20751 W ACORN CIR UNIT# 155 91326

Certificate Information: 20751 W ACORN CIR UNIT# 155 91326

Application / Permit
20010-20000-03513
Plan Check / Job No.
B20VN12916
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(35) Condo-Single Family
Work Description
PROPOSE TWO STORY SFD-CONDO WITH ATTACHED GARAGE _ PER STANDARD PLAN #646 PLAN 2C_ BUILDING TO BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 4/12/2021
Issuing Office
Current Status
CofO Issued on 1/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2020 APPLICANT
Assigned to Plan Check Engineer 10/8/2020 DAWN MC NULTY
Corrections Issued 10/19/2020 DAWN MC NULTY
Quality Review Completed 10/20/2020 CHON CHIO KUO
Building Plans Picked Up 10/20/2020 APPLICANT
Plan Check Approved 3/24/2021 DAWN MC NULTY
Issued 4/12/2021 APPLICANT
CofO in Progress 1/21/2022 HENRY KIM
CofO Issued 1/21/2022 MICHAEL SMITH
Permit Finaled 1/21/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/29/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/29/2021 LEE GUILBEAUX
Permit Cleared 1/29/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/29/2021 LEE GUILBEAUX
Sewer availability Cleared 1/29/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/29/2021 LEE GUILBEAUX
"T" removal Cleared 2/1/2021 DENZEL HENDERSON
APC Cleared 2/1/2021 DENZEL HENDERSON
APC Cleared 2/1/2021 DENZEL HENDERSON
CPC Cleared 2/1/2021 DENZEL HENDERSON
Frnt yard landscape/Water mgmt Cleared 2/1/2021 DENZEL HENDERSON
Miscellaneous Cleared 2/1/2021 DENZEL HENDERSON
Opn space landscape/Water mgmt Cleared 2/1/2021 DENZEL HENDERSON
Specific Plan Cleared 2/1/2021 DENZEL HENDERSON
Tract Map conditions Cleared 2/1/2021 DENZEL HENDERSON
Tract Map conditions Cleared 2/1/2021 DENZEL HENDERSON
Tract Map conditions Cleared 2/1/2021 DENZEL HENDERSON
Tract Map conditions Cleared 2/1/2021 DENZEL HENDERSON
Low Impact Development Cleared 2/3/2021 AMMAR ELTAWIL
Hydrant and Access approval Cleared 2/6/2021 ROBERT DUFF
ZA Case Cleared 2/16/2021 DENZEL HENDERSON

Contact Information

Architect Falese, Debra Suzanne; Lic. No.: C24900 2943 PULLMAN SUITE A      SANTA ANA, CA 92705
Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLLBROTHERS - TA   ATTN: GATES/LEGAL    FORT WASHINGTON, PA 19034
Engineer Christian, Dale Alan; Lic. No.: S2705 1744 W KATELLA AVENUE SUITE 107      ORANGE, CA 92867
Engineer Hattar, Basil Ibrahim; Lic. No.: GE2734 3525 PARK MEADOW CT      PALMDALE, CA 93551
Engineer Kim, Kevin Chae; Lic. No.: C53821 2349 N CAMPUS AVENUE      UPLAND, CA 91784
Engineer Nelson, William Mc Kee; Lic. No.: S3417 5 DELLWOOD      DOVE CANYON, CA 92679

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/2/2021 Approved SEAN WIRCH
Footing/Foundation/Slab 6/18/2021 Approved SEAN WIRCH
Sewer 6/28/2021 Approved SEAN WIRCH
Underground Mechanical 7/1/2021 Not Ready for Inspection SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 7/20/2021 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 8/6/2021 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Approved SEAN WIRCH
Interior/Exterior Lathing 9/17/2021 Partial Approval JOSEPH SAGEN
BUILDING-Rough-Frame 9/20/2021 Approved SEAN WIRCH
ELECTRICAL-Rough 9/20/2021 Approved SEAN WIRCH
Green Building Rough 9/20/2021 Approved SEAN WIRCH
HVAC-Rough 9/20/2021 Approved SEAN WIRCH
PLUMBING-Rough 9/20/2021 Approved SEAN WIRCH
Verify Sprinkler Sign Off 9/20/2021 Approved SEAN WIRCH
Drywall Nailing 10/1/2021 Approved SEAN WIRCH
Interior/Exterior Lathing 10/27/2021 Partial Approval JOSEPH SAGEN
Gas Test 11/1/2021 Not Ready for Inspection HENRY KIM
Gas Test 11/4/2021 Not Ready for Inspection JOSEPH SAGEN
Gas Test 11/15/2021 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 11/16/2021 SGSOV Not Ready SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 11/22/2021 SGSOV Approved SEAN WIRCH
Service/Power Release 11/22/2021 Approved SEAN WIRCH
ELECTRICAL-Final 1/10/2022 Not Ready for Inspection HENRY KIM
Final 1/10/2022 Not Ready for Inspection HENRY KIM
Green Building Final 1/10/2022 Not Ready for Inspection HENRY KIM
HVAC-Final 1/10/2022 Not Ready for Inspection HENRY KIM
PLUMBING-Final 1/10/2022 Not Ready for Inspection HENRY KIM
Smoke Detectors 1/10/2022 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 1/18/2022 Corrections Issued HENRY KIM
Final 1/18/2022 Not Ready for Inspection HENRY KIM
Green Building Final 1/18/2022 Approved HENRY KIM
HVAC-Final 1/18/2022 Approved HENRY KIM
PLUMBING-Final 1/18/2022 Approved HENRY KIM
Smoke Detectors 1/18/2022 Approved HENRY KIM
ELECTRICAL-Final 1/20/2022 Approved HENRY KIM
Final 1/20/2022 OK to Issue CofO HENRY KIM