20717 W CHESTNUT CIR UNIT# 252 91326
Certificate Information: 20717 W CHESTNUT CIR UNIT# 252 91326
- Application / Permit
- 20010-20000-03494
- Plan Check / Job No.
- B20VN12897
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (35) Condo-Single Family
- Work Description
- TWO STORY SFD-CONDO WITH ATTACHED 2 CAR GARAGE (STANDARD PLAN#646_PLAN 2B) _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 5/7/2021
- Issuing Office
- Current Status
- CofO Issued on 2/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | DAWN MC NULTY |
| Corrections Issued | 10/28/2020 | DAWN MC NULTY |
| Quality Review Completed | 10/29/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 10/29/2020 | APPLICANT |
| Applicant returned to address corrections | 4/7/2021 | DAWN MC NULTY |
| Plan Check Approved | 4/12/2021 | DAWN MC NULTY |
| Issued | 5/7/2021 | APPLICANT |
| CofO in Progress | 2/11/2022 | HENRY KIM |
| Permit Finaled | 2/12/2022 | MICHAEL SMITH |
| CofO Issued | 2/12/2022 | MICHAEL SMITH |
| Permit Finaled | 2/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/7/2021 | AMMAR ELTAWIL |
| Hydrant and Access approval | Cleared | 1/14/2021 | MATTHEW CRAIG |
| Address approval | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Permit | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/27/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/27/2021 | LEE GUILBEAUX |
| "T" removal | Cleared | 1/29/2021 | DENZEL HENDERSON |
| CPC | Cleared | 1/29/2021 | DENZEL HENDERSON |
| CPC | Cleared | 1/29/2021 | DENZEL HENDERSON |
| Miscellaneous | Cleared | 1/29/2021 | DENZEL HENDERSON |
| Private street | Cleared | 1/29/2021 | DENZEL HENDERSON |
| Specific Plan | Cleared | 1/29/2021 | DENZEL HENDERSON |
| Tract Map conditions | Cleared | 1/29/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 1/29/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 1/29/2021 | DENZEL HENDERSON |
Contact Information
| Architect | Falese, Debra Suzanne; Lic. No.: C24900 | 2943 PULLMAN SUITE A SANTA ANA, CA 92705 |
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 250 GIBRALTAR RD ATTN: GATES/LEGAL HORSHAM, PA 19044 |
| Engineer | Christian, Dale Alan; Lic. No.: S2705 | 1744 W KATELLA AVENUE SUITE 107 ORANGE, CA 92867 |
| Engineer | Hattar, Basil Ibrahim; Lic. No.: GE2734 | 3525 PARK MEADOW CT PALMDALE, CA 93551 |
| Engineer | Kim, Kevin Chae; Lic. No.: C53821 | 2349 N CAMPUS AVENUE UPLAND, CA 91784 |
| Engineer | Nelson, William Mc Kee; Lic. No.: S3417 | 5 DELLWOOD DOVE CANYON, CA 92679 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/3/2021 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 6/25/2021 | Approved | SEAN WIRCH |
| Sewer | 7/7/2021 | Not Ready for Inspection | SEAN WIRCH |
| Underground Mechanical | 7/14/2021 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2021 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2021 | Partial Approval | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 10/12/2021 | Approved | JOSEPH SAGEN |
| ELECTRICAL-Rough | 10/12/2021 | Approved | JOSEPH SAGEN |
| Green Building Rough | 10/12/2021 | Approved | JOSEPH SAGEN |
| HVAC-Rough | 10/12/2021 | Approved | JOSEPH SAGEN |
| Interior/Exterior Lathing | 10/12/2021 | Partial Approval | JOSEPH SAGEN |
| PLUMBING-Rough | 10/12/2021 | Approved | JOSEPH SAGEN |
| Verify Sprinkler Sign Off | 10/12/2021 | Approved | JOSEPH SAGEN |
| Drywall Nailing | 10/25/2021 | Approved | JOSEPH SAGEN |
| Gas Test | 11/19/2021 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 11/19/2021 | Approved | SEAN WIRCH |
| Gas Test | 11/22/2021 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 12/2/2021 | SGSOV Approved | HENRY KIM |
| Service/Power Release | 12/17/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 2/2/2022 | Approved | HENRY KIM |
| Final | 2/2/2022 | Corrections Issued | HENRY KIM |
| Green Building Final | 2/2/2022 | Approved | HENRY KIM |
| HVAC-Final | 2/2/2022 | Approved | HENRY KIM |
| PLUMBING-Final | 2/2/2022 | Not Ready for Inspection | HENRY KIM |
| Smoke Detectors | 2/2/2022 | Approved | HENRY KIM |
| ELECTRICAL-Final | 2/10/2022 | Approved | HENRY KIM |
| Final | 2/10/2022 | OK to Issue CofO | HENRY KIM |
| HVAC-Final | 2/10/2022 | Approved | HENRY KIM |
| PLUMBING-Final | 2/10/2022 | Approved | HENRY KIM |
| Sewer | 2/11/2022 | Approved | HENRY KIM |