7735 N AGNES AVE 91605
Certificate Information: 7735 N AGNES AVE 91605
- Application / Permit
- 20010-20000-03542
- Plan Check / Job No.
- B20VN12940
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 35' X 27' DETACHED ACCESSORY DWELLING UNIT LAMC 12.22.A.33 (C) AND (E), ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/2/2021
- Issuing Office
- Current Status
- CofO Issued on 5/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2020 | RARES BODEA |
| Corrections Issued | 10/12/2020 | RARES BODEA |
| Building Plans Picked Up | 10/14/2020 | APPLICANT |
| Plan Check Approved | 5/12/2021 | RARES BODEA |
| Issued | 6/2/2021 | APPLICANT |
| CofO in Progress | 2/17/2022 | CHRISTOPHER DELLEFIELD |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
| CofO Issued | 5/14/2022 | MICHAEL SMITH |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| "T" removal | Cleared | 12/30/2020 | DANG NGUYEN |
| Low Impact Development | Cleared | 12/30/2020 | JORGE MEJIA LEMUS |
| Address approval | Cleared | 1/5/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/6/2021 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 2/11/2021 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 3/8/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mejia,, Fernando Finuliar; Lic. No.: C54382 | 8305 DUCOR AVE WEST HILLS, CA 91304 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/27/2021 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 8/9/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 8/11/2021 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 8/11/2021 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 8/17/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 9/10/2021 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 9/10/2021 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 9/10/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 9/10/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 9/10/2021 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 9/10/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 9/15/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 9/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 9/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 9/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 9/22/2021 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/22/2021 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 9/29/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 9/29/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 11/30/2021 | Approved | WILLIAM WREN |
| Shower Pan | 11/30/2021 | Approved | WILLIAM WREN |
| Sewer | 12/7/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 12/7/2021 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 1/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 1/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 1/28/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 1/28/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 1/28/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 1/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 1/28/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 1/28/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 1/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 1/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 2/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 2/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 2/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 2/1/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 2/17/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 2/17/2022 | Approved | CHRISTOPHER DELLEFIELD |