Piling/Pier/Caisson
|
4/29/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
7/18/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Piling/Pier/Caisson
|
7/19/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Piling/Pier/Caisson
|
9/14/2022
|
Partial Inspection
|
RAUL BARAJAS
|
|
Deputy Other (see comments)
|
9/23/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
9/23/2022
|
Conditional Approval
|
RAUL BARAJAS
|
|
Piling/Pier/Caisson
|
12/7/2022
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
1/12/2023
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
1/17/2023
|
Conditional Approval
|
RUBEN SALAS
|
|
Footing/Foundation/Slab
|
1/18/2023
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
1/25/2023
|
Approved
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
4/27/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
5/9/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Deputy Shotcrete
|
5/11/2023
|
Conditional Approval
|
STUART CHAPMAN
|
|
Deputy Drilled-In Anchors
|
5/22/2023
|
Approved
|
STUART CHAPMAN
|
|
Deputy Shotcrete
|
5/22/2023
|
Approved
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
5/22/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Deputy Shotcrete
|
5/23/2023
|
Conditional Approval
|
STUART CHAPMAN
|
|
PLUMBING-Rough
|
6/7/2023
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Deputy Shotcrete
|
6/12/2023
|
Approved
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
6/12/2023
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
6/28/2023
|
Partial Approval
|
JOAQUIN GREENOUGH
|
|
Footing/Foundation/Slab
|
7/14/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
7/27/2023
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
8/18/2023
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
9/7/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Excavation/Setback/Form/Re-Bar
|
9/18/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Structural Steel Frame
|
9/18/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
PLUMBING-Rough
|
9/22/2023
|
Partial Approval
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
10/5/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
10/11/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Masonry Wall/Backfill
|
10/11/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
10/20/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Green Building Rough
|
10/20/2023
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Reinforced Concrete Frame
|
10/20/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Verify Sprinkler Sign Off
|
10/20/2023
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Deputy Reinf. Concrete
|
10/30/2023
|
Conditional Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
10/30/2023
|
Partial Approval
|
RAUL BARAJAS
|
|
Grading Pre-Inspection
|
11/20/2023
|
Not Ready for Inspection
|
ALEXANDER HELFER
|
|
Deputy Steel/Welding
|
12/8/2023
|
Conditional Approval
|
STUART CHAPMAN
|
|
Deputy Steel/Welding
|
12/27/2023
|
Conditional Approval
|
STUART CHAPMAN
|
|
Piling/Pier/Caisson
|
1/5/2024
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Piling/Pier/Caisson
|
1/10/2024
|
Partial Approval
|
STUART CHAPMAN
|
|
Deputy Reinf. Concrete
|
1/17/2024
|
Conditional Approval
|
STUART CHAPMAN
|
|
Deputy Reinf. Concrete
|
1/26/2024
|
Conditional Approval
|
STUART CHAPMAN
|
|
Deputy Reinf. Concrete
|
1/29/2024
|
Approved
|
STUART CHAPMAN
|
|
Deputy Reinf. Concrete
|
1/30/2024
|
Conditional Approval
|
ROY SPAULDING
|
|
Deputy Reinf. Concrete
|
1/31/2024
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
2/8/2024
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
2/14/2024
|
Conditional Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
2/15/2024
|
Approved
|
ROY SPAULDING
|
|
Deputy Reinf. Concrete
|
2/23/2024
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
2/28/2024
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
2/28/2024
|
Conditional Approval
|
ROY SPAULDING
|
|
Deputy Reinf. Concrete
|
2/29/2024
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
3/1/2024
|
Conditional Approval
|
RAUL BARAJAS
|
|
Green Building Rough
|
3/6/2024
|
Not Ready for Inspection
|
ROY SPAULDING
|
|
Reinforced Concrete Frame
|
3/6/2024
|
Partial Approval
|
ROY SPAULDING
|
|
Verify Sprinkler Sign Off
|
3/6/2024
|
Not Ready for Inspection
|
ROY SPAULDING
|
|
Excavation/Setback/Form/Re-Bar
|
3/7/2024
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
4/9/2024
|
Approved
|
ROY SPAULDING
|
|
Underground Mechanical
|
4/10/2024
|
Partial Inspection
|
BRIAN SULLIVAN
|
|
Green Building Rough
|
5/9/2024
|
Not Ready for Inspection
|
JOAQUIN GREENOUGH
|
|
Reinforced Concrete Frame
|
5/9/2024
|
Corrections Issued
|
JOAQUIN GREENOUGH
|
|
Verify Sprinkler Sign Off
|
5/9/2024
|
Not Ready for Inspection
|
JOAQUIN GREENOUGH
|
|
Deputy Steel/Welding
|
5/16/2024
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
5/24/2024
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
5/28/2024
|
Conditional Approval
|
BRIAN SULLIVAN
|
|
Piling/Pier/Caisson
|
5/30/2024
|
Partial Approval
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
6/3/2024
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
|
Excavation/Setback/Form/Re-Bar
|
6/4/2024
|
Approved
|
ROY SPAULDING
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/5/2024
|
Conditional Approval
|
RAUL BARAJAS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/6/2024
|
Partial Inspection
|
BRENDAN MORELLI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/10/2024
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/20/2024
|
Partial Inspection
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
6/21/2024
|
Conditional Approval
|
RAUL BARAJAS
|
|
HVAC-Rough
|
7/3/2024
|
Partial Approval
|
RAUL BARAJAS
|
|
ELECTRICAL-Rough
|
7/9/2024
|
Corrections Issued
|
BRIAN SULLIVAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/17/2024
|
Partial Approval
|
ROY SPAULDING
|
|
Excavation/Setback/Form/Re-Bar
|
7/22/2024
|
Corrections Issued
|
JOAQUIN GREENOUGH
|
|
Excavation/Setback/Form/Re-Bar
|
7/24/2024
|
Partial Approval
|
RAUL BARAJAS
|
|
BUILDING-Rough-Frame
|
8/26/2024
|
Corrections Issued
|
RAUL BARAJAS
|
|
Green Building Rough
|
8/26/2024
|
Approved
|
RAUL BARAJAS
|
|
Verify Sprinkler Sign Off
|
8/26/2024
|
Partial Approval
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
9/10/2024
|
Partial Approval
|
CRAIG VAUGHAN
|
|
PLUMBING-Rough
|
9/17/2024
|
Conditional Approval
|
RAUL BARAJAS
|
|
Drywall Nailing
|
10/4/2024
|
Partial Approval
|
BRENDAN MORELLI
|
|
Interior/Exterior Lathing
|
10/23/2024
|
Approved
|
BRIAN SULLIVAN
|
|
BUILDING-Rough-Frame
|
11/14/2024
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
ELECTRICAL-Rough
|
11/14/2024
|
Approved
|
BRIAN SULLIVAN
|
|
HVAC-Rough
|
11/14/2024
|
Approved
|
BRIAN SULLIVAN
|
|
Interior/Exterior Lathing
|
11/14/2024
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Verify Sprinkler Sign Off
|
11/14/2024
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
Wood Frame
|
11/14/2024
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
Service/Power Release
|
2/26/2025
|
Approved
|
ROY SPAULDING
|
|
Gas Test
|
5/2/2025
|
Approved
|
ROY SPAULDING
|
|
PLUMBING-Final
|
5/2/2025
|
Not Ready for Inspection
|
ROY SPAULDING
|
|
HVAC-Final
|
5/5/2025
|
Approved
|
ROY SPAULDING
|
|
PLUMBING-Final
|
5/5/2025
|
Partial Approval
|
ROY SPAULDING
|
|
ELECTRICAL-Final
|
5/6/2025
|
Partial Approval
|
ROY SPAULDING
|
|
BUILDING-Rough-Frame
|
5/8/2025
|
Approved
|
ROY SPAULDING
|
|
Drywall Nailing
|
5/8/2025
|
Approved
|
ROY SPAULDING
|
|
Final
|
5/8/2025
|
Corrections Issued
|
ROY SPAULDING
|
|
Green Building Final
|
5/8/2025
|
Approved
|
ROY SPAULDING
|
|
Green Building Rough
|
5/8/2025
|
Approved
|
ROY SPAULDING
|
|
Reinforced Concrete Frame
|
5/8/2025
|
Approved
|
ROY SPAULDING
|
|
SGSOV-Seismic Gas S/O Valve
|
5/8/2025
|
SGSOV Approved
|
ROY SPAULDING
|
|
Smoke Detectors
|
5/8/2025
|
Not Ready for Inspection
|
ROY SPAULDING
|
|
Verify Sprinkler Sign Off
|
5/8/2025
|
Approved
|
ROY SPAULDING
|
|
Final
|
5/29/2025
|
Corrections Issued
|
ROY SPAULDING
|
|
Smoke Detectors
|
5/29/2025
|
Approved
|
ROY SPAULDING
|
|
Final
|
9/16/2025
|
OK to Issue CofO
|
ROY SPAULDING
|