5146 N GREENBUSH AVE 91423

Certificate Information: 5146 N GREENBUSH AVE 91423

Application / Permit
20010-20000-03531
Plan Check / Job No.
B20VN12923
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 50' X 41' 8" IRR.-SHAPE 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 22' X 20' 2-CAR GARAGE, 6' 7" X 8' 7" ENTRY PORCH AND 13' X 26' OPEN REAR TRELLIS. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
CofO Issued on 4/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2020 APPLICANT
Assigned to Plan Check Engineer 10/8/2020 GURUNATH NESARAJAH
Corrections Issued 10/12/2020 GURUNATH NESARAJAH
Quality Review Completed 10/14/2020 OMID HEDAYAT
Applicant returned to address corrections 3/16/2021 GURUNATH NESARAJAH
Plan Check Approved 4/14/2021 GURUNATH NESARAJAH
Building Plans Picked Up 4/28/2021 APPLICANT
Issued 7/1/2021 APPLICANT
CofO in Progress 3/15/2023 MISAEL ESPARZA
Permit Finaled 4/4/2023 DANIEL ORRANTE
CofO Issued 4/4/2023 DANIEL ORRANTE
Permit Finaled 4/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/23/2020 GUILLERMO PETRA
Permit Cleared 10/23/2020 GUILLERMO PETRA
Sewer availability Cleared 10/23/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 11/23/2020 MATTHEW CRAIG
Construction near power lines Cleared 11/24/2020 WALTER RAMIREZ
Low Impact Development Cleared 12/10/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 12/16/2020 GABRIEL ROBLES
Frnt yard landscape/Water mgmt Cleared 1/27/2021 MIGUEL GAMBOA
ZI Cleared 1/27/2021 MIGUEL GAMBOA
Trees in Parkway Cleared 2/8/2021 JOHN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/21/2021 Approved MISAEL ESPARZA
Sewer 11/2/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 11/4/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 11/8/2021 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 11/15/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 11/16/2021 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 11/22/2021 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/21/2022 Corrections Issued MISAEL ESPARZA
HVAC-Rough 9/21/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/26/2022 Approved MISAEL ESPARZA
HVAC-Rough 9/26/2022 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 9/29/2022 Conditional Approval MISAEL ESPARZA
Green Building Rough 9/29/2022 Approved MISAEL ESPARZA
HVAC-Rough 9/29/2022 Conditional Approval MISAEL ESPARZA
Verify Sprinkler Sign Off 9/29/2022 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 10/3/2022 Approved WILLIAM WREN
Insulation 10/13/2022 Corrections Issued MISAEL ESPARZA
Insulation 10/17/2022 Approved MISAEL ESPARZA
Drywall Nailing 10/21/2022 Corrections Issued MISAEL ESPARZA
Drywall Nailing 12/8/2022 Approved MISAEL ESPARZA
Service/Power Release 12/8/2022 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 2/8/2023 Approved MISAEL ESPARZA
Final 2/8/2023 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 2/8/2023 Approved MISAEL ESPARZA
Green Building Final 2/8/2023 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/8/2023 SGSOV Approved MISAEL ESPARZA
Service/Power Release 2/8/2023 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 2/8/2023 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 2/8/2023 Approved MISAEL ESPARZA
Final 3/9/2023 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 3/9/2023 Approved MISAEL ESPARZA
Service/Power Release 3/9/2023 Corrections Issued MISAEL ESPARZA
Final 3/14/2023 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 3/14/2023 Approved MISAEL ESPARZA