17631 W TARZANA ST 91316
Certificate Information: 17631 W TARZANA ST 91316
- Application / Permit
- 20010-20000-03352
- Plan Check / Job No.
- B20VN12539
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE 64'X66'-6" TWO STORY SSSSSSFD WITH ATTACHED TWO CAR GARAGE AND ATTACHED 3 ATTACHED TRELLIS _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 3/22/2021
- Issuing Office
- Current Status
- CofO Issued on 1/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | DAWN MC NULTY |
| Corrections Issued | 10/5/2020 | DAWN MC NULTY |
| Quality Review Completed | 10/5/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 10/6/2020 | APPLICANT |
| Applicant returned to address corrections | 3/1/2021 | DAWN MC NULTY |
| Applicant returned to address corrections | 3/3/2021 | DAWN MC NULTY |
| Plan Check Approved | 3/8/2021 | DAWN MC NULTY |
| Issued | 3/22/2021 | APPLICANT |
| CofO in Progress | 12/23/2021 | STEVEN BACK |
| Permit Finaled | 1/5/2022 | JOHN JANSON |
| CofO Issued | 1/5/2022 | JOHN JANSON |
| Permit Finaled | 1/5/2022 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 11/12/2020 | MICHAEL SCADUTO |
| Address approval | Cleared | 12/8/2020 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 12/8/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 12/21/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/21/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 1/6/2021 | MATTHEW CRAIG |
| Frnt yard landscape/Water mgmt | Cleared | 1/7/2021 | LAUREN PADICK |
| GPI Written Notices | Cleared | 2/22/2021 | DAWN MC NULTY |
| Grading Pre-Inspection | Cleared | 2/22/2021 | DAWN MC NULTY |
| Trees in Parkway | Cleared | 3/4/2021 | JOHN KIM |
Contact Information
| Architect | Janev,, Valentine S; Lic. No.: C19379 | 19261 WELLS DRIVE TARZANA, CA 91356 |
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/15/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 4/15/2021 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 4/26/2021 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2021 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 6/22/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 6/22/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 6/25/2021 | Approved | STEVEN BACK |
| Shower Pan | 6/25/2021 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 6/28/2021 | Conditional Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2021 | Approved | STEVEN BACK |
| Green Building Rough | 6/28/2021 | Not Ready for Inspection | STEVEN BACK |
| Verify Sprinkler Sign Off | 6/28/2021 | Approved | STEVEN BACK |
| Green Building Rough | 7/1/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 7/1/2021 | Partial Approval | STEVEN BACK |
| Shower Pan | 7/1/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 7/6/2021 | Not Ready for Inspection | RYAN SALAZAR |
| Drywall Nailing | 7/7/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 7/7/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 7/8/2021 | No Access for Inspection | STEVEN BACK |
| ELECTRICAL-Final | 11/15/2021 | Approved | STEVEN BACK |
| Gas Test | 11/15/2021 | Corrections Issued | STEVEN BACK |
| HVAC-Final | 11/15/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Final | 11/15/2021 | No Access for Inspection | STEVEN BACK |
| Gas Test | 11/19/2021 | Approved | STEVEN BACK |
| HVAC-Final | 11/19/2021 | Approved | STEVEN BACK |
| PLUMBING-Final | 11/19/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/19/2021 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 12/6/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 12/23/2021 | Approved | STEVEN BACK |
| Final | 12/23/2021 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 12/23/2021 | Approved | STEVEN BACK |
| Smoke Detectors | 12/23/2021 | Approved | STEVEN BACK |