6227 N ORION AVE 91411

Certificate Information: 6227 N ORION AVE 91411

Application / Permit
20010-20000-03571
Plan Check / Job No.
B20VN12996
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 55' X 23' DETACHED ONE STORY ACCESSORY DWELLING UNIT LAMC 12.22 A.33(c) and (d). NFPA 13 D FIRE SPRINKELRS REQUIRED. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
Permit Issued
Issued on 2/3/2023
Issuing Office
Current Status
CofO Issued on 8/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 JEROME MAGAT PALMA
Corrections Issued 11/1/2020 JEROME MAGAT PALMA
Plan Check Approved 2/2/2023 RAMA DABADGE
Plan Check Approved 2/2/2023 RAMA DABADGE
Issued 2/3/2023 APPLICANT
CofO in Progress 5/28/2024 RYAN SALAZAR
Permit Finaled 8/23/2024 DANIEL ORRANTE
CofO Issued 8/23/2024 DANIEL ORRANTE
Permit Finaled 8/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/11/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/12/2022 COLIN LOREDO
Sewer availability Cleared 10/12/2022 COLIN LOREDO
ZI Cleared 10/12/2022 MIGUEL GAMBOA
Roof/Waste drainage to street Cleared 10/25/2022 MEGAN GODINEZ
Hydrant and Access approval Cleared 1/24/2023 LAVEON RIDER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/29/2023 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 9/6/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/13/2023 Partial Inspection RYAN SALAZAR
ELECTRICAL-Rough 10/13/2023 Approved RYAN SALAZAR
Green Building Rough 10/13/2023 Approved RYAN SALAZAR
HVAC-Rough 10/13/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/13/2023 Approved RYAN SALAZAR
MERV13>=Rough 10/13/2023 Approved RYAN SALAZAR
PLUMBING-Rough 10/13/2023 Approved RYAN SALAZAR
Shower Pan 10/13/2023 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 10/13/2023 Approved RYAN SALAZAR
Drywall Nailing 10/24/2023 Approved RYAN SALAZAR
Insulation 10/24/2023 Approved RYAN SALAZAR
Underground Mechanical 10/24/2023 Not Ready for Inspection RYAN SALAZAR
Underground Mechanical 10/31/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 5/22/2024 Approved RYAN SALAZAR
Final 5/22/2024 OK to Issue CofO RYAN SALAZAR
Green Building Final 5/22/2024 Approved RYAN SALAZAR
MERV13>=Final 5/22/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/22/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 5/22/2024 Approved RYAN SALAZAR
Smoke Detectors 5/22/2024 Approved RYAN SALAZAR