5146 N GREENBUSH AVE 91423
Certificate Information: 5146 N GREENBUSH AVE 91423
- Application / Permit
- 20010-20000-03531
- Plan Check / Job No.
- B20VN12923
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 50' X 41' 8" IRR.-SHAPE 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 22' X 20' 2-CAR GARAGE, 6' 7" X 8' 7" ENTRY PORCH AND 13' X 26' OPEN REAR TRELLIS. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 7/1/2021
- Issuing Office
- Current Status
- CofO Issued on 4/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 10/12/2020 | GURUNATH NESARAJAH |
| Quality Review Completed | 10/14/2020 | OMID HEDAYAT |
| Applicant returned to address corrections | 3/16/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 4/14/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 4/28/2021 | APPLICANT |
| Issued | 7/1/2021 | APPLICANT |
| CofO in Progress | 3/15/2023 | MISAEL ESPARZA |
| Permit Finaled | 4/4/2023 | DANIEL ORRANTE |
| CofO Issued | 4/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2020 | GUILLERMO PETRA |
| Permit | Cleared | 10/23/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/23/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 11/23/2020 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 11/24/2020 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 12/10/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 12/16/2020 | GABRIEL ROBLES |
| Frnt yard landscape/Water mgmt | Cleared | 1/27/2021 | MIGUEL GAMBOA |
| ZI | Cleared | 1/27/2021 | MIGUEL GAMBOA |
| Trees in Parkway | Cleared | 2/8/2021 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/21/2021 | Approved | MISAEL ESPARZA |
| Sewer | 11/2/2021 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 11/4/2021 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 11/8/2021 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 11/15/2021 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 11/16/2021 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 11/22/2021 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/21/2022 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 9/21/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/26/2022 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 9/26/2022 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/29/2022 | Conditional Approval | MISAEL ESPARZA |
| Green Building Rough | 9/29/2022 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 9/29/2022 | Conditional Approval | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 9/29/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 10/3/2022 | Approved | WILLIAM WREN |
| Insulation | 10/13/2022 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 10/17/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 10/21/2022 | Corrections Issued | MISAEL ESPARZA |
| Drywall Nailing | 12/8/2022 | Approved | MISAEL ESPARZA |
| Service/Power Release | 12/8/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/8/2023 | Approved | MISAEL ESPARZA |
| Final | 2/8/2023 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/8/2023 | Approved | MISAEL ESPARZA |
| Green Building Final | 2/8/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/8/2023 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 2/8/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 2/8/2023 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 2/8/2023 | Approved | MISAEL ESPARZA |
| Final | 3/9/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 3/9/2023 | Approved | MISAEL ESPARZA |
| Service/Power Release | 3/9/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 3/14/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 3/14/2023 | Approved | MISAEL ESPARZA |