2515 S BROADWAY 90007

Certificate Information: 2515 S BROADWAY 90007

Application / Permit
20010-20000-03381
Plan Check / Job No.
B20VN12638
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Storage Building
Work Description
(N) 180'8" X 171'4" 3-STORY SELF STORAGE BLDG W/BASEMENT AND ON-GRADE PKG GARAGE
Permit Issued
Issued on 8/12/2021
Issuing Office
Current Status
CofO Corrected on 5/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2020 APPLICANT
Green Plans Picked Up 10/19/2020 APPLICANT
Disabled Access Plans Picked Up 10/20/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 MARVEL DELACRUZ
Corrections Issued 10/27/2020 MARVEL DELACRUZ
Quality Review Completed 11/13/2020 STEVEN KIM
Building Plans Picked Up 11/13/2020 APPLICANT
Applicant returned to address corrections 1/4/2021 MARVEL DELACRUZ
Applicant returned to address corrections 2/25/2021 MARVEL DELACRUZ
Applicant returned to address corrections 3/15/2021 MARVEL DELACRUZ
Applicant returned to address corrections 7/27/2021 MARVEL DELACRUZ
Plan Check Approved 7/29/2021 MARVEL DELACRUZ
Issued 8/12/2021 APPLICANT
TCO Issued (Expire Date: 07-27-2024) 1/29/2024 ERNESTO CORRAL
CofO in Progress 5/2/2024 JAMES POWERS
CofO Issued-Status Void 5/2/2024 ADAM BURGESS
Permit Finaled-Status Void 5/2/2024 ADAM BURGESS
Re-Activate Permit 5/8/2024 ADAM BURGESS
Permit Finaled 5/8/2024 ADAM BURGESS
CofO Corrected 5/8/2024 ADAM BURGESS
Permit Finaled 5/8/2024 ADAM BURGESS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/2/2020 ROSA SILVA
Address approval Cleared 1/5/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 1/6/2021 MATTHEW CRAIG
Highway dedication Cleared 1/12/2021 CECILIO NAVARRO
Trees in Parkway Cleared 1/25/2021 JOHN KIM
Redevelopment Project Area Cleared 2/4/2021 DAVID URITA
ZI Cleared 2/4/2021 DAVID URITA
Driveway location Cleared 2/17/2021 KEVIN ARUCAN
Internal circulation Cleared 2/17/2021 KEVIN ARUCAN
Green Code Cleared 2/19/2021 MICHAEL AYERS
Building over 36-ft Cleared 3/23/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/23/2021 CALOSHA APPROVED
DAS Clearance Cleared 5/13/2021 MARVEL DELACRUZ
Miscellaneous Cleared 5/13/2021 LOUIS ORTEGA
Prkng lot landscape/Water mgmt Cleared 5/13/2021 LOUIS ORTEGA
Work Adjacent to Public Way Cleared 6/3/2021 JOSE RODRIGUEZ
Sewer availability Cleared 6/24/2021 CECILIO NAVARRO
Low Impact Development Cleared 7/16/2021 ORVAL HERNANDEZ-MARCI
Permit Cleared 7/22/2021 ARMEN MEHRABIAN
Roof/Waste drainage to street Cleared 7/28/2021 JEANIE LAM

Contact Information

Architect Jordan,, Bruce Didrik; Lic. No.: C12923 131 CALLE IGLESIA SUITE 100      SAN CLEMENTE, CA 92672
Contractor Monarch Construction Management Inc; Lic. No.: 777725-B 1001 DOVE ST STE 205      NEWPORT BEACH, CA 92660
Engineer Elder,, John Brittan; Lic. No.: S6534 5181 S EMERALD PL      CHANDLER, AZ 85249
Engineer Marcus,, Matthew Werner; Lic. No.: C81591 4518 N 12TH STREET STE 201      PHOENIX, AZ 85016
Landscape Architect Miertschin,, David M; Lic. No.: LA3308 34032 ALCAZAR DR      DANA POINT, CA 92629

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/28/2022 Partial Approval JAMES POWERS
METHANE-Barrier 1/28/2022 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 1/28/2022 Not Ready for Inspection JAMES POWERS
Piling/Pier/Caisson 1/31/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/10/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/10/2022 Partial Approval JAMES POWERS
METHANE-Barrier 2/10/2022 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 2/10/2022 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 2/11/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/15/2022 Partial Approval JAMES POWERS
Deputy Methane Barrier 2/22/2022 Partial Approval JAMES POWERS
Deputy Methane Barrier 2/23/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/1/2022 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/1/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/9/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/9/2022 Partial Approval JAMES POWERS
Green Building Rough 3/9/2022 Not Ready for Inspection JAMES POWERS
METHANE-Rough 3/9/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/9/2022 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 3/9/2022 Not Ready for Inspection JAMES POWERS
Deputy Methane Barrier 3/21/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/29/2022 Conditional Approval NICK DANERI
Footing/Foundation/Slab 3/29/2022 Partial Approval NICK DANERI
METHANE-Barrier 3/29/2022 Conditional Approval NICK DANERI
METHANE-Subgrade 3/29/2022 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 3/31/2022 Conditional Approval NICK DANERI
Deputy Methane Barrier 4/21/2022 Conditional Approval DAVID BURKHEAD
Deputy Methane Barrier 4/22/2022 Conditional Approval DAVID BURKHEAD
Deputy Methane Barrier 4/25/2022 Partial Approval JAMES POWERS
Deputy Methane Barrier 4/26/2022 Conditional Approval TED RIES
METHANE-Final 4/26/2022 Partial Approval TED RIES
Green Building Rough 4/28/2022 Not Ready for Inspection JAMES POWERS
METHANE-Rough 4/28/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 4/28/2022 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 4/28/2022 Not Ready for Inspection JAMES POWERS
Pre-Inspection 5/4/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/5/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/6/2022 Partial Approval JAMES POWERS
METHANE-Barrier 5/6/2022 Partial Approval JAMES POWERS
METHANE-Subgrade 5/6/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/10/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/12/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/18/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/19/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/20/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/23/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/24/2022 Conditional Approval ERNESTO CORRAL
Green Building Rough 5/26/2022 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 5/26/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 5/26/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 5/26/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/27/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/2/2022 Conditional Approval ERNESTO CORRAL
Masonry Wall/Backfill 6/21/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/22/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/23/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/24/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/5/2022 Partial Approval JAMES POWERS
Structural Steel Frame 7/5/2022 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 7/18/2022 Conditional Approval WINSTON DUNNING
Deputy Steel/Welding 7/18/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/19/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/20/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/28/2022 Partial Approval JAMES POWERS
METHANE-Barrier 7/28/2022 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 7/28/2022 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 7/29/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 8/1/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/4/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/5/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/18/2022 Conditional Approval ERNESTO CORRAL
Masonry Wall/Backfill 8/19/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/24/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/24/2022 Partial Approval JAMES POWERS
METHANE-Barrier 8/24/2022 Partial Approval JAMES POWERS
METHANE-Subgrade 8/24/2022 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 8/25/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 8/25/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/26/2022 Conditional Approval NICK DANERI
Green Building Rough 8/26/2022 Not Ready for Inspection NICK DANERI
METHANE-Rough 8/26/2022 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 8/26/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 8/26/2022 Not Ready for Inspection NICK DANERI
Deputy Reinf. Masonry 8/29/2022 Partial Approval JAMES POWERS
Deputy Other (see comments) 8/30/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 8/30/2022 Conditional Approval WINSTON DUNNING
Deputy Other (see comments) 8/31/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 8/31/2022 Conditional Approval WINSTON DUNNING
Deputy Other (see comments) 9/1/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 9/1/2022 Conditional Approval WINSTON DUNNING
Deputy Other (see comments) 9/2/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 9/2/2022 Conditional Approval WINSTON DUNNING
Deputy Other (see comments) 9/9/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 9/9/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Other (see comments) 9/13/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 9/13/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Methane Barrier 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/19/2022 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/19/2022 Not Ready for Inspection JAMES POWERS
METHANE-Rough 10/19/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/20/2022 Partial Approval JAMES POWERS
METHANE-Barrier 10/20/2022 Partial Approval JAMES POWERS
METHANE-Subgrade 10/20/2022 Approved JAMES POWERS
Deputy Reinf. Concrete 10/27/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/28/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/2/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/3/2022 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 11/4/2022 Not Ready for Inspection GREGORY POMISH
METHANE-Rough 11/4/2022 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 11/4/2022 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 11/4/2022 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 11/10/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 12/2/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/9/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 12/16/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/19/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/28/2022 Partial Approval NICK DANERI
METHANE-Barrier 12/28/2022 Approved NICK DANERI
Deputy Reinf. Concrete 1/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/18/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/31/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/1/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 2/2/2023 Partial Approval NICK DANERI
Deputy Reinf. Masonry 2/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/10/2023 Partial Approval JAMES POWERS
Masonry Wall/Backfill 2/10/2023 Partial Approval JAMES POWERS
Green Building Rough 2/13/2023 Not Ready for Inspection JAMES POWERS
METHANE-Rough 2/13/2023 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 2/13/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/13/2023 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 2/21/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 2/24/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 2/24/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 2/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 2/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/9/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/9/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/10/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/17/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 4/4/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/4/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/7/2023 Partial Approval JAMES POWERS
Reinforced Masonry Frame 4/7/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 4/14/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/14/2023 Partial Approval JAMES POWERS
Green Building Rough 4/14/2023 Approved JAMES POWERS
Light Gage Steel Frame 4/14/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/20/2023 Partial Approval GREGORY POMISH
Reinforced Concrete Frame 5/1/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/3/2023 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 5/5/2023 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 5/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/11/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 5/11/2023 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/12/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/12/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 5/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 5/16/2023 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 5/16/2023 Conditional Approval GREGORY POMISH
Drywall Nailing 5/16/2023 Not Ready for Inspection GREGORY POMISH
Insulation 5/16/2023 Partial Approval GREGORY POMISH
Drywall Nailing 5/24/2023 Partial Approval GREGORY POMISH
Light Gage Steel Frame 6/14/2023 Partial Approval JAMES POWERS
Drywall Nailing 7/5/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/10/2023 Partial Approval JAMES POWERS
Insulation 7/12/2023 Not Ready for Inspection JAMES POWERS
Insulation 7/21/2023 Partial Approval JAMES POWERS
Insulation 7/25/2023 Partial Approval JAMES POWERS
Drywall Nailing 7/28/2023 Partial Approval JAMES POWERS
Insulation 7/31/2023 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 8/4/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 8/9/2023 Partial Approval RAFAEL ESPINOZA
Structural Steel Frame 8/23/2023 Partial Approval JAMES POWERS
Special/Order Compliance 8/29/2023 Partial Approval JAMES POWERS
Pre-Inspection 10/31/2023 Partial Approval JAMES POWERS
Drywall Nailing 11/30/2023 Approved JAMES POWERS
Final 11/30/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 11/30/2023 Approved JAMES POWERS
Green Building Final 11/30/2023 Approved JAMES POWERS
METHANE-Final 11/30/2023 Approved JAMES POWERS
METHANE-Rough 11/30/2023 Approved JAMES POWERS
Reinforced Concrete Frame 11/30/2023 Approved JAMES POWERS
Reinforced Masonry Frame 11/30/2023 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 11/30/2023 SGSOV No Gas JAMES POWERS
Smoke Detectors 11/30/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 11/30/2023 Approved JAMES POWERS
T-Bar Ceiling 12/11/2023 Approved JAMES POWERS
Deputy Drilled-In Anchors 12/12/2023 Partial Approval JAMES POWERS
Final 3/28/2024 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 5/2/2024 Partial Approval JAMES POWERS
Deputy Methane Barrier 5/2/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/2/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/2/2024 Partial Approval JAMES POWERS
Final 5/2/2024 OK to Issue CofO JAMES POWERS