21631 W HEATHERLEE LANE 91311
Certificate Information: 21631 W HEATHERLEE LANE 91311
- Application / Permit
- 20010-20000-03295
- Plan Check / Job No.
- B20VN12340
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW 20'-0" X 37'-0" FULLY SPRINKLERED DETACHED ACCESSORY LIVING QUARTERS PER ENGINEER
- Permit Issued
- Issued on 1/29/2021
- Issuing Office
- Current Status
- Issued on 1/29/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 9/27/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 1/28/2021 | JEROME MAGAT PALMA |
| Issued | 1/29/2021 | APPLICANT |
Permit Application Clearance Information
| Tract Map conditions | Cleared | 10/22/2020 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 10/30/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 12/15/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 12/24/2020 | ADRIAN CASTRO |
| Private sewage disp. approval | Cleared | 1/14/2021 | PATRICK MISCHLICH |
| GPI Written Notices | Cleared | 1/28/2021 | JEROME MAGAT PALMA |
| Grading Pre-Inspection | Cleared | 1/28/2021 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/3/2021 | Approved | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 2/8/2021 | Partial Approval | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 2/11/2021 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 3/1/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2021 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 3/31/2021 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 3/31/2021 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 3/31/2021 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 5/10/2021 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2021 | Approved | DAVID SCANTLIN |
| Insulation | 5/10/2021 | Approved | DAVID SCANTLIN |
| Green Building Final | 11/19/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Shower Pan | 11/19/2021 | Approved | DAVID SCANTLIN |
| Smoke Detectors | 11/19/2021 | Approved | DAVID SCANTLIN |