7331 N KELVIN AVE 91306

Certificate Information: 7331 N KELVIN AVE 91306

Application / Permit
20010-20000-03317
Plan Check / Job No.
B20VN12462
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT) [Small lot subdivision pursuant to Preliminary Parcel Map No. AA-2018-4978-PMLA-SL. A certificate of occupancy (temporary or final) shall not be issue until after the final map has been recorded]
Permit Issued
Issued on 7/13/2022
Issuing Office
Current Status
Issued on 7/13/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/27/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 NILOOFAR MEHRAIN
Corrections Issued 11/6/2020 NILOOFAR MEHRAIN
Quality Review Completed 11/9/2020 CHON CHIO KUO
Building Plans Picked Up 11/10/2020 APPLICANT
Applicant returned to address corrections 2/16/2021 NILOOFAR MEHRAIN
Plan Check Approved 3/31/2022 NILOOFAR MEHRAIN
Issued 7/13/2022 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 1/19/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/2/2021 LEE GUILBEAUX
Hydrant and Access approval Cleared 4/28/2021 MATTHEW CRAIG
APC Cleared 10/13/2021 MIGUEL GAMBOA
Miscellaneous Cleared 10/13/2021 MIGUEL GAMBOA
Tract Map conditions Cleared 10/13/2021 MIGUEL GAMBOA
Low Impact Development Cleared 12/7/2021 TA ANH
Roof/Waste drainage to street Cleared 12/22/2021 LEE GUILBEAUX
Miscellaneous Cleared 3/14/2022 LEE GUILBEAUX
Permit Cleared 3/14/2022 LEE GUILBEAUX
Address approval Cleared 3/29/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307

Inspector Information

HENRY KIM, (818) 774-4334 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/21/2023 Corrections Issued JEFFREY PARD
Pre-Inspection 6/21/2023 Approved JEFFREY PARD
PLUMBING-Rough 6/26/2023 Partial Approval JEFFREY PARD
Excavation/Setback/Form/Re-Bar 7/10/2023 Approved JEFFREY PARD
Footing/Foundation/Slab 7/21/2023 Corrections Issued HENRY KIM
Excavation/Setback/Form/Re-Bar 7/24/2023 Approved JEFFREY PARD
Deputy Steel/Welding 8/2/2023 Approved JEFFREY PARD
Footing/Foundation/Slab 8/2/2023 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Approved JEFFREY PARD
Deputy Wood Construction 9/25/2023 Conditional Approval HENRY KIM
Wood Frame 10/3/2023 Approved JEFFREY PARD
ELECTRICAL-Rough 10/23/2023 Approved JEFFREY PARD
BUILDING-Rough-Frame 11/16/2023 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 11/16/2023 Not Ready for Inspection JEFFREY PARD
Green Building Rough 11/16/2023 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 11/16/2023 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 11/16/2023 Not Ready for Inspection JEFFREY PARD
Verify Sprinkler Sign Off 11/16/2023 Not Ready for Inspection JEFFREY PARD
Wood Frame 11/21/2023 Approved JEFFREY PARD
BUILDING-Rough-Frame 11/27/2023 Not Ready for Inspection JEFFREY PARD
Green Building Rough 11/27/2023 Not Ready for Inspection JEFFREY PARD
Verify Sprinkler Sign Off 11/27/2023 Not Ready for Inspection JEFFREY PARD
Wood Frame 12/1/2023 Approved JEFFREY PARD
PLUMBING-Rough 12/12/2023 Corrections Issued JEFFREY PARD
Wood Frame 12/12/2023 Not Ready for Inspection JEFFREY PARD
Rough-Elec/Plmb/HVAC 12/14/2023 Approved JEFFREY PARD
Wood Frame 12/22/2023 Approved JEFFREY PARD
HVAC-Rough 12/29/2023 Approved JEFFREY PARD
Interior/Exterior Lathing 1/5/2024 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 1/9/2024 Approved JEFFREY PARD
Insulation 2/12/2024 Approved JEFFREY PARD
Drywall Nailing 3/5/2024 Approved JEFFREY PARD
Interior/Exterior Lathing 4/9/2024 Approved JEFFREY PARD
Sewer 12/23/2024 Corrections Issued JEFFREY PARD
PLUMBING-Rough 2/25/2025 Partial Approval JEFFREY PARD
Gas Test 6/12/2025 Approved JEFFREY PARD
PLUMBING-Final 1/8/2026 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Final 3/11/2026 Not Ready for Inspection JEFFREY PARD
Service/Power Release 3/11/2026 Approved JEFFREY PARD
ELECTRICAL-Final 3/13/2026 Approved JEFFREY PARD
PLUMBING-Final 3/13/2026 Approved JEFFREY PARD