9230 W ROBIN DR 90069
Certificate Information: 9230 W ROBIN DR 90069
- Application / Permit
- 20010-20000-03624
- Plan Check / Job No.
- B20VN13134
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- new detach basement garage 95' x76' irreg.
- Permit Issued
- Issued on 7/2/2021
- Issuing Office
- Current Status
- CofO Issued on 8/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2020 | CHON CHIO KUO |
| Corrections Issued | 11/10/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/6/2021 | CHON CHIO KUO |
| Plan Check Approved | 6/23/2021 | CHON CHIO KUO |
| Issued | 7/2/2021 | APPLICANT |
| CofO in Progress | 8/15/2025 | RAUL BARAJAS |
| No Progress | 8/16/2025 | DEROLD HAUFF |
| CofO in Progress | 8/16/2025 | DEROLD HAUFF |
| Permit Finaled | 8/29/2025 | DEROLD HAUFF |
| CofO Issued | 8/29/2025 | DEROLD HAUFF |
| Permit Finaled | 8/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Paul, Mcclean; Lic. No.: C36197 | 190 S GLASELL #203 ORANGE, CA 92866 |
| Contractor | Hill Pete Construction Company Inc; Lic. No.: 470065-B | 4626 ALBUQUERQUE ST 2ND FLOOR SAN DIEGO, CA 92109 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Labib,, Youhanna T; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/12/2021 | Partial Inspection | RICHARD STEINBACH |
| Piling/Pier/Caisson | 12/19/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Shower Pan | 12/19/2022 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 6/15/2023 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/15/2023 | Corrections Issued | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 6/16/2023 | Partial Inspection | RAUL BARAJAS |
| Green Building Rough | 6/16/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Reinforced Concrete Frame | 6/16/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 6/16/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 7/11/2023 | Partial Approval | RAUL BARAJAS |
| Deck | 9/19/2023 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/19/2023 | Partial Approval | RAUL BARAJAS |
| Pool Piping | 11/28/2023 | Partial Approval | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 11/28/2023 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 12/19/2023 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 12/19/2023 | Partial Approval | RAUL BARAJAS |
| Underground Mechanical | 12/19/2023 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 1/9/2024 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 3/26/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 3/26/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/26/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 3/28/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 3/29/2024 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 4/19/2024 | Approved | RAUL BARAJAS |
| Drywall Nailing | 4/23/2024 | No Access for Inspection | ROY SPAULDING |
| Drywall Nailing | 4/25/2024 | Approved | RAUL BARAJAS |
| Final | 8/12/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Footing/Foundation/Slab | 8/12/2025 | Approved | BRENDAN MORELLI |
| Green Building Final | 8/12/2025 | Approved | BRENDAN MORELLI |
| Green Building Rough | 8/12/2025 | Approved | BRENDAN MORELLI |
| Reinforced Concrete Frame | 8/12/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 8/12/2025 | SGSOV Not Ready | BRENDAN MORELLI |
| Service/Power Release | 8/12/2025 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 8/12/2025 | Approved | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 8/12/2025 | Approved | BRENDAN MORELLI |
| Final | 8/14/2025 | OK to Issue CofO | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV Gas Company | RAUL BARAJAS |