6051 N FAIR AVE 91606

Certificate Information: 6051 N FAIR AVE 91606

Application / Permit
20010-20000-03487
Plan Check / Job No.
B20VN12890
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 35'4" X 22'2" TWO STORY DETACHED ACCESSORY DEWELING UNIT WITH 12'11" X 5'11" OPEN TRELLIS ATTACHED , NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING - SEE COMMENTS
Permit Issued
Issued on 12/29/2020
Issuing Office
Current Status
CofO Issued on 7/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 RARES BODEA
Plans on Hold 10/24/2020 RARES BODEA
Hold Released 10/26/2020 RARES BODEA
Corrections Issued 10/26/2020 RARES BODEA
Quality Review Completed 10/29/2020 STEVEN KIM
Building Plans Picked Up 10/29/2020 APPLICANT
Plan Check Approved 12/16/2020 RARES BODEA
Issued 12/29/2020 APPLICANT
CofO in Progress 6/17/2021 ARAM AVEDISIAN
Permit Finaled 7/17/2021 MICHAEL SMITH
CofO Issued 7/17/2021 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 11/18/2020 WALTER RAMIREZ
Construction within easement Cleared 11/18/2020 WALTER RAMIREZ
Hydrant and Access approval Cleared 11/19/2020 MATTHEW CRAIG
Address approval Cleared 11/24/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/2/2020 GUILLERMO PETRA
Sewer availability Cleared 12/2/2020 GUILLERMO PETRA
Low Impact Development Cleared 12/8/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 12/14/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Wassef,, Mena Maher Salama; Lic. No.: C84979 28131 VALERIO CT      VALENCIA, CA 91354

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/31/2020 Partial Approval DANIEL DREW
Footing/Foundation/Slab 1/6/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 2/9/2021 Approved DANIEL DREW
HVAC-Rough 2/9/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 2/19/2021 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Rough 2/19/2021 Approved DANIEL DREW
Gas Test 2/19/2021 Approved DANIEL DREW
Green Building Rough 2/19/2021 Corrections Issued DANIEL DREW
Interior/Exterior Lathing 2/19/2021 Approved DANIEL DREW
PLUMBING-Rough 2/19/2021 Approved DANIEL DREW
Verify Sprinkler Sign Off 2/19/2021 Not Ready for Inspection DANIEL DREW
BUILDING-Rough-Frame 2/24/2021 Approved DANIEL DREW
Green Building Rough 2/24/2021 Approved DANIEL DREW
Insulation 2/24/2021 Approved DANIEL DREW
Verify Sprinkler Sign Off 2/24/2021 Approved DANIEL DREW
Drywall Nailing 3/1/2021 Approved DANIEL DREW
Interior/Exterior Lathing 3/1/2021 Approved DANIEL DREW
Sewer 3/15/2021 Approved DANIEL DREW
Underground Mechanical 3/15/2021 Approved DANIEL DREW
Service/Power Release 4/6/2021 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Final 4/23/2021 Approved DANIEL DREW
Green Building Final 4/23/2021 Approved DANIEL DREW
HVAC-Final 4/23/2021 Approved DANIEL DREW
PLUMBING-Final 4/23/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 4/23/2021 SGSOV Approved DANIEL DREW
Smoke Detectors 4/23/2021 Approved DANIEL DREW
Final 6/10/2021 Corrections Issued JOHN HAYES
Service/Power Release 6/10/2021 Not Ready for Inspection JOHN HAYES
Final 6/17/2021 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 6/17/2021 Approved ARAM AVEDISIAN