23299 W FRIAR ST 91367
Certificate Information: 23299 W FRIAR ST 91367
- Application / Permit
- 20010-20000-03193
- Plan Check / Job No.
- B20VN12094
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30' X 34'-10.75" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 09/03/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 1/15/2022
- Issuing Office
- Current Status
- CofO Issued on 2/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2020 | RAPHAEL ROSAS |
| Corrections Issued | 9/24/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/27/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/14/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 10/26/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/11/2021 | RAPHAEL ROSAS |
| Issued | 1/15/2022 | APPLICANT |
| Building Plans Picked Up | 1/19/2022 | APPLICANT |
| CofO in Progress | 2/1/2023 | ROBERT SUNSERI |
| Permit Finaled | 2/27/2023 | DAVID JAMES |
| CofO Issued | 2/27/2023 | DAVID JAMES |
| Permit Finaled | 2/27/2023 | DAVID JAMES |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 11/19/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 11/24/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 11/24/2020 | GABRIEL ROBLES |
| ZA Case | Cleared | 3/3/2021 | LAUREN PADICK |
| ZA Case | Cleared | 3/3/2021 | LAUREN PADICK |
| Low Impact Development | Cleared | 5/11/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 7/20/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Liam & Adam Associates Inc; Lic. No.: 1052079-B | 20024 CHASE ST WINNETKA, CA 91306 |
| Engineer | Vasquez,, Mario Alberto; Lic. No.: C89006 | 43023 40TH ST WEST LANCASTER, CA 93536 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/19/2022 | Corrections Issued | RICHARD SIMONS |
| Sewer | 1/19/2022 | Approved | RICHARD SIMONS |
| Underground Mechanical | 1/19/2022 | Approved | RICHARD SIMONS |
| Excavation/Setback/Form/Re-Bar | 1/21/2022 | Approved | RICHARD SIMONS |
| Footing/Foundation/Slab | 1/21/2022 | Approved | RICHARD SIMONS |
| Pre-Inspection | 1/21/2022 | Approved | RICHARD SIMONS |
| Underground Mechanical | 1/21/2022 | Approved | RICHARD SIMONS |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2022 | Approved | RICHARD SIMONS |
| Deputy Drilled-In Anchors | 2/15/2022 | Approved | RICHARD SIMONS |
| PLUMBING-Rough | 3/1/2022 | Corrections Issued | RICHARD SIMONS |
| Shower Pan | 3/8/2022 | Approved | RICHARD SIMONS |
| Interior/Exterior Lathing | 3/9/2022 | Conditional Approval | ROBERT SUNSERI |
| BUILDING-Rough-Frame | 6/7/2022 | Corrections Issued | RICHARD SIMONS |
| ELECTRICAL-Rough | 6/7/2022 | Corrections Issued | RICHARD SIMONS |
| Gas Test | 6/7/2022 | Approved | RICHARD SIMONS |
| Green Building Rough | 6/7/2022 | Approved | RICHARD SIMONS |
| HVAC-Rough | 6/7/2022 | Corrections Issued | RICHARD SIMONS |
| Interior/Exterior Lathing | 6/7/2022 | Approved | RICHARD SIMONS |
| PLUMBING-Rough | 6/7/2022 | Corrections Issued | RICHARD SIMONS |
| BUILDING-Rough-Frame | 6/13/2022 | Approved | EMIL ALEXANDRIAN |
| Insulation | 6/13/2022 | Approved | EMIL ALEXANDRIAN |
| Rough-Elec/Plmb/HVAC | 6/13/2022 | Approved | EMIL ALEXANDRIAN |
| Drywall Nailing | 6/15/2022 | Approved | RICHARD SIMONS |
| Service/Power Release | 7/25/2022 | Corrections Issued | EMIL ALEXANDRIAN |
| Final | 7/26/2022 | Corrections Issued | RICHARD SIMONS |
| Green Building Final | 7/26/2022 | Approved | RICHARD SIMONS |
| SGSOV-Seismic Gas S/O Valve | 7/26/2022 | SGSOV Not Ready | RICHARD SIMONS |
| Smoke Detectors | 7/26/2022 | Approved | RICHARD SIMONS |
| Final | 8/19/2022 | Corrections Issued | RICHARD SIMONS |
| SGSOV-Seismic Gas S/O Valve | 8/19/2022 | SGSOV Not Ready | RICHARD SIMONS |
| Service/Power Release | 8/19/2022 | Corrections Issued | RICHARD SIMONS |
| Final | 8/26/2022 | Not Ready for Inspection | ROBERT SUNSERI |
| SGSOV-Seismic Gas S/O Valve | 8/26/2022 | SGSOV Not Ready | ROBERT SUNSERI |
| Service/Power Release | 8/26/2022 | Corrections Issued | ROBERT SUNSERI |
| Final | 9/13/2022 | Conditional Approval | ROBERT SUNSERI |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Not Ready | ROBERT SUNSERI |
| Service/Power Release | 9/13/2022 | Approved | ROBERT SUNSERI |
| Final | 9/26/2022 | Conditional Approval | ROBERT SUNSERI |
| SGSOV-Seismic Gas S/O Valve | 9/26/2022 | SGSOV Approved | ROBERT SUNSERI |
| Service/Power Release | 9/26/2022 | Approved | ROBERT SUNSERI |