10819 N DARBY AVE 91326

Certificate Information: 10819 N DARBY AVE 91326

Application / Permit
20010-20000-03610
Plan Check / Job No.
B20VN13112
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 23'-3" x 24'-7" DETACHED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 6/21/2021
Issuing Office
Current Status
CofO Issued on 1/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 SEAN SHAHMIRI
Corrections Issued 11/2/2020 SEAN SHAHMIRI
Quality Review Completed 12/1/2020 OMID HEDAYAT
Building Plans Picked Up 12/3/2020 APPLICANT
Plan Check Approved 6/9/2021 SEAN SHAHMIRI
Applicant returned to address corrections 6/10/2021 SEAN SHAHMIRI
Issued 6/21/2021 APPLICANT
CofO in Progress 12/29/2022 SEAN WIRCH
Permit Finaled 1/3/2023 JOHN JANSON
CofO Issued 1/3/2023 JOHN JANSON
Permit Finaled 1/3/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/15/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/21/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/21/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 3/6/2021 RIDWAN HARDY
Construction within easement Cleared 3/6/2021 RIDWAN HARDY
Low Impact Development Cleared 4/20/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 4/21/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Oruncakciel,, Sayat; Lic. No.: C77182 15445 VENTURA BLVD 25      SHERMAN OAKS, CA 91403

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/2/2021 Not Ready for Inspection JEFFREY PARD
Excavation/Setback/Form/Re-Bar 11/24/2021 Not Ready for Inspection JEFFREY PARD
Pre-Inspection 1/14/2022 No Access for Inspection VINCENT HANLEY
Footing/Foundation/Slab 1/19/2022 Partial Approval DAVID SCANTLIN
Deputy Drilled-In Anchors 1/26/2022 Conditional Approval DAVID SCANTLIN
PLUMBING-Rough 1/27/2022 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 1/28/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 2/3/2022 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 2/16/2022 Approved JEFFREY PARD
ELECTRICAL-Rough 3/17/2022 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Approved JEFFREY PARD
HVAC-Rough 3/17/2022 Approved JEFFREY PARD
PLUMBING-Rough 3/17/2022 Approved JEFFREY PARD
Wood Frame 3/17/2022 Corrections Issued JEFFREY PARD
ELECTRICAL-Rough 3/25/2022 Approved DAVID SCANTLIN
Interior/Exterior Lathing 3/25/2022 Partial Approval DAVID SCANTLIN
Wood Frame 3/25/2022 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 5/6/2022 Approved JEFFREY PARD
Green Building Rough 5/6/2022 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 5/6/2022 Approved JEFFREY PARD
Verify Sprinkler Sign Off 5/6/2022 Approved JEFFREY PARD
Insulation 5/10/2022 Approved JEFFREY PARD
Drywall Nailing 5/23/2022 Approved KRISTEN CAUSEY
Green Building Rough 5/23/2022 Approved KRISTEN CAUSEY
ELECTRICAL-Final 9/1/2022 Not Ready for Inspection JEFFREY PARD
Gas Test 9/1/2022 Not Ready for Inspection JEFFREY PARD
HVAC-Final 9/1/2022 Not Ready for Inspection JEFFREY PARD
PLUMBING-Final 9/1/2022 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Final 9/21/2022 Approved SEAN HAUPT
Final 9/21/2022 Corrections Issued SEAN HAUPT
Gas Test 9/21/2022 Approved SEAN HAUPT
HVAC-Final 9/21/2022 Approved SEAN HAUPT
PLUMBING-Final 9/21/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 11/3/2022 SGSOV Not Ready DAVID SCANTLIN
Green Building Final 11/22/2022 Corrections Issued JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Approved JOHN KIDWELL
Smoke Detectors 11/22/2022 Approved JOHN KIDWELL
Green Building Final 12/14/2022 Corrections Issued JOHN KIDWELL
Final 12/23/2022 Corrections Issued JOHN KIDWELL
Green Building Final 12/23/2022 Approved JOHN KIDWELL
Final 12/29/2022 OK to Issue CofO SEAN WIRCH
Service/Power Release 12/29/2022 Approved SEAN WIRCH