13830 1/2 W PAXTON ST 91331

Certificate Information: 13830 1/2 W PAXTON ST 91331

Application / Permit
20010-20000-03383
Plan Check / Job No.
B20VN12639
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 26'3" X 39'2" ONE STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(C) AND (E), ALL WORK PER WFPP
Permit Issued
Issued on 10/6/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2020 APPLICANT
Assigned to Plan Check Engineer 10/2/2020 RARES BODEA
Plans on Hold 10/4/2020 RARES BODEA
Hold Released 11/10/2020 RARES BODEA
Corrections Issued 11/12/2020 RARES BODEA
Building Plans Picked Up 11/13/2020 APPLICANT
Plan Check Approved 12/14/2021 RARES BODEA
Issued 10/6/2022 APPLICANT
CofO in Progress 8/7/2025 JENNIFER RABUCHIN
Permit Finaled 8/14/2025 RUBEN SALAS
CofO Issued 8/14/2025 RUBEN SALAS
Permit Finaled 8/14/2025 RUBEN SALAS

Permit Application Clearance Information

Hold Cleared 11/10/2020 JASON SHEETS
Address approval Cleared 12/17/2020 GUILLERMO PETRA
Sewer availability Cleared 12/18/2020 GUILLERMO PETRA
Low Impact Development Cleared 9/24/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/1/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 11/13/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/27/2023 Approved MICHEL ABAJAN
METHANE-Barrier 7/27/2023 Approved MICHEL ABAJAN
METHANE-Subgrade 7/27/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 8/18/2023 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 10/24/2023 Approved MICHEL ABAJAN
HVAC-Rough 10/24/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 10/24/2023 Approved MICHEL ABAJAN
Underground Mechanical 10/24/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/14/2023 Approved MICHEL ABAJAN
Shower Pan 11/14/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 11/27/2023 Approved MICHEL ABAJAN
Green Building Rough 11/27/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/27/2023 Approved MICHEL ABAJAN
MERV13>=Rough 11/27/2023 Approved MICHEL ABAJAN
METHANE-Rough 11/27/2023 Approved MICHEL ABAJAN
Insulation 12/14/2023 Approved MICHEL ABAJAN
Drywall Nailing 1/4/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Final 5/17/2024 Corrections Issued JENNIFER RABUCHIN
Final 5/17/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 5/17/2024 Approved JENNIFER RABUCHIN
HVAC-Final 5/17/2024 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Final 5/17/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 5/17/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/17/2024 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 5/17/2024 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 5/17/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/2/2025 Approved JENNIFER RABUCHIN
Final 6/2/2025 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 6/2/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/2/2025 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 6/2/2025 Conditional Approval JENNIFER RABUCHIN
ELECTRICAL-Final 8/7/2025 Approved JENNIFER RABUCHIN
Final 8/7/2025 OK to Issue CofO JENNIFER RABUCHIN
Service/Power Release 8/7/2025 Approved JENNIFER RABUCHIN