16629 1/2 W TUBA ST 91343
Certificate Information: 16629 1/2 W TUBA ST 91343
- Application / Permit
- 20010-20000-03457
- Plan Check / Job No.
- B20VN12797
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY STATE-APPROVED PRE-MANUFACTURED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c) & (d)
- Permit Issued
- Issued on 1/7/2021
- Issuing Office
- Current Status
- CofO Issued on 9/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/13/2020 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 10/15/2020 | APPLICANT |
| Plan Check Approved | 12/10/2020 | NILOOFAR MEHRAIN |
| Issued | 1/7/2021 | APPLICANT |
| CofO in Progress | 8/31/2022 | JAVIER RAMOS JR |
| Permit Finaled | 9/3/2022 | DEROLD HAUFF |
| CofO Issued | 9/3/2022 | DEROLD HAUFF |
| Permit Finaled | 9/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 11/4/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 11/5/2020 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 11/5/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 1/6/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wilson,, Yvette Marie; Lic. No.: C60245 | 1100 MAIN ST STE A WATSONVILLE, CA 95076 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Final | 12/6/2021 | Not Ready for Inspection | MARK JOHNSON |
| Footing/Foundation/Slab | 12/6/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Final | 12/6/2021 | Corrections Issued | MARK JOHNSON |
| BUILDING-Rough-Frame | 7/26/2022 | Approved | JAVIER RAMOS JR |
| Final | 7/26/2022 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/26/2022 | Approved | JAVIER RAMOS JR |
| Green Building Final | 7/26/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 7/26/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/26/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 7/26/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 7/26/2022 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 7/26/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 8/31/2022 | Approved | JAVIER RAMOS JR |
| Final | 8/31/2022 | Conditional Approval | JAVIER RAMOS JR |
| HVAC-Final | 8/31/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 8/31/2022 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 8/31/2022 | Approved | JAVIER RAMOS JR |