5244 N TAMPA AVE 91356

Certificate Information: 5244 N TAMPA AVE 91356

Application / Permit
20010-20000-03405
Plan Check / Job No.
B20VN12697
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 61'-1" x 68'-5" IRREGULAR SHAPED TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED TRELLIS AT REAR." NFPA - 13D FIRE SPRINKLERS THRU-OUT ".
Permit Issued
Issued on 8/17/2021
Issuing Office
Current Status
CofO Issued on 6/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 SARKIS HARABEDIAN
Corrections Issued 10/3/2020 SARKIS HARABEDIAN
Quality Review Completed 10/6/2020 STEVEN KIM
Plan Check Approved 7/26/2021 SARKIS HARABEDIAN
Issued 8/17/2021 APPLICANT
Building Plans Picked Up 8/17/2021 APPLICANT
CofO in Progress 5/21/2024 JOHN KIDWELL
Permit Finaled 6/10/2024 JOHN JANSON
CofO Issued 6/10/2024 JOHN JANSON
Permit Finaled 6/10/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/13/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 10/14/2020 GUILLERMO PETRA
Sewer availability Cleared 10/14/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 11/2/2020 MATTHEW CRAIG
Low Impact Development Cleared 4/8/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/7/2021 ABDULLAH SADOZAI
GPI Written Notices Cleared 7/8/2021 SARKIS HARABEDIAN
Grading Pre-Inspection Cleared 7/8/2021 SARKIS HARABEDIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/4/2021 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 10/5/2021 Corrections Issued JAVIER RAMOS JR
Special/Order Compliance 10/5/2021 Partial Inspection DAVID SANDOVAL
Footing/Foundation/Slab 10/25/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 10/25/2021 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 10/28/2021 Partial Inspection DAVID SANDOVAL
Underground Mechanical 10/28/2021 Partial Approval DAVID SANDOVAL
Deputy Drilled-In Anchors 11/1/2021 Approved DAVID SANDOVAL
Footing/Foundation/Slab 11/2/2021 Corrections Issued DAVID SANDOVAL
Deputy Steel/Welding 11/9/2021 No Access for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Partial Approval DAVID SANDOVAL
Green Building Rough 12/20/2021 Not Ready for Inspection DAVID SANDOVAL
Verify Sprinkler Sign Off 12/20/2021 No Access for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 4/19/2022 Corrections Issued DAVID SANDOVAL
Green Building Rough 4/19/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 4/19/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 4/19/2022 Partial Inspection DAVID SANDOVAL
Verify Sprinkler Sign Off 4/19/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 6/23/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Partial Approval DAVID SANDOVAL
Green Building Rough 6/23/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 6/23/2022 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 6/23/2022 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 6/23/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 6/29/2022 Approved DAVID SANDOVAL
Green Building Rough 6/29/2022 Not Ready for Inspection DAVID SANDOVAL
Green Building Rough 7/12/2022 Not Ready for Inspection PETER FOLLING
HVAC-Rough 7/12/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 7/21/2022 Approved PETER FOLLING
Green Building Rough 7/21/2022 Approved PETER FOLLING
Interior/Exterior Lathing 7/21/2022 Partial Approval PETER FOLLING
Insulation 7/25/2022 Approved DAVID SANDOVAL
Drywall Nailing 8/1/2022 Approved JUSTIN HAWLEY
Shower Pan 8/4/2022 Corrections Issued JUSTIN HAWLEY
Shower Pan 8/5/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 8/23/2022 Approved DAVID SANDOVAL
Footing/Foundation/Slab 9/15/2022 Approved DAVID SANDOVAL
Underground Mechanical 5/17/2023 Approved SEAN HAUPT
Underground Mechanical 6/5/2023 Partial Approval JOHN KIDWELL
ELECTRICAL-Final 3/14/2024 Approved JOHN KIDWELL
HVAC-Final 3/14/2024 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 3/14/2024 Not Ready for Inspection JOHN KIDWELL
Sewer 3/27/2024 Partial Inspection JOHN KIDWELL
ELECTRICAL-Final 4/11/2024 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 4/11/2024 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 4/17/2024 Partial Inspection JOHN KIDWELL
Service/Power Release 4/22/2024 Approved JOHN KIDWELL
Final 5/2/2024 Corrections Issued JOHN KIDWELL
Green Building Final 5/2/2024 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/2/2024 SGSOV Approved JOHN KIDWELL
Smoke Detectors 5/2/2024 Approved JOHN KIDWELL
Service/Power Release 5/3/2024 Approved JOHN KIDWELL
Final 5/9/2024 Not Ready for Inspection JOHN KIDWELL
Green Building Final 5/9/2024 Approved JOHN KIDWELL
Special/Order Compliance 5/14/2024 Corrections Issued JOHN KIDWELL
Final 5/20/2024 OK to Issue CofO JOHN KIDWELL