9230 W ROBIN DR 90069

Certificate Information: 9230 W ROBIN DR 90069

Application / Permit
20010-20000-03624
Plan Check / Job No.
B20VN13134
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
new detach basement garage 95' x76' irreg.
Permit Issued
Issued on 7/2/2021
Issuing Office
Current Status
CofO Issued on 8/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2020 APPLICANT
Assigned to Plan Check Engineer 10/19/2020 CHON CHIO KUO
Corrections Issued 11/10/2020 CHON CHIO KUO
Applicant returned to address corrections 5/6/2021 CHON CHIO KUO
Plan Check Approved 6/23/2021 CHON CHIO KUO
Issued 7/2/2021 APPLICANT
CofO in Progress 8/15/2025 RAUL BARAJAS
No Progress 8/16/2025 DEROLD HAUFF
CofO in Progress 8/16/2025 DEROLD HAUFF
Permit Finaled 8/29/2025 DEROLD HAUFF
CofO Issued 8/29/2025 DEROLD HAUFF
Permit Finaled 8/29/2025 DEROLD HAUFF

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Paul, Mcclean; Lic. No.: C36197 190 S GLASELL   #203    ORANGE, CA 92866
Contractor Hill Pete Construction Company Inc; Lic. No.: 470065-B 4626 ALBUQUERQUE ST 2ND FLOOR      SAN DIEGO, CA 92109
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Labib,, Youhanna T; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/12/2021 Partial Inspection RICHARD STEINBACH
Piling/Pier/Caisson 12/19/2022 Not Ready for Inspection RAUL BARAJAS
Shower Pan 12/19/2022 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/15/2023 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 6/15/2023 Corrections Issued RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/16/2023 Partial Inspection RAUL BARAJAS
Green Building Rough 6/16/2023 Not Ready for Inspection RAUL BARAJAS
Reinforced Concrete Frame 6/16/2023 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 6/16/2023 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/11/2023 Partial Approval RAUL BARAJAS
Deck 9/19/2023 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 9/19/2023 Partial Approval RAUL BARAJAS
Pool Piping 11/28/2023 Partial Approval RAUL BARAJAS
Rough-Elec/Plmb/HVAC 11/28/2023 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 12/19/2023 Partial Approval RAUL BARAJAS
PLUMBING-Rough 12/19/2023 Partial Approval RAUL BARAJAS
Underground Mechanical 12/19/2023 Approved RAUL BARAJAS
Footing/Foundation/Slab 1/9/2024 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 3/26/2024 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 3/26/2024 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 3/26/2024 Corrections Issued JOAQUIN GREENOUGH
Rough-Elec/Plmb/HVAC 3/28/2024 Not Ready for Inspection RAUL BARAJAS
Rough-Elec/Plmb/HVAC 3/29/2024 Approved RAUL BARAJAS
Interior/Exterior Lathing 4/19/2024 Approved RAUL BARAJAS
Drywall Nailing 4/23/2024 No Access for Inspection ROY SPAULDING
Drywall Nailing 4/25/2024 Approved RAUL BARAJAS
Final 8/12/2025 Not Ready for Inspection BRENDAN MORELLI
Footing/Foundation/Slab 8/12/2025 Approved BRENDAN MORELLI
Green Building Final 8/12/2025 Approved BRENDAN MORELLI
Green Building Rough 8/12/2025 Approved BRENDAN MORELLI
Reinforced Concrete Frame 8/12/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 8/12/2025 SGSOV Not Ready BRENDAN MORELLI
Service/Power Release 8/12/2025 Approved BRENDAN MORELLI
Smoke Detectors 8/12/2025 Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 8/12/2025 Approved BRENDAN MORELLI
Final 8/14/2025 OK to Issue CofO RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 8/14/2025 SGSOV Gas Company RAUL BARAJAS