5244 N TAMPA AVE 91356
Certificate Information: 5244 N TAMPA AVE 91356
- Application / Permit
- 20010-20000-03405
- Plan Check / Job No.
- B20VN12697
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 61'-1" x 68'-5" IRREGULAR SHAPED TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED TRELLIS AT REAR." NFPA - 13D FIRE SPRINKLERS THRU-OUT ".
- Permit Issued
- Issued on 8/17/2021
- Issuing Office
- Current Status
- CofO Issued on 6/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | SARKIS HARABEDIAN |
| Corrections Issued | 10/3/2020 | SARKIS HARABEDIAN |
| Quality Review Completed | 10/6/2020 | STEVEN KIM |
| Plan Check Approved | 7/26/2021 | SARKIS HARABEDIAN |
| Issued | 8/17/2021 | APPLICANT |
| Building Plans Picked Up | 8/17/2021 | APPLICANT |
| CofO in Progress | 5/21/2024 | JOHN KIDWELL |
| Permit Finaled | 6/10/2024 | JOHN JANSON |
| CofO Issued | 6/10/2024 | JOHN JANSON |
| Permit Finaled | 6/10/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/13/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/14/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 11/2/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 4/8/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/7/2021 | ABDULLAH SADOZAI |
| GPI Written Notices | Cleared | 7/8/2021 | SARKIS HARABEDIAN |
| Grading Pre-Inspection | Cleared | 7/8/2021 | SARKIS HARABEDIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/4/2021 | Partial Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 10/5/2021 | Corrections Issued | JAVIER RAMOS JR |
| Special/Order Compliance | 10/5/2021 | Partial Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/25/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 10/25/2021 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/28/2021 | Partial Inspection | DAVID SANDOVAL |
| Underground Mechanical | 10/28/2021 | Partial Approval | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 11/1/2021 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 11/2/2021 | Corrections Issued | DAVID SANDOVAL |
| Deputy Steel/Welding | 11/9/2021 | No Access for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2021 | Partial Approval | DAVID SANDOVAL |
| Green Building Rough | 12/20/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 12/20/2021 | No Access for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 4/19/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Rough | 4/19/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 4/19/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 4/19/2022 | Partial Inspection | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 4/19/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 6/23/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Partial Approval | DAVID SANDOVAL |
| Green Building Rough | 6/23/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 6/23/2022 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 6/23/2022 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 6/23/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 6/29/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Rough | 7/12/2022 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 7/12/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 7/21/2022 | Approved | PETER FOLLING |
| Green Building Rough | 7/21/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 7/21/2022 | Partial Approval | PETER FOLLING |
| Insulation | 7/25/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 8/1/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 8/4/2022 | Corrections Issued | JUSTIN HAWLEY |
| Shower Pan | 8/5/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 8/23/2022 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 9/15/2022 | Approved | DAVID SANDOVAL |
| Underground Mechanical | 5/17/2023 | Approved | SEAN HAUPT |
| Underground Mechanical | 6/5/2023 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Final | 3/14/2024 | Approved | JOHN KIDWELL |
| HVAC-Final | 3/14/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 3/14/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Sewer | 3/27/2024 | Partial Inspection | JOHN KIDWELL |
| ELECTRICAL-Final | 4/11/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 4/11/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 4/17/2024 | Partial Inspection | JOHN KIDWELL |
| Service/Power Release | 4/22/2024 | Approved | JOHN KIDWELL |
| Final | 5/2/2024 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 5/2/2024 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 5/2/2024 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 5/2/2024 | Approved | JOHN KIDWELL |
| Service/Power Release | 5/3/2024 | Approved | JOHN KIDWELL |
| Final | 5/9/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 5/9/2024 | Approved | JOHN KIDWELL |
| Special/Order Compliance | 5/14/2024 | Corrections Issued | JOHN KIDWELL |
| Final | 5/20/2024 | OK to Issue CofO | JOHN KIDWELL |