5444 N MURIETTA AVE 91401

Certificate Information: 5444 N MURIETTA AVE 91401

Application / Permit
20010-20000-03271
Plan Check / Job No.
B20VN12254
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1-STORY SFD/GARAGE
Permit Issued
Issued on 4/30/2021
Issuing Office
Current Status
CofO Issued on 8/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 CHON CHIO KUO
Corrections Issued 9/28/2020 CHON CHIO KUO
Quality Review Completed 10/1/2020 STEVEN KIM
Building Plans Picked Up 10/1/2020 APPLICANT
Applicant returned to address corrections 4/20/2021 CHON CHIO KUO
Plan Check Approved 4/28/2021 CHON CHIO KUO
Issued 4/30/2021 APPLICANT
CofO in Progress 8/19/2022 JENNIFER RABUCHIN
CofO Issued 8/19/2022 MICHAEL SMITH
Permit Finaled 8/19/2022 MICHAEL SMITH

Permit Application Clearance Information

Permit Cleared 10/23/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/27/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 12/7/2020 MATTHEW CRAIG
Low Impact Development Cleared 4/1/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 4/5/2021 ADRIAN CASTRO
Sewer availability Cleared 4/5/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/24/2021 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 7/7/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 8/23/2021 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/14/2021 No Access for Inspection RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 9/29/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 11/4/2021 Not Ready for Inspection RICHARD DOCKUS
Green Building Rough 11/4/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 11/4/2021 Approved RICHARD DOCKUS
Verify Sprinkler Sign Off 11/4/2021 Not Ready for Inspection RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Approved RICHARD DOCKUS
HVAC-Rough 11/8/2021 Not Ready for Inspection RICHARD DOCKUS
Interior/Exterior Lathing 11/16/2021 Partial Approval ALAN MORELOS
BUILDING-Rough-Frame 11/29/2021 Corrections Issued MICHAEL TEMPLE
HVAC-Rough 11/29/2021 Corrections Issued MICHAEL TEMPLE
Shower Pan 11/29/2021 Approved MICHAEL TEMPLE
Verify Sprinkler Sign Off 11/29/2021 Approved MICHAEL TEMPLE
BUILDING-Rough-Frame 12/7/2021 Not Ready for Inspection RICHARD DOCKUS
HVAC-Rough 12/7/2021 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 12/10/2021 Approved RICHARD DOCKUS
HVAC-Rough 12/10/2021 Approved RICHARD DOCKUS
Insulation 12/10/2021 Approved RICHARD DOCKUS
Drywall Nailing 12/16/2021 Not Ready for Inspection MICHAEL TEMPLE
Interior/Exterior Lathing 12/16/2021 Partial Approval MICHAEL TEMPLE
Drywall Nailing 12/22/2021 Approved RICHARD DOCKUS
Green Building Final 8/8/2022 Approved RICHARD DOCKUS
PLUMBING-Final 8/8/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 8/8/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 8/8/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 8/12/2022 Approved JENNIFER RABUCHIN
HVAC-Final 8/12/2022 Approved JENNIFER RABUCHIN
Final 8/18/2022 OK to Issue CofO JENNIFER RABUCHIN
Service/Power Release 8/18/2022 Approved JENNIFER RABUCHIN