8536 N NOBLE AVE 91343
Certificate Information: 8536 N NOBLE AVE 91343
- Application / Permit
- 20010-20000-03315
- Plan Check / Job No.
- B20VN12456
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 48' X 25' ACCESSORY DWELLING UNIT PER LAMC 12.33 A.33(c) AND (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 7/23/2021
- Issuing Office
- Current Status
- CofO Issued on 3/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2020 | ROSENDO MEDINA |
| Corrections Issued | 10/20/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 5/14/2021 | ROSENDO MEDINA |
| Plan Check Approved | 6/22/2021 | ROSENDO MEDINA |
| Building Plans Picked Up | 6/25/2021 | APPLICANT |
| Issued | 7/23/2021 | APPLICANT |
| CofO in Progress | 3/9/2023 | CHRISTOPHER DELLEFIELD |
| CofO Issued | 3/15/2023 | MICHAEL SMITH |
| Permit Finaled | 3/15/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/2/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 11/30/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 12/8/2020 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 4/5/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 4/8/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 4/13/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sin,, John P; Lic. No.: C91162 | 122 N GRAMERCY PL LOS ANGELES, CA 90004 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/24/2022 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2022 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/4/2022 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 5/4/2022 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/6/2022 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 5/6/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 5/6/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/10/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 5/10/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 5/10/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 5/10/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/12/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/12/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 5/12/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/12/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 5/12/2022 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 5/12/2022 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 5/12/2022 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 5/16/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/18/2022 | Approved | WILLIAM WREN |
| Shower Pan | 5/18/2022 | Approved | WILLIAM WREN |
| Insulation | 5/23/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/3/2022 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 11/9/2022 | No Access for Inspection | GREGG CUMMINGS |
| Final | 11/9/2022 | No Access for Inspection | GREGG CUMMINGS |
| Green Building Final | 11/9/2022 | No Access for Inspection | GREGG CUMMINGS |
| Green Building Rough | 11/9/2022 | No Access for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 11/9/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 11/9/2022 | No Access for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 11/9/2022 | No Access for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 1/25/2023 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 1/25/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 1/25/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 1/25/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 1/25/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 1/25/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 1/25/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 1/25/2023 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 1/25/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 1/25/2023 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 2/1/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 2/1/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 2/1/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 2/1/2023 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 2/15/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 2/15/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 2/15/2023 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 2/15/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 2/15/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 2/28/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 2/28/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 2/28/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 3/3/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 3/3/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 3/9/2023 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 3/9/2023 | Approved | CHRISTOPHER DELLEFIELD |