3072 N HOLLYRIDGE DR 90068
Certificate Information: 3072 N HOLLYRIDGE DR 90068
- Application / Permit
- 20010-20000-03632
- Plan Check / Job No.
- B20VN13175
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD AND BASEMENT ;FIRE SPRINKLERS NFPA-13D
- Permit Issued
- Issued on 10/16/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 11/13/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 12/4/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 12/9/2020 | APPLICANT |
| Applicant returned to address corrections | 6/9/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 10/11/2023 | MOHAMMAD ESMAILI |
| Issued | 10/16/2023 | APPLICANT |
| CofO in Progress | 6/4/2026 | BRIAN SULLIVAN |
| Permit Finaled | 6/4/2026 | DEROLD HAUFF |
| CofO Issued | 6/4/2026 | DEROLD HAUFF |
| Permit Finaled | 6/4/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 1/7/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 2/10/2021 | MATTHEW CRAIG |
| Address approval | Cleared | 2/26/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 2/26/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 2/26/2021 | WALLIE JONG |
| Permit | Cleared | 2/26/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2021 | WALLIE JONG |
| Sewer availability | Cleared | 3/1/2021 | WALLIE JONG |
| Distance to fire station | Cleared | 3/8/2021 | JEREMY CARTER |
| Low Impact Development | Cleared | 10/26/2021 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 11/2/2021 | CHRISTOPHER ROCHA |
| Miscellaneous | Cleared | 11/12/2021 | RICHARD REASER |
| BHO/Hillside ordinance | Cleared | 12/6/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 5/9/2023 | MATIAS FARFAN |
| Landscape for retaining wall | Cleared | 5/18/2023 | GEORGIA SMITH |
| Miscellaneous | Cleared | 5/18/2023 | GEORGIA SMITH |
| Miscellaneous | Cleared | 5/18/2023 | GEORGIA SMITH |
| Miscellaneous | Cleared | 5/18/2023 | GEORGIA SMITH |
| Specific Plan | Cleared | 5/18/2023 | GEORGIA SMITH |
| ZA Case | Cleared | 5/18/2023 | GEORGIA SMITH |
| ZI | Cleared | 5/18/2023 | GEORGIA SMITH |
| BHO/Hillside ordinance | Cleared | 6/1/2023 | WALLIE JONG |
| Miscellaneous | Cleared | 7/25/2023 | NOAH MCCOY |
| Excavation more than 5-ft deep | Cleared | 9/20/2023 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 9/20/2023 | MOHAMMAD ESMAILI |
| Grading Pre-Inspection | Cleared | 9/20/2023 | MOHAMMAD ESMAILI |
Contact Information
| Architect | Akopian,, Harout; Lic. No.: C37146 | 2124 ARMOUR PL GLENDALE, CA 91208 |
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/15/2024 | Partial Inspection | ALIZAH MAYAGOITIA |
| Deputy Reinf. Concrete | 3/22/2024 | Conditional Approval | ROY SPAULDING |
| Piling/Pier/Caisson | 3/26/2024 | Partial Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 4/1/2024 | Conditional Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 4/1/2024 | Partial Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 4/8/2024 | Conditional Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/22/2024 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 5/8/2024 | Approved | ROY SPAULDING |
| Deputy Reinf. Concrete | 5/13/2024 | Conditional Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 5/23/2024 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 5/23/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Reinforced Concrete Frame | 5/23/2024 | Partial Approval | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 5/23/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/7/2024 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Partial Inspection | BRIAN SULLIVAN |
| Wood Frame | 11/1/2024 | Partial Inspection | BRIAN SULLIVAN |
| Deputy Wood Construction | 1/17/2025 | Conditional Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 1/21/2025 | Conditional Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 1/21/2025 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2025 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 1/21/2025 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 1/21/2025 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 1/21/2025 | Approved | BRIAN SULLIVAN |
| Sewer | 1/21/2025 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 1/21/2025 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 2/6/2025 | Approved | BRIAN SULLIVAN |
| Insulation | 2/6/2025 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 2/6/2025 | Not Ready for Inspection | BRIAN SULLIVAN |
| Shower Pan | 2/6/2025 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 2/25/2025 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/25/2025 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 9/15/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 9/16/2025 | Partial Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 9/16/2025 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 12/19/2025 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 12/19/2025 | Partial Inspection | BRIAN SULLIVAN |
| Green Building Final | 12/19/2025 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 12/19/2025 | Not Ready for Inspection | BRIAN SULLIVAN |
| Reinforced Concrete Frame | 12/19/2025 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 12/19/2025 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 12/19/2025 | Approved | BRIAN SULLIVAN |
| Final | 1/30/2026 | Corrections Issued | BRIAN SULLIVAN |
| Final | 6/3/2026 | OK to Issue CofO | BRIAN SULLIVAN |