHEW CRAIG

Contact Information

Contractor Pampa Investment Inc; Lic. No.: 832632-B 984 BROADWAY #302      CHULA VISTA, CA 91911

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/18/2021 Corrections Issued JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 9/1/2021 Approved JACK KARGODORIAN
Footing/Foundation/Slab 9/1/2021 Approved JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 9/3/2021 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 9/16/2021 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 9/16/2021 Partial Approval JACK KARGODORIAN
Verify Sprinkler Sign Off 9/16/2021 Approved JACK KARGODORIAN
Wood Frame 9/16/2021 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 9/22/2021 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 9/22/2021 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 9/22/2021 Approved JACK KARGODORIAN
Wood Frame 9/22/2021 Partial Inspection JACK KARGODORIAN
ELECTRICAL-Rough 10/14/2021 Not Ready for Inspection ALAN MORELOS
Wood Frame 10/14/2021 Not Ready for Inspection ALAN MORELOS
ELECTRICAL-Rough 10/20/2021 Approved JENNIFER RABUCHIN
Wood Frame 10/20/2021 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/4/2022 Approved RAUL OLAGI
Final 4/4/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/4/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 4/4/2022 Approved RAUL OLAGI
Final 5/2/2022 Corrections Issued RAUL OLAGI
Service/Power Release 5/2/2022 Approved RAUL OLAGI
Final 5/3/2022 OK to Issue CofO RAUL OLAGI