18353 W ARMINTA ST 91335

Certificate Information: 18353 W ARMINTA ST 91335

Application / Permit
20010-20000-03378
Plan Check / Job No.
B20VN12629
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 21'-8" x 40' detached Accessory Dwelling Unit per LAMC 12.22 A.33 (c)-(d). NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT.
Permit Issued
Issued on 9/2/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Application Withdrawn-Void 12/10/2020 ALDO UBAU
Re-Activate Application 1/14/2021 ALDO UBAU
Submitted 2/9/2021 APPLICANT
Assigned to Plan Check Engineer 3/16/2021 ANGELICA DAVE
Corrections Issued 3/16/2021 ANGELICA DAVE
Plan Check Approved 6/10/2022 ZAW HAN
Issued 9/2/2022 APPLICANT
CofO in Progress 12/13/2024 ARUTYUN MADATYAN
Permit Finaled 1/6/2025 JOHN JANSON
CofO Issued 1/6/2025 JOHN JANSON
Permit Finaled 1/6/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/29/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/29/2021 GABRIEL ROBLES
Sewer availability Cleared 9/29/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 1/11/2022 MATTHEW CRAIG
Low Impact Development Cleared 3/9/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 3/22/2022 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/7/2022 Approved JEFFREY BULL
PLUMBING-Rough 10/28/2022 Partial Approval JEFFREY BULL
Excavation/Setback/Form/Re-Bar 7/6/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 9/26/2023 Corrections Issued JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/20/2023 Approved JEFFREY BULL
Special/Order Compliance 10/20/2023 Corrections Issued JEFFREY BULL
BUILDING-Rough-Frame 12/15/2023 Not Ready for Inspection JEFFREY BULL
Green Building Rough 12/15/2023 Approved JEFFREY BULL
Rough-Elec/Plmb/HVAC 12/15/2023 Approved JEFFREY BULL
Insulation 12/20/2023 Approved JEFFREY BULL
Drywall Nailing 1/12/2024 Approved JEFFREY BULL
Shower Pan 1/12/2024 Approved JEFFREY BULL
Gas Test 7/9/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 10/15/2024 Approved JEFFREY BULL
Final 10/15/2024 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 10/15/2024 Approved JEFFREY BULL
Green Building Final 10/15/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 10/15/2024 SGSOV Approved JEFFREY BULL
Service/Power Release 10/15/2024 Approved JEFFREY BULL
Smoke Detectors 10/15/2024 Approved JEFFREY BULL
Verify Sprinkler Sign Off 10/15/2024 Approved JEFFREY BULL
ELECTRICAL-Final 12/12/2024 Approved ARUTYUN MADATYAN
Final 12/12/2024 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 12/12/2024 Approved ARUTYUN MADATYAN
PLUMBING-Final 12/12/2024 Approved ARUTYUN MADATYAN
Service/Power Release 12/12/2024 Approved ARUTYUN MADATYAN