8806 N ENFIELD AVE 91325
Certificate Information: 8806 N ENFIELD AVE 91325
- Application / Permit
- 20010-20000-03530
- Plan Check / Job No.
- B20VN12920
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 48' X 31' IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 4/15/2021
- Issuing Office
- Current Status
- CofO Issued on 2/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2020 | SELLA BENYAMIN |
| Corrections Issued | 10/15/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 10/16/2020 | APPLICANT |
| Issued | 4/15/2021 | APPLICANT |
| CofO in Progress | 2/7/2022 | MICHAEL TEMPLE |
| CofO Issued | 2/7/2022 | MICHAEL SMITH |
| Permit Finaled | 2/7/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/22/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 10/26/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 11/19/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 1/12/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/23/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 3/11/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/7/2021 | Corrections Issued | MARK JOHNSON |
| Footing/Foundation/Slab | 5/14/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 7/8/2021 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2021 | Approved | JACK KARGODORIAN |
| Green Building Rough | 7/8/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 7/8/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 7/8/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 7/8/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 7/8/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 7/20/2021 | Corrections Issued | JEFFREY PARD |
| Green Building Rough | 7/20/2021 | Not Ready for Inspection | JEFFREY PARD |
| Interior/Exterior Lathing | 7/20/2021 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 7/20/2021 | Not Ready for Inspection | JEFFREY PARD |
| Rough-Elec/Plmb/HVAC | 7/20/2021 | Not Ready for Inspection | JEFFREY PARD |
| Verify Sprinkler Sign Off | 7/20/2021 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 7/22/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 7/22/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 7/22/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 7/22/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 7/26/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 7/26/2021 | Approved | MARK JOHNSON |
| Verify Sprinkler Sign Off | 7/26/2021 | Approved | MARK JOHNSON |
| Insulation | 8/2/2021 | Approved | AMY COLIN |
| Drywall Nailing | 8/11/2021 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 10/20/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Final | 11/2/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Final | 11/2/2021 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Final | 11/18/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 11/18/2021 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 11/18/2021 | Approved | JACK KARGODORIAN |
| HVAC-Final | 11/18/2021 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 11/18/2021 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2021 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 11/18/2021 | Not Required | JACK KARGODORIAN |
| Smoke Detectors | 11/18/2021 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 12/2/2021 | Approved | MARK JOHNSON |
| Final | 12/2/2021 | Corrections Issued | MARK JOHNSON |
| HVAC-Final | 12/2/2021 | Approved | MARK JOHNSON |
| PLUMBING-Final | 12/2/2021 | Approved | MARK JOHNSON |
| Pre-Inspection | 1/20/2022 | Conditional Approval | MICHAEL TEMPLE |
| Final | 2/7/2022 | OK to Issue CofO | MICHAEL TEMPLE |