4832 N GENTRY AVE 91607

Certificate Information: 4832 N GENTRY AVE 91607

Application / Permit
20010-20000-03537
Plan Check / Job No.
B20VN12929
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW REC. ROOM (13'-00"X19'-6")
Permit Issued
Issued on 3/3/2021
Issuing Office
Current Status
CofO Issued on 2/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2020 APPLICANT
Assigned to Plan Check Engineer 10/8/2020 MOHAMMAD ESMAILI
Corrections Issued 10/11/2020 MOHAMMAD ESMAILI
Quality Review Completed 10/14/2020 OMID HEDAYAT
Building Plans Picked Up 10/21/2020 APPLICANT
Plan Check Approved 3/3/2021 MOHAMMAD ESMAILI
Issued 3/3/2021 APPLICANT
CofO in Progress 1/26/2022 RICHARD DOCKUS
Permit Finaled 2/12/2022 MICHAEL SMITH
CofO Issued 2/12/2022 MICHAEL SMITH
Permit Finaled 2/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 11/17/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/18/2020 ADRIAN CASTRO
Specific Plan Cleared 11/18/2020 OLGA AYALA
ZI Cleared 11/18/2020 OLGA AYALA
ZI Cleared 11/18/2020 OLGA AYALA
Low Impact Development Cleared 12/18/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/28/2020 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/5/2021 Partial Approval JOHN HAYES
Footing/Foundation/Slab 4/13/2021 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/11/2021 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Partial Approval THOMAS FINNILA
HVAC-Rough 5/18/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/18/2021 Approved THOMAS FINNILA
ELECTRICAL-Rough 5/26/2021 Approved THOMAS FINNILA
HVAC-Rough 5/26/2021 Approved THOMAS FINNILA
Shower Pan 5/26/2021 Not Ready for Inspection THOMAS FINNILA
Shower Pan 6/3/2021 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/9/2021 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 6/14/2021 Conditional Approval THOMAS FINNILA
Green Building Rough 6/14/2021 Conditional Approval THOMAS FINNILA
Verify Sprinkler Sign Off 6/14/2021 Approved THOMAS FINNILA
BUILDING-Rough-Frame 6/21/2021 Approved THOMAS FINNILA
Green Building Rough 6/21/2021 Approved THOMAS FINNILA
Insulation 6/21/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 6/21/2021 Partial Approval THOMAS FINNILA
Drywall Nailing 6/25/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 6/25/2021 Approved THOMAS FINNILA
Drywall Nailing 6/30/2021 Approved THOMAS FINNILA
HVAC-Final 12/9/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 12/9/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 12/10/2021 Corrections Issued JACK KARGODORIAN
Smoke Detectors 12/10/2021 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 12/16/2021 Approved THOMAS FINNILA
PLUMBING-Final 12/16/2021 Partial Approval THOMAS FINNILA
PLUMBING-Final 12/23/2021 Approved THOMAS FINNILA
ELECTRICAL-Final 1/5/2022 Approved THOMAS FINNILA
Final 1/11/2022 Not Ready for Inspection THOMAS FINNILA
Green Building Final 1/11/2022 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 1/11/2022 SGSOV Approved THOMAS FINNILA
Smoke Detectors 1/11/2022 Approved THOMAS FINNILA
Pre-Inspection 1/14/2022 Approved THOMAS FINNILA
Service/Power Release 1/14/2022 Not Ready for Inspection THOMAS FINNILA
Final 1/20/2022 Corrections Issued MISAEL ESPARZA
Service/Power Release 1/20/2022 Corrections Issued MISAEL ESPARZA
Final 1/25/2022 OK to Issue CofO RICHARD DOCKUS
Service/Power Release 1/25/2022 Approved RICHARD DOCKUS