17631 W TARZANA ST 91316

Certificate Information: 17631 W TARZANA ST 91316

Application / Permit
20010-20000-03353
Plan Check / Job No.
B20VN12539
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
PROPOSE 13'X18' RECREATION WITH MAXIMUM 1/2 BATH, AND A STORAGE WITH EXTERIOR ACCESS ONLY.
Permit Issued
Issued on 3/22/2021
Issuing Office
Current Status
CofO Issued on 1/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 DAWN MC NULTY
Corrections Issued 10/5/2020 DAWN MC NULTY
Quality Review Completed 10/5/2020 CHON CHIO KUO
Building Plans Picked Up 10/6/2020 APPLICANT
Applicant returned to address corrections 3/1/2021 DAWN MC NULTY
Applicant returned to address corrections 3/3/2021 DAWN MC NULTY
Plan Check Approved 3/8/2021 DAWN MC NULTY
Issued 3/22/2021 APPLICANT
CofO in Progress 12/23/2021 STEVEN BACK
Permit Finaled 1/5/2022 JOHN JANSON
CofO Issued 1/5/2022 JOHN JANSON
Permit Finaled 1/5/2022 JOHN JANSON

Permit Application Clearance Information

Low Impact Development Cleared 11/12/2020 MICHAEL SCADUTO
Address approval Cleared 12/8/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/8/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/21/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 12/21/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 1/6/2021 MATTHEW CRAIG
GPI Written Notices Cleared 2/22/2021 DAWN MC NULTY
Grading Pre-Inspection Cleared 2/22/2021 DAWN MC NULTY

Contact Information

Architect Janev,, Valentine S; Lic. No.: C19379 19261 WELLS DRIVE      TARZANA, CA 91356
Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/15/2021 Approved STEVEN BACK
PLUMBING-Rough 4/15/2021 Partial Approval STEVEN BACK
Footing/Foundation/Slab 4/26/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 6/4/2021 Partial Approval STEVEN BACK
HVAC-Rough 6/22/2021 Approved STEVEN BACK
PLUMBING-Rough 6/22/2021 Approved STEVEN BACK
ELECTRICAL-Rough 6/25/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 6/28/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/28/2021 Approved STEVEN BACK
Green Building Rough 6/28/2021 Not Ready for Inspection STEVEN BACK
Verify Sprinkler Sign Off 6/28/2021 Approved STEVEN BACK
Green Building Rough 7/1/2021 Approved STEVEN BACK
Interior/Exterior Lathing 7/1/2021 Partial Approval STEVEN BACK
Shower Pan 7/1/2021 Approved STEVEN BACK
Interior/Exterior Lathing 7/6/2021 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 7/7/2021 Approved STEVEN BACK
Drywall Nailing 7/8/2021 Approved STEVEN BACK
ELECTRICAL-Final 11/15/2021 Approved STEVEN BACK
Gas Test 11/15/2021 Corrections Issued STEVEN BACK
HVAC-Final 11/15/2021 Corrections Issued STEVEN BACK
PLUMBING-Final 11/15/2021 Approved STEVEN BACK
Gas Test 11/19/2021 Approved STEVEN BACK
HVAC-Final 11/19/2021 Approved STEVEN BACK
Final 12/23/2021 OK to Issue CofO STEVEN BACK
Green Building Final 12/23/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 12/23/2021 SGSOV Approved STEVEN BACK
Service/Power Release 12/23/2021 Approved STEVEN BACK
Smoke Detectors 12/23/2021 Approved STEVEN BACK