1426 S GLENDON AVE 90024

Certificate Information: 1426 S GLENDON AVE 90024

Application / Permit
20010-20000-03308
Plan Check / Job No.
B20VN12401
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT (512 SQ FT) PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g) WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 11/29/2023
Issuing Office
Valley
Current Status
CofO Issued on 1/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 SELLA BENYAMIN
Corrections Issued 10/19/2020 SELLA BENYAMIN
Quality Review Completed 10/23/2020 STEVEN KIM
Building Plans Picked Up 10/26/2020 APPLICANT
Applicant returned to address corrections 4/26/2022 SELLA BENYAMIN
Plan Check Approved 8/22/2023 SELLA BENYAMIN
Issued 11/29/2023 APPLICANT
CofO in Progress 12/31/2025 MICHAEL ALLEN
Permit Finaled 1/2/2026 RICHARD STEINBACH
CofO Issued 1/2/2026 RICHARD STEINBACH
Permit Finaled 1/2/2026 RICHARD STEINBACH

Permit Application Clearance Information

Construction near power lines Cleared 3/18/2021 RIDWAN HARDY
Address approval Cleared 7/25/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 7/28/2021 ANTHONY MAINEZ
Sewer availability Cleared 7/28/2021 ANTHONY MAINEZ
Low Impact Development Cleared 2/4/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 2/25/2022 STEVEN JIN
Hydrant and Access approval Cleared 5/18/2023 JOHN CONNEALLY

Contact Information

Contractor E H D Builders Inc; Lic. No.: 1034101-B 18375 VENTURA BLVD STE #122      TARZANA, CA 91356
Engineer Simonian,, Ara; Lic. No.: C37208 314 E BROADWAY STE A      GLENDALE, CA 91205

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/19/2024 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 5/14/2024 No Access for Inspection SEAN HAUPT
Excavation/Setback/Form/Re-Bar 7/5/2024 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 7/5/2024 Corrections Issued MEL KHACHATOURIAN
METHANE-Barrier 7/5/2024 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Subgrade 7/5/2024 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 7/9/2024 Partial Approval KIRK SANDERS
Piling/Pier/Caisson 7/9/2024 Not Ready for Inspection KIRK SANDERS
Footing/Foundation/Slab 7/16/2024 Partial Approval KIRK SANDERS
METHANE-Barrier 7/16/2024 Not Ready for Inspection KIRK SANDERS
METHANE-Subgrade 7/16/2024 Not Ready for Inspection KIRK SANDERS
Excavation/Setback/Form/Re-Bar 8/14/2024 Approved KIRK SANDERS
Footing/Foundation/Slab 8/14/2024 Approved KIRK SANDERS
METHANE-Barrier 8/14/2024 Approved KIRK SANDERS
METHANE-Subgrade 8/14/2024 Approved KIRK SANDERS
Pre-Inspection 8/14/2024 Not Ready for Inspection KIRK SANDERS
Underground Mechanical 8/14/2024 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 8/26/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Conditional Approval KIRK SANDERS
BUILDING-Rough-Frame 9/9/2024 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 9/9/2024 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 9/9/2024 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 9/9/2024 Not Ready for Inspection JESUS RODRIGUEZ
Sewer 9/11/2024 Approved ARAM AVEDISIAN
Underground Mechanical 9/11/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 9/23/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/23/2024 Corrections Issued KIRK SANDERS
Green Building Rough 9/23/2024 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 9/23/2024 Corrections Issued KIRK SANDERS
METHANE-Rough 9/23/2024 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 9/23/2024 Corrections Issued KIRK SANDERS
Verify Sprinkler Sign Off 9/23/2024 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 10/8/2024 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 10/8/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Corrections Issued KIRK SANDERS
Green Building Rough 10/8/2024 Not Ready for Inspection KIRK SANDERS
METHANE-Rough 10/8/2024 Not Ready for Inspection KIRK SANDERS
Verify Sprinkler Sign Off 10/8/2024 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 10/10/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 10/10/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 10/10/2024 Conditional Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Conditional Approval KIRK SANDERS
Green Building Rough 10/10/2024 Not Ready for Inspection KIRK SANDERS
HVAC-Final 10/10/2024 Corrections Issued KIRK SANDERS
HVAC-Rough 10/10/2024 Conditional Approval KIRK SANDERS
METHANE-Rough 10/10/2024 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 10/10/2024 Corrections Issued KIRK SANDERS
Verify Sprinkler Sign Off 10/10/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 10/21/2024 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 10/23/2024 No Access for Inspection KIRK SANDERS
Green Building Rough 10/23/2024 No Access for Inspection KIRK SANDERS
Interior/Exterior Lathing 10/23/2024 Partial Approval KIRK SANDERS
METHANE-Rough 10/23/2024 No Access for Inspection KIRK SANDERS
PLUMBING-Rough 10/23/2024 No Access for Inspection KIRK SANDERS
Wood Frame 10/23/2024 No Access for Inspection KIRK SANDERS
BUILDING-Rough-Frame 10/25/2024 Partial Approval KIRK SANDERS
Green Building Rough 10/25/2024 Approved KIRK SANDERS
METHANE-Rough 10/25/2024 Approved KIRK SANDERS
PLUMBING-Rough 10/25/2024 Approved KIRK SANDERS
Wood Frame 10/25/2024 Partial Approval KIRK SANDERS
Insulation 10/31/2024 Corrections Issued KIRK SANDERS
Insulation 11/4/2024 Corrections Issued TEMISTOCLES CAAL
Insulation 11/6/2024 Approved KIRK SANDERS
Drywall Nailing 11/13/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 11/13/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 7/17/2025 No Access for Inspection MICHAEL PELHAM
Deputy Drilled-In Anchors 7/17/2025 Conditional Approval MICHAEL PELHAM
Final 7/17/2025 No Access for Inspection MICHAEL PELHAM
Green Building Final 7/17/2025 No Access for Inspection MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 7/17/2025 SGSOV Not Ready MICHAEL PELHAM
Service/Power Release 7/17/2025 No Access for Inspection MICHAEL PELHAM
Smoke Detectors 7/17/2025 No Access for Inspection MICHAEL PELHAM
BUILDING-Rough-Frame 7/22/2025 Approved BOBBY KEY
ELECTRICAL-Final 7/22/2025 Corrections Issued BOBBY KEY
Final 7/22/2025 Corrections Issued BOBBY KEY
Green Building Final 7/22/2025 Approved BOBBY KEY
HVAC-Final 7/22/2025 Corrections Issued BOBBY KEY
PLUMBING-Final 7/22/2025 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 7/22/2025 SGSOV Approved BOBBY KEY
Smoke Detectors 7/22/2025 Approved BOBBY KEY
Final 11/3/2025 Corrections Issued MICHAEL ALLEN
HVAC-Final 11/3/2025 Approved MICHAEL ALLEN
Service/Power Release 11/3/2025 Not Ready for Inspection MICHAEL ALLEN
Final 11/6/2025 Corrections Issued MICHAEL ALLEN
Service/Power Release 11/6/2025 Not Ready for Inspection MICHAEL ALLEN
ELECTRICAL-Final 12/30/2025 Approved MICHAEL ALLEN
Final 12/30/2025 OK to Issue CofO MICHAEL ALLEN
PLUMBING-Final 12/30/2025 Approved MICHAEL ALLEN
Service/Power Release 12/30/2025 Approved MICHAEL ALLEN