10336 1/2 N SAMOA AVE 91042

Certificate Information: 10336 1/2 N SAMOA AVE 91042

Application / Permit
20010-20000-03588
Plan Check / Job No.
B20VN13097
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 48'7"X22'4" 2-STORY ADU WITH ATTACHED 19'6"X20'0" 2-STORY GARAGE PER LAMC 12.22 A.33(c) and (d) AND LOT TIE
Permit Issued
Issued on 2/14/2022
Issuing Office
Current Status
Issued on 2/14/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/6/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 MARVEL DELACRUZ
Corrections Issued 10/31/2020 MARVEL DELACRUZ
Quality Review Completed 11/13/2020 STEVEN KIM
Building Plans Picked Up 11/16/2020 APPLICANT
Applicant returned to address corrections 11/18/2021 MARVEL DELACRUZ
Plan Check Approved 1/26/2022 MARVEL DELACRUZ
Issued 2/14/2022 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/12/2021 TIMOTHY POWELL
Miscellaneous Cleared 4/13/2021 KENTON TRINH
ZA Case Cleared 4/13/2021 KENTON TRINH
Address approval Cleared 4/16/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/16/2021 ADRIAN CASTRO
Permit Cleared 4/16/2021 ADRIAN CASTRO
Sewer availability Cleared 4/16/2021 ADRIAN CASTRO
Specific Plan Cleared 4/19/2021 KORA MCNAUGHTON
ZI Cleared 4/19/2021 KORA MCNAUGHTON
Miscellaneous Cleared 5/17/2021 DANG NGUYEN
Hydrant and Access approval Cleared 5/22/2021 MATTHEW CRAIG
Trees in Parkway Cleared 7/1/2021 JOHN KIM
Low Impact Development Cleared 9/2/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/15/2021 GABRIEL ROBLES
GPI Written Notices Cleared 1/26/2022 MARVEL DELACRUZ
Green Code Cleared 1/26/2022 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng David; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/29/2022 Corrections Issued MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 10/18/2022 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 10/18/2022 Not Ready for Inspection MATTHEW NELSON
Footing/Foundation/Slab 10/19/2022 Corrections Issued MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 10/28/2022 Approved MATTHEW NELSON
Footing/Foundation/Slab 11/3/2022 Approved MATTHEW NELSON
Pre-Inspection 11/7/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 9/8/2023 Partial Approval WILLIAM WREN
Green Building Rough 9/8/2023 Not Ready for Inspection WILLIAM WREN
Verify Sprinkler Sign Off 9/8/2023 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 9/22/2023 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 11/20/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 3/15/2024 Approved WILLIAM WREN
ELECTRICAL-Rough 3/15/2024 Approved WILLIAM WREN
Green Building Rough 3/15/2024 Approved WILLIAM WREN
HVAC-Rough 3/15/2024 Approved WILLIAM WREN
PLUMBING-Rough 3/15/2024 Approved WILLIAM WREN
Sewer 3/15/2024 Not Ready for Inspection WILLIAM WREN
Verify Sprinkler Sign Off 3/15/2024 Approved WILLIAM WREN
Insulation 4/4/2024 Approved WILLIAM WREN
Drywall Nailing 4/26/2024 Approved DAVID ANDERSON
Shower Pan 4/2/2025 Approved WILLIAM WREN