1763 1/2 W 37TH DR 90018
Certificate Information: 1763 1/2 W 37TH DR 90018
- Application / Permit
- 20010-20000-03380
- Plan Check / Job No.
- B20VN12637
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 37' X 15' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A33(C) AND (E), ALL WORK PER WFPP
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- Issued on 5/24/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2020 | RARES BODEA |
| Corrections Issued | 10/4/2020 | RARES BODEA |
| Building Plans Picked Up | 10/6/2020 | APPLICANT |
| No Progress | 4/1/2021 | RARES BODEA |
| Applicant returned to address corrections | 4/12/2021 | RARES BODEA |
| Issued | 5/24/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2020 | JEANIE LAM |
| Sewer availability | Cleared | 10/23/2020 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 1/4/2021 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 1/6/2021 | RIDWAN HARDY |
| Construction near power lines | Cleared | 1/6/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 1/21/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 2/9/2021 | ORVAL HERNANDEZ-MARCI |
| Community Plan Implem. Overlay | Cleared | 2/17/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 2/17/2021 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 3/31/2021 | JOHN KIM |
| Trees in Parkway | Cleared | 3/31/2021 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/20/2021 | Partial Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 8/20/2021 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 8/20/2021 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/7/2021 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 12/7/2021 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Approved | SABAS ALONSO |
| Green Building Rough | 12/7/2021 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 12/7/2021 | Not Ready for Inspection | SABAS ALONSO |
| Verify Sprinkler Sign Off | 12/7/2021 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/14/2021 | Approved | SABAS ALONSO |
| Green Building Rough | 12/14/2021 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/14/2021 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 12/14/2021 | Approved | SABAS ALONSO |
| Insulation | 1/3/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/3/2022 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 1/24/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/24/2022 | Approved | SABAS ALONSO |
| Sewer | 2/28/2022 | Approved | AMY COLIN |
| Underground Mechanical | 2/28/2022 | Approved | AMY COLIN |
| Underground Mechanical | 4/19/2022 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Final | 5/25/2022 | Approved | SABAS ALONSO |
| Final | 5/25/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 5/25/2022 | Approved | SABAS ALONSO |
| HVAC-Final | 5/25/2022 | Approved | SABAS ALONSO |
| PLUMBING-Final | 5/25/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 5/25/2022 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 5/25/2022 | Approved | SABAS ALONSO |
| Smoke Detectors | 5/25/2022 | Approved | SABAS ALONSO |