877 1/2 E 41ST ST 90011

Certificate Information: 877 1/2 E 41ST ST 90011

Application / Permit
20010-20000-03445
Plan Check / Job No.
B20VN12757
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 30' X 20' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/10/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 10/27/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 11/6/2020 OMID HEDAYAT
Building Plans Picked Up 11/12/2020 APPLICANT
Applicant returned to address corrections 8/4/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 8/18/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 9/1/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 9/15/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 9/28/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 9/30/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 3/14/2022 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 4/10/2023 RARES BODEA
Issued 4/10/2023 APPLICANT
CofO in Progress 5/8/2025 SCOTT FINNILA
CofO in Progress 5/8/2025 SCOTT FINNILA
CofO in Progress 5/9/2025 BRENDAN MORELLI
Permit Finaled 5/10/2025 DEROLD HAUFF
CofO Issued 5/10/2025 DEROLD HAUFF
Permit Finaled 5/10/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/29/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 4/19/2021 CECILIO NAVARRO
Sewer availability Cleared 4/19/2021 CECILIO NAVARRO
Tenant Habitability Plan Cleared 5/18/2021 PHILLIP MUNGUIA
Low Impact Development Cleared 7/8/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/16/2021 STEVE MELGAR
Miscellaneous Cleared 12/13/2022 DANIEL CORONADO

Contact Information

Contractor Owner-Builder       ,
Engineer Rodriguez,, Jacob; Lic. No.: S5084 8206 ENCINO AVE      NORTHRIDGE, CA 91325

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/17/2023 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 7/17/2023 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 7/24/2023 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/2/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/18/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 8/18/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/24/2023 Approved ALEJANDRO DE ARTOLA
Sewer 2/29/2024 Not Ready for Inspection DAVID FEILER
Underground Mechanical 2/29/2024 Partial Approval DAVID FEILER
Gas Test 3/7/2024 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/7/2024 Approved ALEJANDRO DE ARTOLA
Sewer 3/7/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 3/7/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/12/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 4/12/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 4/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 4/24/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/2/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 5/2/2024 Approved ALEJANDRO DE ARTOLA
Insulation 5/2/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 5/2/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 5/6/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 5/6/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 3/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 3/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/1/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 4/1/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Final 4/9/2025 Approved ALEJANDRO DE ARTOLA
Final 4/9/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 4/9/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 4/9/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 4/9/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/9/2025 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 4/9/2025 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 4/9/2025 Approved ALEJANDRO DE ARTOLA
Final 5/7/2025 Conditional Approval BRENDAN MORELLI
Gas Test 5/7/2025 Approved BRENDAN MORELLI
Final 5/9/2025 OK to Issue CofO BRENDAN MORELLI