5308 N LENNOX AVE 91401
Certificate Information: 5308 N LENNOX AVE 91401
- Application / Permit
- 20010-20000-03246
- Plan Check / Job No.
- B20VN12217
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 13' X 19'-6" REC ROOM WITH 3/4 BATHROOM (POOL PERMIT UNDER 20047-10000-01622)
- Permit Issued
- Issued on 2/4/2021
- Issuing Office
- Current Status
- CofO Issued on 9/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | SELLA BENYAMIN |
| Corrections Issued | 9/29/2020 | SELLA BENYAMIN |
| Quality Review Completed | 10/1/2020 | STEVEN KIM |
| Building Plans Picked Up | 10/1/2020 | APPLICANT |
| Plan Check Approved | 2/4/2021 | MICHAEL PEREZ |
| Issued | 2/4/2021 | APPLICANT |
| CofO in Progress | 8/19/2021 | MICHAEL PELHAM |
| Permit Finaled | 9/2/2021 | MICHAEL SMITH |
| CofO Issued | 9/2/2021 | MICHAEL SMITH |
| Permit Finaled | 9/2/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/10/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 1/5/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2021 | Approved | JOHN HAYES |
| Pre-Inspection | 3/1/2021 | Corrections Issued | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2021 | Not Ready for Inspection | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/5/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 4/5/2021 | Corrections Issued | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Rough | 4/5/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| HVAC-Rough | 4/5/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| PLUMBING-Rough | 4/5/2021 | Approved | MICHAEL TEMPLE |
| Verify Sprinkler Sign Off | 4/5/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Shower Pan | 4/7/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 4/12/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/12/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/12/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 4/12/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/12/2021 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 4/12/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 4/16/2021 | Approved | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 4/16/2021 | Partial Approval | MICHAEL TEMPLE |
| Pre-Inspection | 5/26/2021 | Partial Inspection | MARK JOHNSON |
| ELECTRICAL-Final | 6/30/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| Green Building Final | 6/30/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| HVAC-Final | 6/30/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Final | 6/30/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 7/7/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| Final | 7/7/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| HVAC-Final | 7/7/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Final | 7/7/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/7/2021 | SGSOV Not Ready | ARTHUR SARGSYAN |
| Service/Power Release | 7/7/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| Smoke Detectors | 7/7/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 7/16/2021 | Approved | RICHARD DOCKUS |
| Green Building Final | 7/16/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 7/16/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 7/16/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 7/16/2021 | Approved | RICHARD DOCKUS |
| Final | 7/20/2021 | Corrections Issued | DAVID MATSON |
| HVAC-Final | 7/20/2021 | Corrections Issued | DAVID MATSON |
| Final | 7/26/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Final | 7/26/2021 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 7/26/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 8/19/2021 | OK to Issue CofO | MICHAEL PELHAM |
| Service/Power Release | 8/19/2021 | Approved | MICHAEL PELHAM |