6227 N ORION AVE 91411
Certificate Information: 6227 N ORION AVE 91411
- Application / Permit
- 20010-20000-03571
- Plan Check / Job No.
- B20VN12996
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 55' X 23' DETACHED ONE STORY ACCESSORY DWELLING UNIT LAMC 12.22 A.33(c) and (d). NFPA 13 D FIRE SPRINKELRS REQUIRED. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
- Permit Issued
- Issued on 2/3/2023
- Issuing Office
- Current Status
- CofO Issued on 8/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 11/1/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 2/2/2023 | RAMA DABADGE |
| Plan Check Approved | 2/2/2023 | RAMA DABADGE |
| Issued | 2/3/2023 | APPLICANT |
| CofO in Progress | 5/28/2024 | RYAN SALAZAR |
| Permit Finaled | 8/23/2024 | DANIEL ORRANTE |
| CofO Issued | 8/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/11/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 10/12/2022 | COLIN LOREDO |
| ZI | Cleared | 10/12/2022 | MIGUEL GAMBOA |
| Roof/Waste drainage to street | Cleared | 10/25/2022 | MEGAN GODINEZ |
| Hydrant and Access approval | Cleared | 1/24/2023 | LAVEON RIDER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/29/2023 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 9/6/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/13/2023 | Partial Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 10/13/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 10/13/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 10/13/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/13/2023 | Approved | RYAN SALAZAR |
| MERV13>=Rough | 10/13/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 10/13/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 10/13/2023 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 10/13/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 10/24/2023 | Approved | RYAN SALAZAR |
| Insulation | 10/24/2023 | Approved | RYAN SALAZAR |
| Underground Mechanical | 10/24/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Underground Mechanical | 10/31/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/22/2024 | Approved | RYAN SALAZAR |
| Final | 5/22/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 5/22/2024 | Approved | RYAN SALAZAR |
| MERV13>=Final | 5/22/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/22/2024 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 5/22/2024 | Approved | RYAN SALAZAR |
| Smoke Detectors | 5/22/2024 | Approved | RYAN SALAZAR |