129 S BURLINGAME AVE 90049

Certificate Information: 129 S BURLINGAME AVE 90049

Application / Permit
20010-20000-03314
Plan Check / Job No.
B20VN12444
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)¹, (d)¹, and (g) FIRE SPRINKLERES NFPA 13D
Permit Issued
Issued on 7/19/2021
Issuing Office
Current Status
CofO Issued on 8/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/22/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 MOHAMMAD ESMAILI
Corrections Issued 10/22/2020 MOHAMMAD ESMAILI
Quality Review Completed 11/9/2020 OMID HEDAYAT
Building Plans Picked Up 11/10/2020 APPLICANT
Applicant returned to address corrections 3/1/2021 MOHAMMAD ESMAILI
Plan Check Approved 7/19/2021 MOHAMMAD ESMAILI
Issued 7/19/2021 APPLICANT
CofO in Progress 5/26/2022 JOHN KIDWELL
Permit Finaled 8/2/2022 DANIEL ORRANTE
CofO Issued 8/2/2022 DANIEL ORRANTE
Permit Finaled 8/2/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 11/19/2020 NOAH MCCOY
ZI Cleared 11/19/2020 NOAH MCCOY
Address approval Cleared 12/9/2020 NIKTA MOUSAVI
Eng Process Fee Ord 176,300 Cleared 12/16/2020 NIKTA MOUSAVI
Hydrant and Access approval Cleared 12/16/2020 MATTHEW CRAIG
Sewer availability Cleared 12/18/2020 NIKTA MOUSAVI
Low Impact Development Cleared 1/15/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/19/2021 NIKTA MOUSAVI
GPI Written Notices Cleared 3/8/2021 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 3/8/2021 MOHAMMAD ESMAILI
Miscellaneous Cleared 7/12/2021 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Durand,, Paul Henri; Lic. No.: S4222 611 N G ST      OXNARD, CA 93030
Engineer Tan,, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/30/2021 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/6/2021 Conditional Approval JOHN KIDWELL
Wood Frame 8/24/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 8/30/2021 Approved JOHN KIDWELL
HVAC-Rough 8/30/2021 Approved JOHN KIDWELL
PLUMBING-Rough 8/30/2021 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 9/8/2021 Approved CARLOS MATAMOROS
HVAC-Rough 9/8/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 9/8/2021 Approved CARLOS MATAMOROS
Wood Frame 9/8/2021 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 9/14/2021 Approved JUAN VALENZUELA
Green Building Rough 9/14/2021 Approved JUAN VALENZUELA
Insulation 9/14/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 9/14/2021 Partial Approval JUAN VALENZUELA
Verify Sprinkler Sign Off 9/14/2021 Approved JUAN VALENZUELA
Drywall Nailing 5/2/2022 Approved JOHN KIDWELL
ELECTRICAL-Final 5/3/2022 Not Ready for Inspection JUAN VALENZUELA
Final 5/3/2022 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 5/3/2022 Not Ready for Inspection JUAN VALENZUELA
Green Building Final 5/3/2022 Not Ready for Inspection JUAN VALENZUELA
HVAC-Final 5/3/2022 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Final 5/3/2022 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 5/3/2022 SGSOV Not Ready JUAN VALENZUELA
Service/Power Release 5/3/2022 Not Ready for Inspection JUAN VALENZUELA
Smoke Detectors 5/3/2022 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 5/11/2022 Approved JOHN KIDWELL
Final 5/11/2022 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 5/11/2022 Approved JOHN KIDWELL
Green Building Final 5/11/2022 Approved JOHN KIDWELL
HVAC-Final 5/11/2022 Approved JOHN KIDWELL
PLUMBING-Final 5/11/2022 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/11/2022 SGSOV Approved JOHN KIDWELL
Smoke Detectors 5/11/2022 Approved JOHN KIDWELL
Final 5/25/2022 OK to Issue CofO JOHN KIDWELL