1728 S SHENANDOAH ST 90035
Certificate Information: 1728 S SHENANDOAH ST 90035
- Application / Permit
- 20010-20000-03309
- Plan Check / Job No.
- B20VN12424
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY, IRREGULAR SHAPED SINGLE FAMILY DWELLING W/ATTACHED GARAGE. NFPA 13-D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/5/2021
- Issuing Office
- Current Status
- CofO Issued on 12/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | COLIN LOREDO |
| Corrections Issued | 10/20/2020 | COLIN LOREDO |
| Quality Review Completed | 11/16/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 11/18/2020 | APPLICANT |
| Applicant returned to address corrections | 3/4/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 4/20/2021 | COLIN LOREDO |
| Plan Check Approved | 5/4/2021 | COLIN LOREDO |
| Issued | 5/5/2021 | APPLICANT |
| Refund in Progress | 5/10/2022 | TERENCE SHIA |
| Refund Denied | 6/22/2022 | JOYCE TAN |
| Issued | 6/22/2022 | JOYCE TAN |
| CofO in Progress | 11/27/2023 | MICHAEL PELHAM |
| Permit Finaled | 12/6/2023 | DANIEL ORRANTE |
| CofO Issued | 12/8/2023 | KENNETH NAGLE |
| Permit Finaled | 12/8/2023 | KENNETH NAGLE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2020 | JUAN ASHTON |
| Address approval | Cleared | 12/2/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 12/4/2020 | JUAN ASHTON |
| Hydrant and Access approval | Cleared | 1/18/2021 | ROBERT DUFF |
| Trees in Parkway | Cleared | 3/3/2021 | JOHN KIM |
| Low Impact Development | Cleared | 4/9/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 4/12/2021 | JEANIE LAM |
| Permit | Cleared | 4/27/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | M & D Development & Construction Inc; Lic. No.: 736716-B | 1617 S SHERBOURNE DRIVE LOS ANGELES, CA 90035 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/13/2021 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 6/14/2021 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 7/14/2021 | Corrections Issued | EVAN COOPER |
| METHANE-Barrier | 7/14/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 7/14/2021 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 7/23/2021 | Corrections Issued | KEVIN SARGSYAN |
| METHANE-Barrier | 7/23/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 7/23/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/27/2021 | Corrections Issued | KENNETH NAGLE |
| METHANE-Barrier | 7/27/2021 | Not Ready for Inspection | KENNETH NAGLE |
| METHANE-Subgrade | 7/27/2021 | Not Ready for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 8/12/2021 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 8/12/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 8/12/2021 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 8/24/2021 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 8/31/2021 | Corrections Issued | EVAN COOPER |
| METHANE-Barrier | 8/31/2021 | Approved | EVAN COOPER |
| METHANE-Subgrade | 8/31/2021 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 9/10/2021 | Approved | EVAN COOPER |
| Deputy Steel/Welding | 10/15/2021 | Conditional Approval | EVAN COOPER |
| Deputy Steel/Welding | 11/2/2021 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2021 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 11/18/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2021 | Corrections Issued | EVAN COOPER |
| HVAC-Rough | 1/20/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 1/20/2022 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 2/2/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 2/8/2022 | Approved | EVAN COOPER |
| Deputy Wood Construction | 2/9/2022 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2022 | Partial Approval | EVAN COOPER |
| Green Building Rough | 2/18/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 2/18/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 3/30/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/4/2022 | Approved | EVAN COOPER |
| Green Building Rough | 4/4/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 4/4/2022 | Partial Approval | EVAN COOPER |
| METHANE-Rough | 4/4/2022 | Approved | EVAN COOPER |
| Shower Pan | 4/4/2022 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 4/4/2022 | Approved | EVAN COOPER |
| Insulation | 4/8/2022 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 4/13/2022 | Not Ready for Inspection | EVAN COOPER |
| Insulation | 4/13/2022 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 4/13/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 4/25/2022 | Approved | STEPHANIE SWANSON |
| Insulation | 4/25/2022 | Approved | STEPHANIE SWANSON |
| Underground Mechanical | 7/7/2022 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Final | 10/24/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 10/24/2022 | Approved | EVAN COOPER |
| Service/Power Release | 10/24/2022 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 10/27/2022 | Approved | EVAN COOPER |
| Service/Power Release | 11/21/2022 | Approved | MICHAEL PELHAM |
| Final | 11/23/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 11/23/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 11/23/2022 | Approved | OGANES TARAKHCHYAN |
| Structural Steel Frame | 11/23/2022 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 11/29/2022 | Approved | EVAN COOPER |
| Special/Order Compliance | 11/29/2022 | Partial Inspection | JEREMY TODD |
| Final | 11/27/2023 | OK to Issue CofO | MICHAEL PELHAM |
| Green Building Final | 11/27/2023 | Approved | MICHAEL PELHAM |