8536 N NOBLE AVE 91343

Certificate Information: 8536 N NOBLE AVE 91343

Application / Permit
20010-20000-03315
Plan Check / Job No.
B20VN12456
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 48' X 25' ACCESSORY DWELLING UNIT PER LAMC 12.33 A.33(c) AND (d). WORK PER ENGINEER.
Permit Issued
Issued on 7/23/2021
Issuing Office
Current Status
CofO Issued on 3/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2020 APPLICANT
Assigned to Plan Check Engineer 10/20/2020 ROSENDO MEDINA
Corrections Issued 10/20/2020 ROSENDO MEDINA
Applicant returned to address corrections 5/14/2021 ROSENDO MEDINA
Plan Check Approved 6/22/2021 ROSENDO MEDINA
Building Plans Picked Up 6/25/2021 APPLICANT
Issued 7/23/2021 APPLICANT
CofO in Progress 3/9/2023 CHRISTOPHER DELLEFIELD
CofO Issued 3/15/2023 MICHAEL SMITH
Permit Finaled 3/15/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/2/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/25/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/30/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 12/8/2020 MATTHEW CRAIG
Construction near power lines Cleared 4/5/2021 RIDWAN HARDY
Low Impact Development Cleared 4/8/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 4/13/2021 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Sin,, John P; Lic. No.: C91162 122 N GRAMERCY PL      LOS ANGELES, CA 90004

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/24/2022 Partial Approval GREGG CUMMINGS
Footing/Foundation/Slab 4/5/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/26/2022 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 5/4/2022 Corrections Issued GREGG CUMMINGS
HVAC-Rough 5/4/2022 Corrections Issued GREGG CUMMINGS
BUILDING-Rough-Frame 5/6/2022 Corrections Issued GREGG CUMMINGS
HVAC-Rough 5/6/2022 Approved GREGG CUMMINGS
PLUMBING-Rough 5/6/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 5/10/2022 Not Ready for Inspection GREGG CUMMINGS
Green Building Rough 5/10/2022 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 5/10/2022 Not Ready for Inspection GREGG CUMMINGS
Verify Sprinkler Sign Off 5/10/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 5/12/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 5/12/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/12/2022 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 5/12/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/12/2022 Corrections Issued JENNIFER RABUCHIN
Sewer 5/12/2022 Approved JENNIFER RABUCHIN
Underground Mechanical 5/12/2022 Partial Approval JENNIFER RABUCHIN
Verify Sprinkler Sign Off 5/12/2022 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 5/16/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/18/2022 Approved WILLIAM WREN
Shower Pan 5/18/2022 Approved WILLIAM WREN
Insulation 5/23/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/23/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 6/3/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 11/9/2022 No Access for Inspection GREGG CUMMINGS
Final 11/9/2022 No Access for Inspection GREGG CUMMINGS
Green Building Final 11/9/2022 No Access for Inspection GREGG CUMMINGS
Green Building Rough 11/9/2022 No Access for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Not Ready GREGG CUMMINGS
Service/Power Release 11/9/2022 No Access for Inspection GREGG CUMMINGS
Smoke Detectors 11/9/2022 No Access for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 1/24/2023 SGSOV Not Ready CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 1/25/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 1/25/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Final 1/25/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 1/25/2023 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 1/25/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 1/25/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 1/25/2023 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Approved CHRISTOPHER DELLEFIELD
Service/Power Release 1/25/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 1/25/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 2/1/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 2/1/2023 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Final 2/1/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Final 2/1/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 2/15/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Final 2/15/2023 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Final 2/15/2023 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 2/15/2023 Approved CHRISTOPHER DELLEFIELD
Service/Power Release 2/15/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 2/28/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Final 2/28/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Service/Power Release 2/28/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 3/3/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Service/Power Release 3/3/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 3/9/2023 OK to Issue CofO CHRISTOPHER DELLEFIELD
Service/Power Release 3/9/2023 Approved CHRISTOPHER DELLEFIELD