20810 BUR OAK CIR 91326
Certificate Information: 20810 BUR OAK CIR 91326
- Application / Permit
- 20010-20000-03219
- Plan Check / Job No.
- B20VN12162
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (35) Condo-Single Family
- Work Description
- (N) 2-STORY SFD W/ ATTACHED GARAGE, STANDARD PLAN #646, PLAN TYPE 1A (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 1/7/2021
- Issuing Office
- Current Status
- CofO Issued on 9/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/22/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 10/22/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 10/27/2020 | APPLICANT |
| Applicant returned to address corrections | 12/12/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/14/2020 | NILOOFAR MEHRAIN |
| Issued | 1/7/2021 | APPLICANT |
| CofO in Progress | 9/14/2021 | SEAN WIRCH |
| Permit Finaled | 9/14/2021 | MICHAEL SMITH |
| CofO Issued | 9/14/2021 | MICHAEL SMITH |
| Permit Finaled | 9/14/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 11/13/2020 | AMMAR ELTAWIL |
| Address approval | Cleared | 11/16/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2020 | LEE GUILBEAUX |
| Permit | Cleared | 11/16/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 11/16/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/16/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 11/16/2020 | LEE GUILBEAUX |
| "T" removal | Cleared | 11/19/2020 | DENZEL HENDERSON |
| Miscellaneous | Cleared | 11/19/2020 | DENZEL HENDERSON |
| Specific Plan | Cleared | 11/19/2020 | DENZEL HENDERSON |
| Tract Map conditions | Cleared | 11/19/2020 | DENZEL HENDERSON |
| Tract Map conditions | Cleared | 11/19/2020 | DENZEL HENDERSON |
| Tract Map conditions | Cleared | 11/19/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 11/19/2020 | DENZEL HENDERSON |
| ZI | Cleared | 11/19/2020 | DENZEL HENDERSON |
| Grading Pre-Inspection | Cleared | 12/9/2020 | NILOOFAR MEHRAIN |
| GPI Written Notices | Cleared | 12/14/2020 | NILOOFAR MEHRAIN |
| Hydrant and Access approval | Cleared | 12/18/2020 | KURT CORRAL |
| ZA Case | Cleared | 12/21/2020 | DENZEL HENDERSON |
Contact Information
| Architect | Falese,, Debra Suzanne; Lic. No.: C24900 | 2943 PULLMAN SUITE A SANTA ANA, CA 92705 |
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
| Engineer | Christian,, Dale Alan; Lic. No.: S2705 | 1744 W KATELLA AVENUE SUITE 107 ORANGE, CA 92867 |
| Engineer | Hattar,, Basil Ibrahim; Lic. No.: GE2734 | 3525 PARK MEADOW CT PALMDALE, CA 93551 |
| Engineer | Nelson,, William Mc Kee; Lic. No.: S3417 | 5 DELLWOOD DOVE CANYON, CA 92679 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/8/2021 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 3/3/2021 | Approved | SEAN WIRCH |
| Sewer | 3/15/2021 | Not Ready for Inspection | SEAN WIRCH |
| Sewer | 3/17/2021 | Approved | SEAN WIRCH |
| Underground Mechanical | 3/24/2021 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2021 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2021 | Approved | SEAN WIRCH |
| Deputy Wood Construction | 5/13/2021 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2021 | Not Ready for Inspection | SEAN WIRCH |
| BUILDING-Rough-Frame | 5/27/2021 | Approved | SEAN WIRCH |
| ELECTRICAL-Rough | 5/27/2021 | Approved | SEAN WIRCH |
| Green Building Rough | 5/27/2021 | Approved | SEAN WIRCH |
| HVAC-Rough | 5/27/2021 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 5/27/2021 | Approved | SEAN WIRCH |
| Verify Sprinkler Sign Off | 5/27/2021 | Approved | SEAN WIRCH |
| Drywall Nailing | 6/9/2021 | No Access for Inspection | SEAN WIRCH |
| Interior/Exterior Lathing | 6/14/2021 | Partial Approval | SEAN WIRCH |
| Interior/Exterior Lathing | 7/14/2021 | Approved | SEAN WIRCH |
| Gas Test | 7/15/2021 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 7/22/2021 | SGSOV Approved | SEAN WIRCH |
| Service/Power Release | 7/23/2021 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 9/13/2021 | Approved | SEAN WIRCH |
| Final | 9/13/2021 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 9/13/2021 | Approved | SEAN WIRCH |
| HVAC-Final | 9/13/2021 | Approved | SEAN WIRCH |
| PLUMBING-Final | 9/13/2021 | Approved | SEAN WIRCH |
| Smoke Detectors | 9/13/2021 | Approved | SEAN WIRCH |