11460 W KILLION ST 91601
Certificate Information: 11460 W KILLION ST 91601
- Application / Permit
- 20010-20000-03347
- Plan Check / Job No.
- B20VN12523
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 3-STORY APT BLDG - 100% AFFORDABLE HOUSING T.O.C TIER-3 PROJECT(3 Extremely Low Units; 1 Very Low Income Unit; 17 Low Income Units) "COMPLY WITH DEPARTMENT ORDER effective date 03/07/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 4/7/2022
- Issuing Office
- Current Status
- CofO Issued on 11/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | CHON CHIO KUO |
| Corrections Issued | 10/19/2020 | CHON CHIO KUO |
| Quality Review Completed | 10/21/2020 | STEVEN KIM |
| Disabled Access Plans Picked Up | 10/21/2020 | APPLICANT |
| Green Plans Picked Up | 10/21/2020 | APPLICANT |
| Applicant returned to address corrections | 2/2/2022 | MARVEL DELACRUZ |
| Plan Check Approved | 3/11/2022 | MARVEL DELACRUZ |
| Issued | 4/7/2022 | APPLICANT |
| Building Plans Picked Up | 4/11/2022 | APPLICANT |
| TCO Issued (Expire Date: 01-21-2026) | 7/25/2025 | JEFFREY DURAN |
| CofO in Progress | 10/17/2025 | JOHN KITCKO |
| Permit Finaled | 11/4/2025 | RICKEY JACKSON |
| CofO Issued | 11/4/2025 | RICKEY JACKSON |
| Permit Finaled | 11/4/2025 | RICKEY JACKSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2021 | GABRIEL ROBLES |
| Highway dedication | Cleared | 1/7/2021 | GABRIEL ROBLES |
| Work Adjacent to Public Way | Cleared | 1/7/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 1/25/2021 | GABRIEL ROBLES |
| ZA Case | Cleared | 2/2/2021 | TERRI OSBORNE |
| Frnt yard landscape/Water mgmt | Cleared | 2/9/2021 | TERRI OSBORNE |
| Opn space landscape/Water mgmt | Cleared | 2/9/2021 | TERRI OSBORNE |
| Hydrant and Access approval | Cleared | 2/24/2021 | JEREMY CARTER |
| Redevelopment Project Area | Cleared | 3/26/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 3/26/2021 | MICAELA TORRES-GIL |
| Fire Marshal Fire Life Safety | Cleared | 7/7/2021 | VIDAL GARCIA |
| Low Impact Development | Cleared | 10/21/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/22/2021 | JOHN LIN |
| DAS Clearance | Cleared | 12/15/2021 | CHON CHIO KUO |
| Density Bonus 12.22.A.31 | Cleared | 12/15/2021 | KENNETH LE |
| Green Code | Cleared | 1/5/2022 | MICHAEL AYERS |
Contact Information
| Contractor | Quality Grading & Paving; Lic. No.: 643034-B | 552 E CARSON ST #104 CARSON, CA 90745 |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 6541 ODESSA AVE UNIT 11 LAKE BALBOA, CA 91406 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Landscape Architect | Savage,, Michael Sanford; Lic. No.: LA4397 | 1125 SHEPPARD DRIVE FULLERTON, CA 92831 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/15/2022 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 7/20/2022 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 7/22/2022 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 8/1/2022 | Partial Approval | JOHN KITCKO |
| Deputy Wood Construction | 8/19/2022 | Approved | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Conditional Approval | JOHN KITCKO |
| Green Building Rough | 8/19/2022 | Not Ready for Inspection | JOHN KITCKO |
| Verify Sprinkler Sign Off | 8/19/2022 | Approved | JOHN KITCKO |
| Wood Frame | 8/19/2022 | Conditional Approval | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2022 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 9/15/2022 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 9/15/2022 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Wood Construction | 9/16/2022 | Approved | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2022 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Rough | 10/25/2022 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 10/25/2022 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Wood Construction | 11/23/2022 | Approved | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2022 | Partial Approval | JOHN KITCKO |
| Interior/Exterior Lathing | 12/22/2022 | Partial Approval | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Partial Approval | JOHN KITCKO |
| Interior/Exterior Lathing | 12/27/2022 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 11/30/2023 | Not Ready for Inspection | JOHN KITCKO |
| Insulation | 11/30/2023 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 11/30/2023 | Not Ready for Inspection | JOHN KITCKO |
| Insulation | 12/20/2023 | Partial Approval | JOHN KITCKO |
| Interior/Exterior Lathing | 1/24/2024 | Not Ready for Inspection | JOHN KITCKO |
| Interior/Exterior Lathing | 1/30/2024 | Approved | JOHN KITCKO |
| Deputy Wood Construction | 2/21/2024 | Approved | JOHN KITCKO |
| Interior/Exterior Lathing | 3/13/2024 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Rough | 4/24/2024 | Partial Inspection | JOHN KITCKO |
| Wood Frame | 4/24/2024 | Not Ready for Inspection | JOHN KITCKO |
| Pre-Inspection | 7/23/2024 | No Access for Inspection | JOHN KITCKO |
| Insulation | 8/19/2024 | Not Ready for Inspection | JOHN KITCKO |
| Insulation | 8/22/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 8/27/2024 | Partial Approval | KENNETH ROBERTS |
| Drywall Nailing | 8/30/2024 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 9/6/2024 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 9/10/2024 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 9/10/2024 | Partial Inspection | JOHN KITCKO |
| Green Building Rough | 9/20/2024 | Partial Approval | JOHN KITCKO |
| Wood Frame | 9/20/2024 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 9/24/2024 | Partial Approval | JOHN KITCKO |
| Wood Frame | 9/24/2024 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 9/26/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 9/26/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Insulation | 9/30/2024 | Partial Approval | JOHN KITCKO |
| Insulation | 10/2/2024 | Approved | JOHN KITCKO |
| Drywall Nailing | 10/8/2024 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 10/22/2024 | Partial Inspection | JOHN KITCKO |
| Drywall Nailing | 10/24/2024 | Partial Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 10/31/2024 | Partial Approval | JOHN KITCKO |
| Interior/Exterior Lathing | 11/19/2024 | Not Ready for Inspection | JOHN KITCKO |
| Interior/Exterior Lathing | 12/3/2024 | Corrections Issued | ROBERT DAVIS |
| Interior/Exterior Lathing | 12/10/2024 | Partial Approval | JOHN KITCKO |
| Interior/Exterior Lathing | 12/13/2024 | Partial Approval | JOHN KITCKO |
| Final | 2/11/2025 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 2/11/2025 | Approved | JOHN KITCKO |
| Green Building Final | 2/11/2025 | Partial Inspection | JOHN KITCKO |
| Green Building Rough | 2/11/2025 | Approved | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 2/11/2025 | SGSOV Not Ready | JOHN KITCKO |
| Smoke Detectors | 2/11/2025 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 2/11/2025 | Approved | JOHN KITCKO |
| Final | 3/18/2025 | Partial Inspection | JOHN KITCKO |
| Green Building Final | 3/18/2025 | Approved | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 3/18/2025 | SGSOV Not Ready | JOHN KITCKO |
| Smoke Detectors | 3/18/2025 | Not Ready for Inspection | JOHN KITCKO |
| Final | 4/3/2025 | Partial Inspection | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 4/3/2025 | SGSOV Not Ready | JOHN KITCKO |
| Smoke Detectors | 4/3/2025 | Not Ready for Inspection | JOHN KITCKO |
| Final | 6/9/2025 | Partial Inspection | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 6/9/2025 | SGSOV Not Ready | JOHN KITCKO |
| Smoke Detectors | 6/9/2025 | Not Ready for Inspection | JOHN KITCKO |
| Final | 7/21/2025 | Not Ready for Inspection | JOHN KITCKO |
| Final | 7/24/2025 | OK to Issue CofO | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 7/24/2025 | SGSOV Approved | JOHN KITCKO |
| Smoke Detectors | 7/24/2025 | Approved | JOHN KITCKO |