15025 W ALTATA DR 90272

Certificate Information: 15025 W ALTATA DR 90272

Application / Permit
20010-20000-03607
Plan Check / Job No.
B20VN13109
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW DETACHED REC. ROOM ,POOL BATH AND PATIO COVER AND TRELLIS (14'-0"X44'-7")
Permit Issued
Issued on 10/6/2021
Issuing Office
Current Status
Issued on 10/6/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/8/2020 APPLICANT
Assigned to Plan Check Engineer 11/5/2020 MOHAMMAD ESMAILI
Corrections Issued 11/7/2020 MOHAMMAD ESMAILI
Quality Review Completed 12/2/2020 OMID HEDAYAT
Building Plans Picked Up 12/2/2020 APPLICANT
Applicant returned to address corrections 9/23/2021 MOHAMMAD ESMAILI
Plan Check Approved 9/27/2021 MOHAMMAD ESMAILI
Issued 10/6/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/18/2020 NIKTA MOUSAVI
Roof/Waste drainage to street Cleared 12/18/2020 NIKTA MOUSAVI
Hydrant and Access approval Cleared 1/21/2021 JEREMY CARTER
Coastal Zone Cleared 6/14/2021 LOUIS ORTEGA
ZA Case Cleared 6/14/2021 LOUIS ORTEGA
ZI Cleared 6/14/2021 LOUIS ORTEGA
GPI Written Notices Cleared 9/27/2021 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 9/27/2021 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 11/24/2021 Conditional Approval KRISTEN CAUSEY
Footing/Foundation/Slab 1/31/2022 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 2/3/2022 Not Ready for Inspection ANDREW NAVE
Pre-Inspection 3/1/2022 Approved ANDREW NAVE
Footing/Foundation/Slab 3/21/2022 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 3/23/2022 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 3/31/2022 Partial Approval JOHN KIDWELL
PLUMBING-Rough 3/31/2022 Partial Approval JOHN KIDWELL
Underground Mechanical 3/31/2022 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 4/5/2022 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 4/13/2022 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 5/4/2022 Approved JOHN KIDWELL
Footing/Foundation/Slab 5/4/2022 Approved JOHN KIDWELL
ELECTRICAL-Rough 5/13/2022 Partial Approval JOHN KIDWELL
PLUMBING-Rough 5/13/2022 Approved JOHN KIDWELL
ELECTRICAL-Rough 5/20/2022 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Approved ANDREW NAVE
Insulation 6/28/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 7/18/2022 Approved ANDREW NAVE
Drywall Nailing 7/18/2022 Approved ANDREW NAVE
Green Building Rough 7/18/2022 Approved ANDREW NAVE
Verify Sprinkler Sign Off 7/18/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 7/20/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 7/28/2022 Approved BRENDAN LOONEY
Final 9/16/2022 Corrections Issued BRENDAN LOONEY
Green Building Final 9/16/2022 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Approved BRENDAN LOONEY
Service/Power Release 9/16/2022 Approved BRENDAN LOONEY
Smoke Detectors 9/16/2022 Approved BRENDAN LOONEY
Final 9/30/2022 Not Ready for Inspection KEVIN SARGSYAN
Final 10/5/2022 Conditional Approval BRENDAN LOONEY